Chapter 6.1 — Foundation Engineering: Bearing Capacity

Foundation bearing capacity governs the structural adequacy of every load-transfer element in railroad infrastructure — bridge abutments and piers, signal equipment…
Authors: Daniel P. Colwell and Mario Ruel

Railroad Geotechnical Services Manual | Primary Source: USACE EM 1110-1-1804 All equations and parameters expressed in English (Imperial) units throughout.

Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database

Strength and stiffness values for preliminary bearing and settlement checks. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

Granular friction angle and cohesive effective strength (31 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Friction angleGravelsGW-SPVery loose / loose303234degLOOK T7.8, p.107
Friction angleGravelsGW-SPMedium dense3436.539degLOOK T7.8, p.107
Friction angleGravelsGW-SPDense3941.544degLOOK T7.8, p.107
Friction angleGravelsGW-SPVery dense4446.549degLOOK T7.8, p.107
Friction angleSandsGW-SPVery loose / loose2729.532degLOOK T7.8, p.107
Friction angleSandsGW-SPMedium dense3234.537degLOOK T7.8, p.107
Friction angleSandsGW-SPDense3739.542degLOOK T7.8, p.107
Friction angleSandsGW-SPVery dense4244.547degLOOK T7.8, p.107
Friction angleSandsGW-SPLoose, uniformly graded2728.530degLOOK T7.8, p.107
Friction angleSandsGW-SPLoose, well graded303132degLOOK T7.8, p.107
Friction angleSandsGW-SPDense, uniformly graded3738.540degLOOK T7.8, p.107
Friction angleSandsGW-SPDense, well graded404142degLOOK T7.8, p.107
Friction angleBroken rock (compacted)RockfillSoft sedimentary303540degLOOK T7.8, p.107
Friction angleBroken rock (compacted)RockfillHard sedimentary354045degLOOK T7.8, p.107
Friction angleBroken rock (compacted)RockfillMetamorphic354045degLOOK T7.8, p.107
Friction angleBroken rock (compacted)RockfillIgneous404550degLOOK T7.8, p.107
Friction angle from SPTClean medium sandSP / SWVery loose (N ≤ 4)28degLOOK T5.4, p.80
Friction angle from SPTClean medium sandSP / SWLoose (N = 4–10)282930degLOOK T5.4, p.80
Friction angle from SPTClean medium sandSP / SWMedium dense (N = 10–30)303540degLOOK T5.4, p.80
Friction angle from SPTClean medium sandSP / SWDense (N = 30–50)4042.545degLOOK T5.4, p.80
Friction angle from SPTClean medium sandSP / SWVery dense (N > 50)4547.550degLOOK T5.4, p.80
Effective cohesion (peak)Cohesive soilsCL-CH / OL-OHSoft – organic104156.5209psfLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHSoft – organic101520degLOOK T7.9, p.107
Effective cohesion (peak)Cohesive soilsCL-CH / OL-OHSoft – non-organic209313.5418psfLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHSoft – non-organic152025degLOOK T7.9, p.107
Effective cohesion (peak)Cohesive soilsCL-CH / OL-OHStiff4187311,044psfLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHStiff202530degLOOK T7.9, p.107
Effective cohesion (peak)Cohesive soilsCL-CH / OL-OHHard1,0441,5662,088psfLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHHard2527.530degLOOK T7.9, p.107
Peak strength, overconsolidated clay joint infillOverconsolidated claysCHPeakc ≈ 3,759 psf; φ = 12–18°LOOK T9.17, p.134
Residual strength, overconsolidated clayOverconsolidated claysCHResidual101316degLOOK T9.17, p.134
Open this set in the database ↗
Stiffness (73 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Young's modulus (drained)GravelGW-SPLoose522.1783.21,044ksfLOOK T11.7, p.152
Young's modulus (drained)GravelGW-SPMedium1,0441,5662,088ksfLOOK T11.7, p.152
Young's modulus (drained)GravelGW-SPDense2,0883,1334,177ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPVery loose104.4ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPLoose62.7135.8208.9ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPMedium dense167.1396.9626.6ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPDense522.1783.21,044ksfLOOK T11.7, p.152
Young's modulus (drained)Medium to coarse sandGW-SPVery dense835.41,4622,088ksfLOOK T11.7, p.152
Young's modulus (drained)Fine sandGW-SPLoose104.4156.7208.9ksfLOOK T11.7, p.152
Young's modulus (drained)Fine sandGW-SPMedium208.9365.5522.1ksfLOOK T11.7, p.152
Young's modulus (drained)Fine sandGW-SPDense522.1783.21,044ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)SiltML-CHSoft208.9ksfLOOK T11.7, p.152
Young's modulus, long term (drained)SiltML-CHSoft167.1ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)SiltML-CHStiff208.9313.3417.7ksfLOOK T11.7, p.152
Young's modulus, long term (drained)SiltML-CHStiff167.1240.2313.3ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)SiltML-CHHard417.7ksfLOOK T11.7, p.152
Young's modulus, long term (drained)SiltML-CHHard313.3ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHVery soft62.7ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHVery soft41.8ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHSoft41.894146.2ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHSoft20.962.7104.4ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHFirm104.4177.5250.6ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHFirm83.5125.3167.1ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHStiff208.9365.5522.1ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHStiff146.2281.9417.7ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHVery stiff417.77311,044ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHVery stiff313.3522.1731ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHHard835.41,2531,671ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHHard626.6939.81,253ksfLOOK T11.7, p.152
Small-strain shear modulusSoft clays57172287ksfGEC5 T30, p.181
Small-strain shear modulusFirm clays144432.5721ksfGEC5 T30, p.181
Small-strain shear modulusSilty sands5761,7292,882ksfGEC5 T30, p.181
Small-strain shear modulusDense sands and gravels1,4414,3237,205ksfGEC5 T30, p.181
Poisson's ratio, short termSands, gravels and other cohesionless soilsShort term0.3–LOOK T11.17, p.157
Poisson's ratio, long termSands, gravels and other cohesionless soilsLong term0.3–LOOK T11.17, p.157
Poisson's ratio, short termClay, low PI (<12%)Short term0.35–LOOK T11.17, p.157
Poisson's ratio, long termClay, low PI (<12%)Long term0.25–LOOK T11.17, p.157
Poisson's ratio, short termClay, medium PI (12–22%)Short term0.4–LOOK T11.17, p.157
Poisson's ratio, long termClay, medium PI (12–22%)Long term0.3–LOOK T11.17, p.157
Poisson's ratio, short termClay, high PI (22–32%)Short term0.45–LOOK T11.17, p.157
Poisson's ratio, long termClay, high PI (22–32%)Long term0.35–LOOK T11.17, p.157
Poisson's ratio, short termClay, extremely high PI (>32%)Short term0.45–LOOK T11.17, p.157
Poisson's ratio, long termClay, extremely high PI (>32%)Long term0.4–LOOK T11.17, p.157
Poisson's ratioCohesive soil (settlement analysis)CL-CH0.4–USACE para. 3-9c, p.47
Poisson's ratioSubgrade soils0.250.3250.4–LOOK T13.28, p.192
Poisson's ratioGranular pavement materialGW / GP0.35–LOOK T13.28, p.192
Poisson's ratioWeathered rock subgradeRock0.3–LOOK T13.28, p.192
Poisson's ratioUnweathered bedrock subgradeRock0.15–LOOK T13.28, p.192
Modulus of elasticitySoft clay365472ksfDASP T11.4, p.319
Modulus of elasticityHard clay122.4205.2288ksfDASP T11.4, p.319
Modulus of elasticityLoose sand216396576ksfDASP T11.4, p.319
Modulus of elasticityDense sand7201,0801,440ksfDASP T11.4, p.319
Poisson's ratioLoose sand0.20.30.4–DASP T11.5, p.320
Poisson's ratioMedium sand0.250.3250.4–DASP T11.5, p.320
Poisson's ratioDense sand0.30.3750.45–DASP T11.5, p.320
Poisson's ratioSilty sand0.20.30.4–DASP T11.5, p.320
Poisson's ratioSoft clay0.150.20.25–DASP T11.5, p.320
Poisson's ratioMedium clay0.20.350.5–DASP T11.5, p.320
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 0–4VIICRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 4–8VICRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 9–15VCRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 16–25IVCRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 26–40IIICRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN = 41–60IICRAIG T8.4, p.315
Compressibility grade (Burland & Burbidge)Normally consolidated sands and gravelsGW-SPN > 60ICRAIG T8.4, p.315
Coefficient of subgrade reaction (1-ft plate)Loose sand18.438.658.9pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Medium dense sand36.8165.8294.7pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Dense sand221340.8460.5pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Clayey sand110.5202.6294.7pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Silty sand73.7128.9184.2pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Clayey soil, su < 1,044 psf (50 kPa)36.855.273.7pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Clayey soil, su 1,044–2,089 psf (50–100 kPa)73.7128.9184.2pciROB T9, p.84
Coefficient of subgrade reaction (1-ft plate)Clayey soil, su > 2,089 psf (100 kPa)184.2pciROB T9, p.84
Open this set in the database ↗
Allowable bearing on rock (21 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Allowable bearing capacityGranite, micrograniteRockIgneous – acid16.791.9167.1ksfLOOK T6.9, p.97
Allowable bearing capacityBasalt, doleriteRockIgneous – basic12.568.9125.3ksfLOOK T6.9, p.97
Allowable bearing capacityTuff, brecciaRockIgneous – pyroclastic8.44683.5ksfLOOK T6.9, p.97
Allowable bearing capacityQuartzite, gneissRockMetamorphic – non-foliated20.9114.9208.8ksfLOOK T6.9, p.97
Allowable bearing capacityPhyllite, slate, schistRockMetamorphic – foliated8.44683.5ksfLOOK T6.9, p.97
Allowable bearing capacityLimestone, dolomite, sandstoneRockSedimentary – hard10.457.4104.4ksfLOOK T6.9, p.97
Allowable bearing capacitySiltstone, coal, chalk, shaleRockSedimentary – soft6.334.562.7ksfLOOK T6.9, p.97
Presumed allowable bearing value (BS 8004)Strong igneous and gneissic rock, soundPreliminary design209ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Strong limestone and strong sandstonePreliminary design84ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Schists and slatesPreliminary design63ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Strong shale, mudstone and siltstonePreliminary design42ksfCURTIN T1.1, p.5
Bearing capacity shape correction on rock, Nc factor CcCircular1.2–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγCircular0.7–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nc factor CcSquare1.25–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγSquare0.85–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nc factor CcRectangular L/B = 21.12–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγRectangular L/B = 20.9–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nc factor CcRectangular L/B = 51.05–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγRectangular L/B = 50.95–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nc factor CcStrip L/B ≥ 101–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγStrip L/B ≥ 101–EM2908 T6-1, p.6-3
Open this set in the database ↗
Bearing capacity shape corrections on rock (Sowers) (10 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Bearing capacity shape correction on rock, Nc factor CcCircular1.2–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγCircular0.7–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nc factor CcSquare1.25–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγSquare0.85–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nc factor CcRectangular L/B = 21.12–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγRectangular L/B = 20.9–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nc factor CcRectangular L/B = 51.05–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγRectangular L/B = 50.95–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nc factor CcStrip L/B ≥ 101–EM2908 T6-1, p.6-3
Bearing capacity shape correction on rock, Nγ factor CγStrip L/B ≥ 101–EM2908 T6-1, p.6-3
Open this set in the database ↗
Presumed allowable bearing values for preliminary design (BS 8004) (14 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Presumed allowable bearing value (BS 8004)Strong igneous and gneissic rock, soundPreliminary design209ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Strong limestone and strong sandstonePreliminary design84ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Schists and slatesPreliminary design63ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Strong shale, mudstone and siltstonePreliminary design42ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Dense gravel, or dense sand and gravelGW, GP, SWFooting width ≥ 3.3 ft; groundwater ≥ B below base12.5ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Medium dense gravel, or sand and gravelGW, GP, SWFooting width ≥ 3.3 ft; groundwater ≥ B below base4.28.312.5ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Loose gravel, or sand and gravelGW, GP, SWFooting width ≥ 3.3 ft; groundwater ≥ B below base4.2ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Compact sandSW, SPFooting width ≥ 3.3 ft; groundwater ≥ B below base6.3ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Medium dense sandSW, SPFooting width ≥ 3.3 ft; groundwater ≥ B below base2.14.26.3ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Loose sandSW, SPFooting width ≥ 3.3 ft; groundwater ≥ B below base2.1ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Very stiff boulder clay and hard clayCL, CHFooting width ≥ 3.3 ft; groundwater ≥ B below base6.39.412.5ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Stiff clayCL, CHFooting width ≥ 3.3 ft; groundwater ≥ B below base3.14.76.3ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Firm clayCL, CHFooting width ≥ 3.3 ft; groundwater ≥ B below base1.62.353.1ksfCURTIN T1.1, p.5
Presumed allowable bearing value (BS 8004)Soft clay and siltCL, CH, MLFooting width ≥ 3.3 ft; groundwater ≥ B below base1.6ksfCURTIN T1.1, p.5
Open this set in the database ↗
Pile shaft friction factors in coarse-grained soil (Ks/Ko, δ/φ') (9 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Coefficient of horizontal soil stress on pile shaft, Ks/KoDriven piles, large displacementCoarse-grained soil11.52–TOMLINSON T4.10, p.172
Coefficient of horizontal soil stress on pile shaft, Ks/KoDriven piles, small displacementCoarse-grained soil0.7511.25–TOMLINSON T4.10, p.172
Coefficient of horizontal soil stress on pile shaft, Ks/KoBored and cast-in-place pilesCoarse-grained soil0.70.851–TOMLINSON T4.10, p.172
Coefficient of horizontal soil stress on pile shaft, Ks/KoJetted pilesCoarse-grained soil0.50.60.7–TOMLINSON T4.10, p.172
Pile–soil interface friction ratio, δ/φ'Smooth (coated) steel / sand0.50.60.7–TOMLINSON T4.11, p.172
Pile–soil interface friction ratio, δ/φ'Rough (corrugated) steel / sand0.70.80.9–TOMLINSON T4.11, p.172
Pile–soil interface friction ratio, δ/φ'Precast concrete / sand0.80.91–TOMLINSON T4.11, p.172
Pile–soil interface friction ratio, δ/φ'Cast-in-place concrete / sand1–TOMLINSON T4.11, p.172
Pile–soil interface friction ratio, δ/φ'Timber / sand0.80.850.9–TOMLINSON T4.11, p.172
Open this set in the database ↗
References (9)
  1. CRAIG – Craig, R.F. (2004). Craig's Soil Mechanics, 7th ed. Spon Press.
  2. CURTIN – Curtin, W.G., Shaw, G., Parkinson, G.I., Golding, J.M. & Seward, N.J. (2006). Structural Foundation Designers' Manual, 2nd ed. Blackwell.
  3. DASP – Das, B.M. (2010). Principles of Geotechnical Engineering, 7th ed. Cengage.
  4. EM2908 – U.S. Army Corps of Engineers (1994). EM 1110-1-2908, Rock Foundations.
  5. GEC5 – Sabatini, P.J. et al. (2002). FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017)), Geotechnical Engineering Circular No. 5: Evaluation of Soil and Rock Properties.
  6. LOOK – Look, B.G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis.
  7. ROB – Robertson, P.K. & Cabal, K.L. (2010). Guide to Cone Penetration Testing for Geotechnical Engineering, 4th ed. Gregg Drilling & Testing.
  8. TOMLINSON – Tomlinson, M. & Woodward, J. (2008). Pile Design and Construction Practice, 5th ed. Taylor & Francis.
  9. USACE – U.S. Army Corps of Engineers (1990). EM 1110-1-1904, Settlement Analysis.
Correlations (7)
EstimateCorrelationLimits / notesSource
Drained modulus of clay from suE′/su ≈ 270 (PI 10–30), 200 (20–30), 150 (30–40), 130 (40–50)Stroud et al. (1975)LOOK 11.13, p.155
Shear modulus at small and large strainG(large) ≈ E/2.5; G(small) ≈ 2E ≈ 5 G(large)LOOK 11.2 notes, p.148
Stiffness degradationE0.01/E0 = 0.8–0.9; E0.1/E0 = 0.4–0.5; E1.0/E0 = 0.1–0.2Heymann (1998)LOOK 11.3, p.148
Small-strain shear modulus from shear wave velocityG0 = ρ Vs² = (γ/g) Vs² (γ in pcf, g = 32.2 ft/s², Vs in ft/s → G0 in psf)Seismic CPT or other Vs measurementROB text, p.53
Subgrade reaction size effectks = ks1 [(B + 1)/(2B)]², B in ftTerzaghi (1955); large scatterROB 9 text, p.84
Shaft friction in coarse-grained soil (effective stress)fs = Ks σ'vo tan δ; Ks = (Ks/Ko) Ko, δ = (δ/φ') φ'Ks/Ko and δ/φ' from Tomlinson Tables 4.10–4.11; base Nq σ'vo AbTOMLINSON Eq. 4.17, T4.10–4.11, p.172
Bearing capacity of rock (general shear)qult = cNc + 0.5γBNγ + γDNq; Nφ = tan²(45 + φ/2), Nc = 2√Nφ(Nφ + 1), Nγ = √Nφ(Nφ² − 1), Nq = Nφ²Strip; multiply Nc by Cc and Nγ by Cγ for other shapes (Table 6-1); compressive failure of poorly confined columns: qult = 2c tan(45 + φ/2)EM2908 Eq. 6-1, 6-2, 6-5, p.6-3–6-5
All correlations ↗

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
Executive Summary

Foundation bearing capacity governs the structural adequacy of every load-transfer element in railroad infrastructure — bridge abutments and piers, signal equipment foundations, grade crossing slabs, retaining wall footings, building slabs at intermodal yards, and pile-supported overhead structures. This chapter develops the complete bearing capacity framework for shallow and deep foundations under railroad loading, applying the Vesić generalized bearing capacity equation to strip, rectangular, and circular footings; eccentric and inclined loading from longitudinal braking and lateral wind; and pile capacity by the α-method (cohesive soils), β-method (cohesionless soils), and Meyerhof SPT-based method. Cooper E-80 live loads with client-specific dynamic amplification factors are translated into equivalent static foundation pressures. Worked examples address a spread footing under a Class I railroad bridge abutment, a drilled shaft at a Class I railroad bridge pier, and a pile group at a Class I railroad intermodal crane rail. Owner railroads impose unique requirements for minimum factors of safety, pile type preferences, and structural review coordination; these are integrated throughout. Cross-references are provided to Chapter 6.2 (Settlement Analysis), Chapter 6.3 (Slope Stability), Chapter 6.5 (Seismic/Liquefaction), and Chapter 2.3 (Railroad Track Subgrade).

Foundation failures IN SANDY SOILS
Foundation failures IN SANDY SOILS
Shallow foundations versus deep foundations
Shallow foundations versus deep foundations
Empirical Equations — Use and Limitations

The correlations used in this chapter are listed below. Each gives an estimate, not a test result. The full equation, variables, range of applicability, constraints and source for each one, and the note to record whenever one is used, are in the Empirical Equations & Correlations reference.

IDCorrelationGives
IS-01SPT energy & procedure correctionN₆₀
IS-04Friction angle of sand from SPT (Schmertmann form)φ'
IS-05Friction angle of sand from SPT (Peck–Hanson–Thornburn)φ'
IS-06Friction angle of sand from SPT (Hatanaka & Uchida)φ'
IS-07Undrained shear strength of clay from SPTSᵤ
IS-14Undrained shear strength from CPTSᵤ
IS-15Friction angle of sand from CPTφ'
RK-07Generalized Hoek–Brown criterionm_b, s, a
6.1.1 Background and Railroad Context

Foundations for railroad structures must support not only static dead loads but also highly dynamic live loads, impact, braking, and lateral forces that are unique to rail operations. Cooper E-80 loading — 80 kips per axle for the locomotive and 80 kips per axle for the tender — remains the standard design live load for Class I structures per AREMA MRE Chapter 8. Dynamic load factors (DLF) applied to axle loads before distribution to foundation elements are set by the owner railroad; they are lowest for slow-speed industrial track and highest for high-speed passenger operations.

6 Costly Mistakes in Foundation design
6 Costly Mistakes in Foundation design
Basic Foundation Components
Basic Foundation Components
Types of Foundations
Types of Foundations
Raft Foundation
Raft Foundation

Owner railroads may set foundation design requirements beyond the AREMA MRE minima; confirm them when the work is scoped. The federal track rules also bear on foundation design:

  • FRA TSS (49 CFR Part 213): Establishes geometry tolerances at the track level; differential settlement between adjacent foundations is the critical link between bearing capacity calculations and FRA compliance.
Foundation Testing
Foundation Testing
Soil Bearing Capacity
Soil Bearing Capacity
Strap Footing
Strap Footing
Wall Footing
Wall Footing

Our role as consultants is to deliver foundation designs that satisfy both structural adequacy (FS against failure) and serviceability (settlement limits per Chapter 6.2), calibrated to each client's operational environment and proprietary standards.

Foundation Failure - Excessive Settlement
Foundation Failure - Excessive Settlement
Foundation Failure
Foundation Failure

Bearing capacity of the track itself

Selig and Waters compare two ways to model the track as a footing:

  • A single tie punching into the granular layer, with B ≈ 9 in..
  • The whole track acting as a continuous strip footing, with B = 8.5 ft.

The strip-footing case gives a much lower capacity and governs. Capacity rises with granular depth H.

Slope-stability approach. A method-of-slices analysis is a conservative, two-dimensional check. The book applies a design load of 4,880 psf over the 8.5-ft tie length. A loaded 100-ton car is equivalent to about 1,400 psf, roughly 30% of that design load. An analysis FS of 1.0 therefore means the car is at about 30% of the failure load. The book treats that as the upper limit for avoiding large plastic deformation under repeated loading. At an analysis FS of about 0.3, expect massive failure.

Table 11-SW1. Analysis FS for track on flat subgrade with 24 in. of granular layer (φ = 42°, 135 pcf)
Subgrade strengthAnalysis FS (target ≥ 1.0)
c = 0, φ = 30°≈ 1.1
c = 1,000 psf, φ = 0≈ 1.1
c = 1,500 psf1.6
c = 2,000 psf2.1
c = 3,000 psf3.0

FS is roughly linear in c and in φ. A cut section gives about the same FS as flat ground. Embankments give lower values, with up to about a 30% reduction at a 1:1 (45°) side slope with a narrow shoulder. On an embankment the critical surface is deeper.

After Selig & Waters (1994), ch. 10. Full reference under Supplemental References.

6.1.2 Shallow Foundation Bearing Capacity — Vesić General Equation
6.1.2.1 General Bearing Capacity Equation

The Vesić (1973) generalization of Terzaghi's original equation is the standard for computing ultimate unit bearing capacity q_ult for shallow foundations:

Bearing Capacity
Bearing Capacity
Bearing Capacity Determination
Bearing Capacity Determination
Safe Bearing Capacity (SBC) Calculation
Safe Bearing Capacity (SBC) Calculation
Equation 6.1-1 — Vesić General Bearing Capacity:

q_ult = c · Nc · Fcs · Fcd · Fci

+ q · Nq · Fqs · Fqd · Fqi

+ 0.5 · γ · B · Nγ · Fγs · Fγd · Fγi

Where:

  • c = cohesion intercept (psf)
  • q = effective overburden pressure at footing base = γ · D_f (psf); D_f = embedment depth (ft)
  • γ = effective unit weight of soil below footing base (pcf)
  • B = footing width (ft)
  • N_c, N_q, N_γ = dimensionless bearing capacity factors (function of φ')
  • F_cs, F_qs, F_γs = shape correction factors
  • F_cd, F_qd, F_γd = depth correction factors
  • F_ci, F_qi, F_γi = inclination correction factors
Inputs: where each value comes from (5)
SymbolWhat it isComes fromHow to get itTypical range
ccohesion intercept (psf)Lab testEffective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more.0–300 psf · by USCS group
qeffective overburden pressure at footing base = γ · D_f (psf)Another equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
Dfembedment depth (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
γeffective unit weight of soil below footing base (pcf)Lab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
Bfooting width (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Equation 6.1-2 — Bearing Capacity Factors (Vesić):

Nq = e^(π·tan φ') · tan²(45 + φ'/2)

Nc = (Nq − 1) · cot φ' (use Nc = 5.14 when φ' = 0)

Nγ = 2(Nq + 1) · tan φ'

Table 6.1-1 — Bearing Capacity Factors vs. Friction Angle
φ' (°)N_cN_qN_γTypical Soil Description
05.141.000.00Soft–medium clay (UU condition)
56.491.570.45Soft clay with minor sand
108.352.471.22Silty clay
1510.983.942.65Stiff clayey silt
2014.836.405.39Dense silt, loose sand
2520.7210.6610.88Medium-dense sand
3030.1418.4022.40Dense sand, gravel-sand
3546.1233.3048.03Dense gravel
4075.3164.20109.4Very dense gravel
45133.9134.9271.8Dense rock fill
Inputs: where each value comes from (4)
SymbolWhat it isComes fromHow to get itTypical range
Nqintermediate value computed on this pageAnother equationComputed: Nq = e^(π·tan φ') · tan²(45 + φ'/2)project-specific
Ncintermediate value computed on this pageAnother equationComputed: Nc = (Nq − 1) · cot φ' (use Nc = 5.14 when φ' = 0)project-specific
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
6.1.2.2 Shape Correction Factors

For a rectangular footing of width B and length L (L ≥ B):

Equation 6.1-3 — Shape Factors:

Fcs = 1 + (B/L)(Nq/Nc)

Fqs = 1 + (B/L) tan φ'

Fγs = 1 − 0.4(B/L)

For a strip footing: B/L → 0, so F_cs = F_qs = F_γs = 1.0. For a circular footing (B = L): B/L = 1.0.

Inputs: where each value comes from (5)
SymbolWhat it isComes fromHow to get itTypical range
Fcsintermediate value computed on this pageAnother equationComputed: Fcs = 1 + (B/L)(Nq/Nc)project-specific
Fqsintermediate value computed on this pageAnother equationComputed: Fqs = 1 + (B/L) tan φ'project-specific
Fγsintermediate value computed on this pageAnother equationComputed: Fγs = 1 − 0.4(B/L)project-specific
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
6.1.2.3 Depth Correction Factors

No additional content.

Equation 6.1-4 — Depth Factors (Df/B ≤ 1):

Fcd = 1 + 0.4(Df/B)

Fqd = 1 + 2·tan φ'·(1 − sin φ')²·(Df/B)

Fγd = 1.0

For D_f/B > 1, replace D_f/B with arctan(D_f/B) in radians in the F_qd expression.

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
6.1.2.4 Inclination Correction Factors

For a resultant load inclined at angle β from vertical (due to braking or wind forces):

Equation 6.1-5 — Inclination Factors:

Fci = Fqi = (1 − β/90)²

Fγi = (1 − β/φ')²

β is in degrees. For purely vertical loading, β = 0 and all inclination factors = 1.0.

Inputs: where each value comes from (2)
SymbolWhat it isComes fromHow to get itTypical range
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
6.1.2.5 Allowable Bearing Capacity

No additional content.

Equation 6.1-6 — Allowable Bearing Pressure:

q_allow = (q_ult − q) / FS + q

Where q = surcharge at footing base; FS = factor of safety (typically 3.0 for railroad structures with limited investigation; 2.5 with comprehensive investigation).

The net allowable bearing pressure is:

q_net,allow = (q_ult − q) / FS

For railroad bridge abutments, FS ≥ 3.0 is common practice. For yard and siding structures, FS = 2.5 may be acceptable with borings at every foundation location; confirm with the owner railroad.

Inputs: where each value comes from (2)
SymbolWhat it isComes fromHow to get itTypical range
qsurcharge at footing baseLoading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
FSfactor of safety (typically 3.0 for railroad structures with limited investigationDesign criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.typically 3.0 for railroad structures with limited investigation
Supplemental reference

Two special cases common on railroad property

Strong layer over weak layer. A compacted ballast/subballast section or desiccated crust over soft clay is the typical railroad profile, and the Vesić equation (which assumes one homogeneous soil) overestimates capacity there. Das presents the Meyerhof and Hanna (1978) method: when the strong layer thickness H is small relative to B, the footing punches through the top layer (resisted by adhesion and passive force on vertical planes below the footing edges) and then fails the lower layer in general shear:

qu = qb + 2(Ca + Pp sin δ′)/B − γ1H  ≤  qt (capacity of the top layer alone)

where qb is the bearing capacity of the weaker layer and Ca = c′aH is the adhesion force. If H is large, the failure surface stays in the top layer and qt governs. For signal and equipment foundations on a thin working platform over soft subgrade, check this mechanism.

Footing at the top of a slope. Signal masts, catenary poles and bridge abutments often sit on or near an embankment crest. Meyerhof (1957) gives qu = c′Ncq + ½γBNγq, with Ncq and Nγq charted against slope angle, footing setback b/B, embedment Df/B and, for clay, the stability number Ns = γH/cu. Capacity increases with setback distance (Das charts b/B from 0 to about 6); a footing right at the crest can have a small fraction of its level-ground capacity. A worked example, footings on the slope face and poles in slopes are in Section 6.1.23. Always follow with a global slope stability check (Chapter 6.3).

Source: Das, B. M. Principles of Foundation Engineering. Cengage Learning

Supplemental reference

Presumptive allowable bearing pressures for preliminary sizing

For signal houses, small culvert headwalls and other minor railroad structures — or to sanity-check a Vesić result — NAVFAC DM-7.02 (Table 1) gives presumptive allowable pressures intended to provide adequate safety against failure and avoid detrimental settlement of individual footings:

Table 11-S1. Presumptive allowable bearing pressure, tsf (NAVFAC DM-7.02, Table 1, abridged)

Bearing materialConsistencyRangeRecommended
Massive crystalline igneous/metamorphic rock (granite, basalt, gneiss)Hard, sound60–10080
Foliated metamorphic rock (slate, schist)Medium hard, sound30–4035
Hard cemented shale, siltstone, sandstone, limestone without cavitiesMedium hard, sound15–2520
Weathered or broken bedrock (RQD < 25), except argillaceousSoft rock8–1210
Compaction shale / argillaceous rock, soundSoft rock8–1210
Glacial till, hardpan (GW-GC, GC, SC)Very compact8–1210
Gravel, gravel–sand (GW, GP, SW, SP)Very compact / medium / loose6–10 / 4–7 / 2–67 / 5 / 3
Coarse to medium sand (SW, SP)Very compact / medium / loose4–6 / 2–4 / 1–34 / 3 / 1.5
Fine to medium sand, silty or clayey sand (SW, SM, SC)Very compact / medium / loose3–5 / 2–4 / 1–23 / 2.5 / 1.5
Inorganic clay (CL, CH)Very stiff–hard / medium–stiff / soft3–6 / 1–3 / 0.5–14 / 2 / 0.5
Inorganic silt, varved silt-clay-fine sandVery stiff–hard / medium–stiff / soft2–4 / 1–3 / 0.5–13 / 1.5 / 0.5

NAVFAC’s notes matter for railroad use: controlled compacted fill takes the value of the equivalent natural soil; organic soil and uncompacted fill (common in old railroad embankments) must be investigated case by case; on compressible fine-grained soil, settlement generally governs; and a rock value may never exceed the intact UCS. Transient wind or earthquake loads may increase the pressure by up to one-third. Presumptive values are not a substitute for analysis where differential settlement matters, soils are soft, or groundwater is shallow.

Source: Naval Facilities Engineering Command (1986). Foundations and Earth Structures, Design Manual 7.02 (NAVFAC DM-7.02)

Foundation Design
Foundation Design
Supplemental reference

Footings on rock: failure mode depends on the joints

USACE EM 1110-1-2908 notes that rock foundation design is usually controlled by settlement, sliding or overturning, but bearing must still be checked, and the failure mode depends on joint spacing S relative to footing width B, joint orientation and condition (Figure 11-S1):

Typical bearing capacity failure modes for foundations on intact, jointed, layered and fractured rock (modified from Sowers, 1979, and Kulhawy &amp; Goodman, 1980).
Supplemental Figure 11-S1. Typical bearing capacity failure modes for foundations on intact, jointed, layered and fractured rock (modified from Sowers, 1979, and Kulhawy & Goodman, 1980). Source: U.S. Army Corps of Engineers (1994). Rock Foundations. EM 1110-1-2908, p. 6-2.
  • Intact rock (S > 4–5B): local shear in brittle rock (slip surfaces stay in the rock) or general wedge failure in ductile rock.
  • Steep, closely spaced, open joints: columns fail in unconfined compression — qult = 2c·tan(45° + φ/2), i.e., roughly the rock-mass UCS.
  • Steep, closely spaced, tight joints: general shear.
  • Steep joints spaced wider than B: splitting that progresses to general shear.
  • Joints dipping 20–70°: general shear, with a joint likely forming one face of the wedge.
  • Layered or fractured rock: punching or flexure of a stiff layer over a weak one, or general shear of a heavily fractured mass treated like soil.

For non-strip footings EM 1110-1-2908 applies Sowers’ shape corrections: Nc × 1.2 (circular), 1.25 (square), 1.12 (L/B = 2), 1.05 (L/B = 5); Nγ × 0.70, 0.85, 0.90, 0.95 respectively. Because rock masses usually have a large margin, USACE recommends starting from lower-bound c and φ.

Source: U.S. Army Corps of Engineers (1994). Rock Foundations. EM 1110-1-2908

6.1.2.6 Vesic Bearing Capacity Method and Calculator

The USACE manual Bearing Capacity of Soils (EM 1110-1-1905) sets out the general bearing capacity equation with the Terzaghi, Meyerhof, Hansen and Vesic factor sets and works each through the same footing. The Vesic set is used here because it handles footing shape, embedment and inclined load in one consistent form and is the basis of many agency programs. Track structures add two things to the usual building problem: longitudinal braking and traction forces make the load inclined, and the manual's table of typical factors of safety lists 4 for railway bridges, against 3 for ordinary footings.

6.1.2.6.1 Method

Equation 6.1-20. General bearing capacity equation (EM 1110-1-1905, Eq. 4-1)

qu = c Nc ζc + σ'D Nq ζq + 0.5 B γ'H Nγ ζγ

where σ'D is the effective overburden at the footing base, γ'H the effective unit weight within a depth B below the base, and each ζ the product of shape, depth and inclination factors.

Equation 6.1-21. Vesic bearing capacity factors

Nq = eπ tanφ tan²(45° + φ/2)   Nc = (Nq − 1) cotφ   Nγ = 2(Nq + 1) tanφ
Table 6.1-4. Vesic correction factors used by the calculator (EM 1110-1-1905, Table 4-6)
EffectCohesion ζcSurcharge ζqWedge ζγ
Shape1 + (B/W)(Nq/Nc)1 + (B/W) tanφ1 − 0.4 B/W
Depth (k = D/B, or tan−1(D/B) when D/B > 1)ζqd − (1 − ζqd)/(Nc tanφ); 1 + 0.4k for φ = 01 + 2 tanφ (1 − sinφ)² k1
Inclination (m = (2 + B/W)/(1 + B/W))ζqi − (1 − ζqi)/(Nc tanφ)(1 − T/Q)m(1 − T/Q)m+1

The calculator reproduces the manual's Vesic worked example (B = 3 ft, W = 6 ft, D = 2 ft, φ' = 30°, T/Q = 0.2): qu = 5.86 ksf.

Groundwater is handled as the manual recommends: σ'D uses buoyant weight below the water table, and γ'H is interpolated between moist and buoyant weight when the water table lies within B below the base. In loose or soft soil the local-shear option reduces tanφ by one third, which gives the lower-bound estimate of the manual's Equation 4-9.

6.1.2.6.2 Worked example: railroad bridge abutment footing

Table 6.1-5. Abutment footing on medium dense sand (calculator output)
InputValueResultValue
Footing B × W, embedment D8 ft × 30 ft, 4 ftNc, Nq, Nγ35.49, 23.18, 30.21
φ', c32°, 0Correction factors ζc, ζq, ζγ1.102, 1.100, 0.666
γ, γsat, water depth125 pcf, 130 pcf, 6 ftUltimate qu19.34 ksf
T/Q (longitudinal braking)0.10Allowable qa at FS 4 (railway bridge)4.83 ksf
Factor of safety4Allowable vertical load1,160.2 kips

The inclination factor alone removes roughly a fifth of the surcharge and wedge terms in this example, which is why longitudinal forces from braking and traction should be carried into the bearing check rather than treated only in the structural design. Settlement (Chapter 6.2) usually controls for footings wider than about 6 ft on sand.

Open the bearing capacity calculator →
Vesic method per EM 1110-1-1905: footing shape, embedment, inclined load, water table, local shear, and allowable pressure for a chosen factor of safety.

6.1.2.6.3 Sources in the library

These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.

  • Bearing Capacity of Soils, USACE EM 1110-1-1905 (1992), Bearing Capacity folder: general equation, Vesic factors, groundwater, factor of safety table and worked examples.Find source ↗Library entry
  • Bearing Capacity of Soils — Shallow Foundations and — Piled Foundations (course notes), Bearing Capacity folder.Find source ↗Library entry
  • Pile Design for Structural and Geotechnical Engineers (book): deep foundations, used where D/B exceeds the shallow range.Find source ↗
6.1.3 Eccentric Loading — Effective Footing Dimensions

Railroad abutment footings routinely carry eccentric loads due to moment from earth pressure, live load surcharge, and longitudinal braking. The effective area method (Meyerhof 1953) reduces the footing dimensions to eliminate tension:

Design of Isolated Footing
Design of Isolated Footing
Isolated Footing
Isolated Footing
Equation 6.1-7 — Effective Dimensions:

B' = B − 2·e_B

L' = L − 2·e_L

Where e_B = M_B / P and e_L = M_L / P are eccentricities (ft) computed from resultant moments about the footing centroid. AREMA MRE Chapter 8 requires that the resultant fall within the middle third of the footing (e ≤ B/6) for unfactored loading.

Bearing capacity calculations use B' and L' in all equations; settlement analysis (Chapter 6.2) uses the full B and L for stress distribution.

Column Load Distribution
Column Load Distribution
6.1.4 Cooper E-80 Load Application to Shallow Foundations

For bridge abutment backwall pressure, use the AREMA Chapter 8 live-load surcharge for Cooper E-80 loading and confirm it with the owner railroad. For footing design, the geotechnical engineer converts the wheel load train to a resultant foundation reaction:

Track Load Transfer
Track Load Transfer
Figure 6.1-11. Simplified tie model: point wheel loads Q and uniform pressure over 2·ℓexc under each rail. Profillidis Fig. 6.1.10.
Figure 6.1-11. Simplified tie model: point wheel loads Q and uniform pressure over 2·ℓexc under each rail. Profillidis Fig. 6.1.10.
Equation 6.1-8 — Design Foundation Pressure:

P_design = (DL + LL·DLF) / A_footing

Where:

  • DL = dead load from structure (kips)
  • LL = live load reaction from Cooper E-80 analysis (kips)
  • DLF = dynamic load factor (1.20 for Class 3–4 freight; 1.30 for Class 5–6; 1.50 for high-speed passenger corridor; illustrative values only, since AREMA Chapter 8 impact depends on span and the owner railroad)
  • A_footing = footing area (ft²)

Take bridge seat reactions from the structural engineer's E-80 analysis of the actual span, then apply the owner railroad's impact factor; with an assumed DLF of 1.30, a seat reaction R becomes 1.30R per bearing.

Inputs: where each value comes from (4)
SymbolWhat it isComes fromHow to get itTypical range
DLdead load from structure (kips)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
LLlive load reaction from Cooper E-80 analysis (kips)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
DLFdynamic load factor (1.20 for Class 3–4 freightChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Afootingfooting area (ft²)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific

Measured contact pressure under a tie

The usual simplification treats the tie as a beam overhanging both rails, with a uniform ballast pressure over a length 2·ℓexc under each rail. Field measurements (ORE, 1973) show a different distribution: pressure concentrated under the rail seats, falling to about a quarter of the peak at the tie center (Figure 6.1-12). The peak pressure is given empirically by:

Figure 6.1-12. Measured pressure distribution under a tie, with peak σ under the rail seats and σ/4 at mid-tie. Profillidis Fig. 6.1.11.
Figure 6.1-12. Measured pressure distribution under a tie, with peak σ under the rail seats and σ/4 at mid-tie. Profillidis Fig. 6.1.11.
σ = P / [ α · ( L/2 + 3·ℓexc/2 ) ]

where P = axle load (2 × wheel load), α = tie width, L = tie length and ℓexc = distance from tie end to rail seat. For an E-80 or heavy-axle check of ballast and subballast bearing, this measured shape is a better basis for the pressure under the rail seat than a uniform average over the whole tie.

After Profillidis (2014), §11.8, Eq. 5.1.1, Figs. 6.1.10–6.1.11; after ORE D71 (1973). Full reference under Supplemental References.

6.1.5 Deep Foundation Bearing Capacity
6.1.5.1 Pile Capacity Components

Total pile capacity Q_ult is the sum of side friction Q_s and tip resistance Q_p:

Types of Pile
Types of Pile
Combined End-bearing and Friction Pile
Combined End-bearing and Friction Pile
Friction Pile
Friction Pile
Equation 6.1-9 — Total Pile Capacity:

Q_ult = Q_s + Q_p = Σ(f_s · A_s) + q_p · A_tip

Where:

  • f_s = unit skin friction over each layer (psf)
  • A_s = pile surface area over each layer (ft²)
  • q_p = unit tip resistance (psf)
  • A_tip = pile tip area (ft²)
Pile Skin Friction Calculation
Pile Skin Friction Calculation

Allowable pile capacity:

Q_allow = Q_ult / FS

Tie FS to the construction control method (FHWA NHI-05-042, superseded by GEC 12, FHWA-NHI-16-009 (2016), Table 11-S2): 2.0 with a static load test; 2.25 with dynamic testing and signal matching (CAPWAP); 2.5 with indicator piles and wave equation analysis; 2.75 with wave equation analysis only; 3.5 with the Gates formula. Owner railroads may require higher values.

Inputs: where each value comes from (6)
SymbolWhat it isComes fromHow to get itTypical range
Qultintermediate value computed on this pageAnother equationComputed: Q_ult = Q_s + Q_p = Σ(f_s · A_s) + q_p · A_tipproject-specific
fsunit skin friction over each layer (psf)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Aspile surface area over each layer (ft²)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
qpunit tip resistance (psf)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Atippile tip area (ft²)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
FS3.0 without load testingChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Pile Load Test
Pile Load Test
Spread Footing vs Pile Load Transfer
Spread Footing vs Pile Load Transfer
6.1.5.2 α-Method (Cohesive Soils)

The α-method (API RP 2A) computes unit skin friction in cohesive soils as a fraction of undrained shear strength:

Equation 6.1-10 — α-Method Skin Friction:

f_s = α · su

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
suundrained shear strengthLab or field testLab: UU triaxial (ASTM D2850) or unconfined compression (D2166). Field: vane shear (D2573), CPT su = (qt − σv)/Nkt, or pocket penetrometer/Torvane for screening.soft 250–500, stiff 1,000–2,000 psf · by USCS group
Equation 6.1-11 — α Factor (API):

α = 0.5 · ψ^(−0.5) when ψ ≤ 1.0

α = 0.5 · ψ^(−0.25) when ψ > 1.0

Where ψ = s_u / σ'_v (undrained strength ratio). For railroad bridge piles in typical alluvial clay (s_u = 800–1,200 psf; σ'_v = 1,500–2,500 psf), ψ ≈ 0.4–0.6 and α ≈ 0.65–0.79.

Rock-Socketed Piles
Rock-Socketed Piles

Unit tip resistance for closed-end pipe piles in clay:

q_p = 9 · su (at pile tip)

Inputs: where each value comes from (3)
SymbolWhat it isComes fromHow to get itTypical range
αintermediate value computed on this pageAnother equationComputed: α = 0.5 · ψ^(−0.5) when ψ ≤ 1.0project-specific
ψundrained shear strength = s_u / σ'_v (undrained strength ratio). For railroad bridge piles in typical alluvial clay (s_u = 800–1,200 psfLab or field testLab: UU triaxial (ASTM D2850) or unconfined compression (D2166). Field: vane shear (D2573), CPT su = (qt − σv)/Nkt, or pocket penetrometer/Torvane for screening.soft 250–500, stiff 1,000–2,000 psf · by USCS group
σ'vvertical stress / pore pressure = 1,500–2,500 psf), ψ ≈ 0.4–0.6 and α ≈ 0.65–0.79.Another equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.≈ 0.4–0.6 and α ≈ 0.65–0.79
6.1.5.3 β-Method (Cohesionless Soils)

In cohesionless soils, skin friction is computed as a fraction of the effective overburden stress:

Equation 6.1-12 — β-Method Skin Friction:

f_s = β · σ'_v

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
σ'vvertical stress / pore pressureAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
Equation 6.1-13 — β Factor:

β = K · tan(δ)

Where:

  • K = lateral earth pressure coefficient ≈ K_0 = 1 − sin φ' for normally consolidated sand (1.2–1.8 for driven piles due to densification)
  • δ = pile-soil interface friction angle ≈ 0.8φ' for steel H-piles; 0.9φ' for concrete piles; δ = φ' for rough concrete

Typical β values: 0.25–0.40 for steel H-piles in medium-dense sand. β = 0.30 is an assumed default for HP14×117 piles in alluvial sand without site-specific testing.

Unit tip resistance in cohesionless soils (Meyerhof):

Inputs: where each value comes from (4)
SymbolWhat it isComes fromHow to get itTypical range
βintermediate value computed on this pageAnother equationComputed: β = K · tan(δ)project-specific
Klateral earth pressure coefficient ≈ K_0 = 1 − sin φ' for normally consolidated sand (1.2–1.8 for driven piles due to densification)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.≈ K_0 = 1 − sin φ' for normally consolidated sand (1.2–1.8 for driven piles due to
δpile-soil interface friction angle ≈ 0.8φ' for steel H-pilesLab test (or fraction of φ')Interface direct shear (ASTM D5321); otherwise δ = 0.6–1.0 φ' depending on the surface (steel, concrete, geosynthetic).0.6–1.0 φ' · by USCS group
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
Equation 6.1-14 — Pile Tip in Sand:

q_p = σ'_v · Nq* ≤ 0.5·P_a·Nq*·tan φ' (Meyerhof 1976)

Nq* = bearing capacity factor for pile tip (Vesić table, typically 50–80 for dense sand, φ' = 35–40°). Apply a limiting unit tip resistance (Meyerhof 1976) and confirm capacity by load testing.

Driven Pile
Driven Pile
End Bearing Pile
End Bearing Pile
Inputs: where each value comes from (4)
SymbolWhat it isComes fromHow to get itTypical range
qpintermediate value computed on this pageAnother equationComputed: q_p = σ'_v · Nq* ≤ 0.5·P_a·Nq*·tan φ' (Meyerhof 1976)project-specific
Nq*bearing capacity factor for pile tip (Vesić table, typically 50–80 for dense sand, φ' = 35–40°)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.typically 50–80 for dense sand, φ' = 35–40°
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
σ'vvertical stress / pore pressureAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
6.1.5.4 Meyerhof SPT-Based Method

For driven displacement piles, the Meyerhof (1976) empirical method using corrected SPT blow counts is widely used for preliminary designs and for a short-line railroad and regional railroad projects where detailed lab testing is not available:

Equation 6.1-15 — Meyerhof Skin Friction (Sand):

f_s = 0.02 · N60 (tsf)

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
N60SPT blow countField testStandard Penetration Test (ASTM D1586); measure hammer energy (ASTM D4633, withdrawn 2025) to correct to N60.loose sand 4–10, dense 30–50 blows/ft · by USCS group
Equation 6.1-16 — Meyerhof Tip Resistance (Sand):

q_p = 0.4 · N60 · (Db/B) ≤ 4·N60 (tsf)

Where:

  • N_60 = SPT blow count corrected for hammer energy (blows/ft)
  • D_b = depth of pile tip below top of bearing stratum (ft)
  • B = pile width or diameter (ft)

For piles in clay, the total-stress (α) method gives:

f_s = α·s_u (α-method, Section 6.1.5.2)

q_p = 9·s_u (9·s_u/2,000 tsf with s_u in psf)

These correlations are suitable for preliminary design and contractor quantity estimates; Verify capacity by static or high-strain dynamic load testing.

Inputs: where each value comes from (5)
SymbolWhat it isComes fromHow to get itTypical range
qpintermediate value computed on this pageAnother equationComputed: q_p = 0.4 · N60 · (Db/B) ≤ 4·N60 (tsf)project-specific
N60SPT blow count corrected for hammer energy (blows/ft)Field testStandard Penetration Test (ASTM D1586); measure hammer energy (ASTM D4633, withdrawn 2025) to correct to N60.loose sand 4–10, dense 30–50 blows/ft · by USCS group
Dbdepth of pile tip below top of bearing stratum (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Bpile width or diameter (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
suundrained shear strengthLab or field testLab: UU triaxial (ASTM D2850) or unconfined compression (D2166). Field: vane shear (D2573), CPT su = (qt − σv)/Nkt, or pocket penetrometer/Torvane for screening.soft 250–500, stiff 1,000–2,000 psf · by USCS group
Supplemental reference

Factor of safety tied to construction control (FHWA)

Client-specific safety factors in Section 6.1.5.1 are consistent with FHWA practice, which links the factor of safety for driven piles to the field verification method:

Table 11-S2. Recommended FS by construction control method (FHWA NHI-05-042, superseded by GEC 12, FHWA-NHI-16-009 (2016), Table 9-1)

Construction control methodFS
Static load test (ASTM D1143) with wave equation analysis2.00
Dynamic testing (ASTM D4945) with wave equation analysis2.25
Indicator piles with wave equation analysis2.50
Wave equation analysis only2.75
Gates dynamic formula3.50

Only resistance from layers that give long-term support counts toward the design load: exclude shaft resistance in soil that can scour in the design flood and in soft compressible layers. Those layers still resist driving, so the driving resistance the hammer must overcome is larger than the design capacity — a frequent source of under-sized hammers at railroad stream crossings.

Setup and relaxation

Table 11-S3. Soil setup factors (Rausche et al., 1996, in FHWA NHI-05-042, superseded by GEC 12, FHWA-NHI-16-009 (2016), Table 9-20)

Predominant soil along shaftRangeRecommended
Clay1.2–5.52.0
Silt–clay1.0–2.01.0
Silt1.5–5.01.5
Sand–clay1.0–6.01.5
Sand–silt1.2–2.01.2
Fine sand1.2–2.01.2
Sand0.8–2.01.0
Sand–gravel1.2–2.01.0

Setup factors should be confirmed with local experience and restrike testing. The opposite effect, relaxation, occurs in dense saturated fine sands and non-cohesive silts (dilation and temporary suction at the toe) and in some laminated shales (release of locked-in horizontal stress). Where relaxation is possible, capacity must be verified by restrike or load test after pore pressures equilibrate, not at end of driving.

Source: Hannigan, P. J., Goble, G. G., Likins, G. E. and Rausche, F. (2006). Design and Construction of Driven Pile Foundations, Vol. I. FHWA NHI-05-042 (superseded by GEC 12, FHWA-NHI-16-009 (2016))

Pile Foundations
Pile Foundations

Underpinning track: micropiles and screw piles

Where soft ground is too deep to remove economically, track load can be carried to competent soil on piles beneath a load-transfer platform. Micropiles are small-diameter drilled and grouted shafts. Screw piles are rotated in with a helix tip, need no excavation or grout, and can be installed from a rail-mounted rig, including in winter. At one Canadian peat site, 68 piles of 18-in. diameter in two flights at 10° from vertical underpinned about 400 ft of track settling into peat.

CFA pile rig
Photo 6.1.5-1. CFA pile rig From Brown et al. (2007)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Low headroom CFA pile application
Photo 6.1.5-2. Low headroom CFA pile application From Brown et al. (2007)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Installation of CFA pile reinforcement
Photo 6.1.5-3. Installation of CFA pile reinforcement From Brown et al. (2007)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Group of CFA piles with form for pile cap
Photo 6.1.5-4. Group of CFA piles with form for pile cap From Brown et al. (2007)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Pilecaps on CFA piles for column-supported embankment
Photo 6.1.5-5. Pilecaps on CFA piles for column-supported embankment From Brown et al. (2007)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
CFA piles used for secant pile wall
Photo 6.1.5-6. CFA piles used for secant pile wall From Brown et al. (2007)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Micropile applications diagram: foundation support, seismic retrofit, slope stabilization, earth retention
Photo 6.1.5-7. Micropile applications — foundation support, seismic retrofit, slope stabilization & earth retention From FHWA NHI-05-039Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Micropile installation on a slope
Photo 6.1.5-8. Micropile installation on a slope Courtesy of a specialty contractor, via FHWA / SHRP2 R02Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Micropile installation with limited headroom under a bridge
Photo 6.1.5-9. Micropile installation with limited headroom Courtesy of a specialty contractor, via FHWA / SHRP2 R02Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Deep Foundations
Deep Foundations
Micropile drilling under limited headroom
Micropile drilling under limited headroom
Figure 6.1-13. Pile foundation with a load-transfer platform spreading load into denser soil.
Figure 6.1-13. Pile foundation with a load-transfer platform spreading load into denser soil.
Figure 6.1-14. Screw-pile installation from a rail-mounted rig in winter.
Figure 6.1-14. Screw-pile installation from a rail-mounted rig in winter.
Figure 6.1-15. Screw-pile helix plate.
Figure 6.1-15. Screw-pile helix plate.
Figure 6.1-16. Pile installation equipment at a peat underpinning site.
Figure 6.1-16. Pile installation equipment at a peat underpinning site.

After Geotechnology for Railroaders Program, Module 6.2; §05. Full reference under Supplemental References.

6.1.5.5 Pile Design Additions: CPT Base Resistance, Separate Factors and Downdrag

CPT-based base resistance

Equation 6.1-23. Pile base resistance from cone resistance

qb,ult = 0.9 qc,m  (plunging failure);   qb,0.1 = 0.6 qc,m  (at a settlement of 10% of the diameter)

Bell and Robinson (2012), Eqs. 54.13–54.14, p. 812; the second after Lehane et al. (2005). qc,m = weighted average cone resistance from 8D above to 4D below the toe (the Dutch method), which accounts for weaker layers near the toe.

Correlations of shaft friction with cone resistance vary widely, from about qc/10 to qc/40; the effective-stress methods of Section 6.1.5 (BC-12) are usually more reliable for shaft resistance (Bell and Robinson, 2012, p. 812).

Separate factors on base and shaft

Equation 6.1-24. Safe working load with separate factors

SWL = Qb/Fb + Qs/Fs

Bell and Robinson (2012), Eq. 54.16, p. 814. Traditional UK values: 2.0 overall with preliminary load tests; 2.5 overall, or 1.5 on shaft and 3.0 on base, with working-pile tests; 3.0 overall without testing.

The separate factors recognise that the base needs much more movement than the shaft to mobilise. Follow AREMA and the owner's requirements where they set the factor; use the split check to see whether a design leans on base resistance it will not mobilise at working settlement.

Negative skin friction and the neutral point

Where new fill or a lowered water table makes the soil settle more than the pile, the upper shaft carries negative skin friction. The point where pile and soil settle equally is the neutral point, and the maximum axial load in the pile occurs there (Ellis and O'Brien, 2012, Eq. 57.2, p. 888):

Equation 6.1-25. Maximum pile load with negative skin friction

Qmax = Qh + Qs− = Qs+ + Qb

Qh = load at the pile head; Qs− = negative skin friction above the neutral point; Qs+ = positive shaft resistance below it; Qb = base resistance.

Downdrag raises the structural load in the pile and adds settlement; it does not reduce the geotechnical capacity in the same way as an applied load. Bridge piers and abutment piles next to a new or raised approach embankment on soft clay are the common railroad case. The same embankment can also push the piles sideways; piles designed only for vertical load are vulnerable to lateral soil movement, and reducing the soil movement (ground improvement, lightweight fill, staged construction) is often simpler than designing the piles for it (Ellis and O'Brien, 2012, pp. 887–897).

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • Bell, A. and Robinson, C. (2012). Single piles. Chapter 54 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 803–822Find source ↗Library entry
  • Ellis, E. and O'Brien, A. S. (2012). Global ground movements and their effects on piles. Chapter 57 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 887–898Find source ↗Library entry
Supplemental reference · Goswami (2015), Chs. 207 and 507

Batter Piles and Underpinning Existing Foundations

Batter piles are driven at an incline, commonly 1H:12V to 5H:12V, so that a pile group can resist horizontal load by axial force rather than bending. The axial load in each pile is found from the resultant of the vertical and horizontal loads resolved along the pile axes. Batter piles are stiff laterally, but in settling ground the soil hangs on them and induces bending, and they transmit horizontal earthquake load to the cap with little give.

Underpinning extends an existing foundation to a deeper or stronger bearing layer, or supports it while the ground beside it is excavated. Common methods:

  • Bracket piles: steel push piers or helical piles installed beside the footing and connected to it with brackets, then jacked or torqued to transfer load.
  • Temporary support with maintenance jacking: the structure is supported on jacks over temporary piles or cribbing while the permanent foundation is built, and the jacks are adjusted to keep it level.
  • Underpinning a damaged pile foundation: new piles are installed beside the defective ones and a new cap or needle beams transfer the load to them.

For railroad work: Bridge abutments and piers that have settled or been undermined by scour, and signal and catenary foundations next to new excavations, are typical underpinning candidates. Track windows and vertical clearance usually favor bracket piles, helical piles and micropiles (Section 6.1.20). Keep any jacking within the track geometry limits set for the work and monitor the track during it (Chapter 5.3).

Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 207 (Batter Piles) and Chapter 507 (Underpinning). Full reference under Supplemental References.

Supplemental reference · Bowles (1996), Section 16-17

Buckling of partially embedded piles and poles

A pile that is fully embedded in any soil stiffer than very soft clay is braced along its length and rarely buckles; the structural check is crushing of the section. Buckling becomes a design case when part of the pile stands free: trestle bents and pile bents, piles exposed by scour, piles through water or very soft clay, and poles and masts. The soil does not fix the pile at the ground line; the point of fixity is some distance below it, deeper in softer soil, so the effective column length is longer than the free length.

Bowles’ example shows the size of the effect: a 10-in. by 0.25-in. steel pipe pile 39 ft long, with 23 ft standing free and 16 ft embedded in extremely soft clay (unconfined strength about 210 psf) on rock, has a computed buckling load of about 45 kips. The Euler load for a column fixed at the ground line (effective length 2 × 23 = 46 ft) is about 86 kips, and for a column fixed at the tip (effective length 2 × 39 = 78 ft) about 30 kips. The true value lies between and closer to the second, so assuming fixity at the ground line would have been unsafe by almost a factor of two.

For railroad work: For timber and steel pile trestles, check buckling of each bent pile with the free length measured from the bottom of the design scour, not the streambed, and with fixity taken several pile diameters below that, or with a beam-on-elastic-foundation (p-y) buckling analysis. Re-check old bents after a flood has lowered the bed. Longitudinal and transverse bracing between piles reduces the effective length and is often the cheapest repair.

Source: Bowles, J. E. (1996). Foundation Analysis and Design, 5th ed., Example 16-14 (converted from SI). McGraw-Hill

Supplemental reference

Base and Side Post-Grouting of Drilled Shafts

The base of a drilled shaft in sand or gravel is often loosened by drilling and cleaning, and the end bearing only develops after large settlement. Post-grouting injects cement grout under pressure through tubes cast into the shaft, after the concrete has cured. Grout at the base (through a sleeve-port tube circuit or a flat-jack cell) densifies and preloads the disturbed soil at the tip. Grout along the side (through sleeve ports on tubes tied to the cage) improves the shaft-soil contact. The grouting is itself a load test: the grout pressure acting on the base area, resisted by side friction, shows the tip resistance mobilized, and the upward movement of the shaft top is measured as the grouting proceeds.

Xiao, Wu and Wu (2009) report base and side post-grouting of more than 18,000 slurry-drilled piles at one airport terminal, with 72 static load tests showing large gains in capacity and in settlement performance, especially in sand. FHWA’s drilled shaft manual (GEC 10) covers base grouting design, the records to keep and acceptance.

For railroad work: Consider post-grouting for bridge pier and abutment shafts that end in sand or gravel, where end bearing would otherwise need large settlement to develop, or where a shorter shaft avoids a difficult layer. Specify the grouting criteria (target grout pressure, maximum grout volume and maximum upward movement of the shaft top) and require a record for each shaft. Do not take credit for the grouted base in design without load test or grouting data from the site. Grout volumes far above the estimate can mean grout escaping into a void or a coarse layer, which needs investigating, especially in karst.

Source: Xiao, D., Wu, C. and Wu, C. (2009), “Bored Pile Post-Grouting Technology and Its Engineering Application,” ASCE GSP 188, 198–206 (summarized in Chapter 7.2, Section 7.2.18); FHWA GEC 10, Drilled Shafts: Construction Procedures and Design Methods (FHWA-NHI-18-024, 2018), FHWA geotechnical publications. Summarized and paraphrased.

6.1.6 Pile Group Efficiency

When piles are installed in a group, the group capacity may be less than the sum of individual pile capacities due to stress overlap. The group efficiency factor η is:

Pile Foundation vs Raft Foundation
Pile Foundation vs Raft Foundation
Equation 6.1-17 — Group Efficiency (Converse-Labarre):

η = 1 − θ · [(n−1)·m + (m−1)·n] / (90 · m · n)

Where:

  • θ = arctan(D/S) in degrees; D = pile diameter (ft); S = center-to-center spacing (ft)
  • m = number of columns; n = number of rows

Common practice (see AREMA MRE Chapter 8 for piles) uses a center-to-center spacing of at least about 2.5–3 pile diameters. At S = 3D, common for railroad bridge pile groups, η ≈ 0.72–0.82.

For cohesive soils, the block failure mode must also be checked: the lesser of the group efficiency method and the block failure capacity controls.

Inputs: where each value comes from (5)
SymbolWhat it isComes fromHow to get itTypical range
θarctan(D/S) in degreesChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Dpile diameter (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Scenter-to-center spacing (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
mnumber of columnsChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
nnumber of rowsChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Equation 6.1-18 — Block Failure Capacity:

Q_block = 2·D_g·(B_g + L_g)·su,avg + Nc·su,tip·B_g·L_g

Where:

  • D_g = pile group embedment depth (ft)
  • B_g, L_g = block perimeter dimensions (ft)
  • N_c = 5(1 + 0.2D_g/B_g)(1 + 0.2B_g/L_g) ≤ 9 (Skempton)
  • s_u,avg = average undrained strength along pile perimeter (psf)
  • s_u,tip = undrained strength at pile tip elevation (psf)
Inputs: where each value comes from (3)
SymbolWhat it isComes fromHow to get itTypical range
Dgpile group embedment depth (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Nc5(1 + 0.2D_g/B_g)(1 + 0.2B_g/L_g) ≤ 9 (Skempton)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
suundrained shear strengthLab or field testLab: UU triaxial (ASTM D2850) or unconfined compression (D2166). Field: vane shear (D2573), CPT su = (qt − σv)/Nkt, or pocket penetrometer/Torvane for screening.soft 250–500, stiff 1,000–2,000 psf · by USCS group
6.1.7 Uplift Capacity

Tension forces from wind uplift, seismic uplift, and locomotive-induced overturning at signal mast foundations must be checked. Net uplift capacity for a single pile:

Micropile applications — foundation support, retrofit, slopes, retention
Micropile applications — foundation support, retrofit, slopes, retention
Equation 6.1-19 — Pile Uplift Capacity:

Q_ult,tension = Σ(f_s · As) + W_pile

Skin friction in tension is typically reduced to 75–80% of the compression value for driven piles (FHWA GEC No. 12). In frost-susceptible soils, frozen soil adhering to the pile can impose a large upward force ("frost heave uplift") that is distinct from structural uplift, and it needs a separate check.

6.1.8 Representative Data Tables
Table 6.1-2 — Typical Bearing Capacity Values by Soil Type (English Units)
Soil Type (USCS)Consistency/Densitys_u or φ'q_allow Shallow Fdn (tsf)Railroad Application
CH (Fat Clay)Very softs_u = 250–500 psf0.25–0.50Avoid; use piles — Class I railroad located in coastal Georgia
CL (Lean Clay)Softs_u = 500–1,000 psf0.5–1.0Siding footings minimum 3 ft embed.
CLStiffs_u = 1,000–2,000 psf1.0–2.0Bridge abutment footings — a Class I railroad
CL/MLVery stiffs_u = 2,000–4,000 psf2.0–4.0Grade crossing slabs — a short-line railroad
SM (Silty Sand)Looseφ' = 28–32°1.0–1.5Use piles for bridge loads — a Class I railroad
SP (Poorly Graded Sand)Medium denseφ' = 32–36°1.5–2.5Signal foundations — a Class I railroad
SW/GWDenseφ' = 36–40°2.5–4.5Intermodal crane footings — a Class I railroad
GW (Well-graded Gravel)Very denseφ' = 40–45°4.5–7.0Mainline bridge piers — a Class I railroad
CL over bedrockStiff clay capMixed1.5–3.0 w/ piles to rockClass I railroad located in Appalachia
Limestone/SandstoneCompetent rockRQD > 50%10–50+A Class I railroad bridge piers
Table 6.1-3 — Pile Type Selection Guide
ClientPreferred Pile TypeMinimum FS (w/test)Minimum FS (no test)Wave Equation RequiredLoad Test Required
FRA (all classes)Per AREMA Ch. 82.5 min3.0 minAs applicablePer client

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.

6.1.9 Reference Photographs
Plate Load Test Bearing Capacity Determination
Plate Load Test Bearing Capacity Determination
Bearing Capacity Determination
Bearing Capacity Determination
Foundation Settlement
Foundation Settlement
Pile Skin Friction Calculation
Pile Skin Friction Calculation
Pile Foundation Execution Inspection
Pile Foundation Execution Inspection
Why Are Some Foundation Piles Tested Until They Move
Why Are Some Foundation Piles Tested Until They Move
6.1.10 Worked Calculation Examples
The three examples cover the three foundation types under railroad structures: a spread footing, a driven pile group and a drilled shaft. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 6.1-1: Spread Footing for a Bridge Abutment

A bridge replacement on a Class I railroad located in West Virginia puts an abutment footing on stiff residual clay. Earth pressure behind the abutment adds a moment, which shifts the resultant toward the toe; the effective-width method replaces the true width with the width that carries the load centrally.

Drilled Piles — Construction Tolerances
Drilled Piles — Construction Tolerances

Given

VariableValueDescription
SoilStiff residual CL; φ′ = 24°, c = 600 psf, γ = 117 pcf
FootingB = 8 ft, L = 12 ft, Df = 4 ft
DL, LL280 kips; 165 kips (Cooper E-80)
DLF1.30Dynamic load factor on live load
M420 kip-ft about the short axisEarth pressure
FS3.0Required
Nq6.40 at 20°; 10.66 at 25°Table 6.1-1

Required

  • Eccentricity and effective width
  • Ultimate and allowable bearing pressure
  • Factor of safety under the applied pressure

Equations

  1. Eq. 6.1-7: e = M/P; B′ = B − 2e (e ≤ B/6) — effective width
  2. Eq. 6.1-2: Nc = (Nq − 1) cotφ′; Nγ = 2(Nq + 1) tanφ′ — Nq from Table 6.1-1
  3. Eq. 6.1-3: Fcs = 1 + (B′/L′)(Nq/Nc); Fqs = 1 + (B′/L′) tanφ′; Fγs = 1 − 0.4 B′/L′ — shape
  4. Eq. 6.1-4: Fcd = 1 + 0.4 Df/B′; Fqd = 1 + 2 tanφ′(1 − sinφ′)² Df/B′; Fγd = 1 — depth, Df/B ≤ 1
  5. Eq. 6.1-1: qult = cNcFcsFcd + qNqFqsFqd + ½γB′NγFγsFγd — general bearing capacity
  6. Eq. 6.1-6: qallow = (qult − q)/FS + q

Steps

Step 1 · Load and eccentricity (Eq. 6.1-7)
P = 280 + 165 × 1.30 = 494.5 kips; e = 420/494.5
e = 0.849 ft < B/6 = 1.33 ft; B′ = 8 − 1.70 = 6.30 ft
↓
Step 2 · Bearing capacity factors (Eq. 6.1-2)
Nq = 6.40 + 0.8(4.26); Nc = 8.81/0.445; Nγ = 2(10.81)(0.445)
Nq = 9.81; Nc = 19.80; Nγ = 9.62
↓
Step 3 · Shape and depth factors (Eq. 6.1-3, 6.1-4)
B′/L′ = 0.525; Df/B′ = 0.635
Fcs 1.260, Fqs 1.234, Fγs 0.790; Fcd 1.254, Fqd 1.199, Fγd 1.0
↓
Step 4 · qult (Eq. 6.1-1)
q = 117 × 4 = 468 psf; 600(19.80)(1.260)(1.254) + 468(9.81)(1.234)(1.199) + 0.5(117)(6.30)(9.62)(0.790) = 18,768 + 6,793 + 2,801
qult = 28,362 psf
↓
Step 5 · qallow (Eq. 6.1-6)
(28,362 − 468)/3.0 + 468
9,766 psf = 4.88 tsf
↓
Step 6 · Applied pressure and FS
494,500 / (6.30 × 12) = 6,541 psf; (28,362 − 468)/(6,541 − 468)
FS = 4.59 ≥ 3.0
Spot check: The applied 6,541 psf is below the 9,766 psf allowable, consistent with FS > 3.
↓
Solution
FS = 4.59: the footing is adequate in bearing.

Solution

The resultant is within the middle third (e = 0.85 ft < 1.33 ft), qallow = 4.88 tsf, and the factor of safety under the applied load is 4.59.

Bearing is comfortably adequate; for a footing on stiff clay under a railroad bridge, settlement will govern. The settlement analysis (Chapter 6.2) must show total settlement under 1.0 in. and differential under 0.75 in. across the span, or the owner railroad’s limits, to hold FRA Class 4 geometry. The railroad’s bridge engineers will review the calculation.

Example 6.1-2: Driven H-Pile Group for a Bridge Pier

A pier replacement on a Class I railroad main line located in Kansas. HP14×117 piles are driven through loose fill into medium-dense alluvial sand and stop 2 ft above limestone. Side resistance is computed with the β-method, tip resistance with Meyerhof’s SPT method, and the group is checked for efficiency.

Bored Pile Tremie Concreting
Bored Pile Tremie Concreting

Given

VariableValueDescription
Fill0 to 15 ft; loose SM; φ′ = 30°; γ = 115 pcf
Sand15 to 45 ft; SP-SM; φ′ = 35°; N60 = 22; γ = 120 pcf
zw8 ft
PileHP14×117: A = 34.4 in.² = 0.239 ft²; perimeter 4.65 ft; tip at 43 ft
K, δFill: 1.0, 24°; sand: 1.2, 28°δ = 0.8φ′
FS2.5Assumed owner requirement
Demand800 kipsPier reaction, two-track 80-ft spans

Required

  • Single-pile capacity
  • Number of piles and group arrangement

Equations

  1. Eq. 6.1-12: fs = β σ′v,avg; β = K tanδ — β-method
  2. Eq. 6.1-16: qp = 0.4 N60 (Db/B) ≤ 4 N60 (tsf) — Meyerhof tip, sand
  3. Eq. 6.1-9: Qult = Qs + Qp; Qallow = Qult/FS
  4. Eq. 6.1-17: η = 1 − θ[(n − 1)m + (m − 1)n] / (90 m n); θ = arctan(D/S) in degrees — Converse-Labarre group efficiency

Steps

Step 1 · Effective stresses
At 15 ft: 8(115) + 7(52.6) = 1,288 psf; at 43 ft: 1,288 + 28(57.6) = 2,901 psf
σ′v = 1,288 and 2,901 psf
↓
Step 2 · Side resistance (Eq. 6.1-12)
Fill: tan24° × 644 = 286 psf × 69.75 ft²; sand: 1.2 tan28° × 2,095 = 1,337 psf × 130.2 ft²
Qs = 19.9 + 174.0 = 193.9 kips
↓
Step 3 · Tip (Eq. 6.1-16)
0.4 × 22 × (28/1.167) = 211 tsf; limit 4 × 22 = 88 tsf governs; 88 × 2,000 × 0.239
Qp = 42.1 kips
↓
Step 4 · Single pile (Eq. 6.1-9)
(193.9 + 42.1) / 2.5
Qallow = 94.4 kips; 800/94.4 = 8.5 piles
↓
Step 5 · 3×3 group (Eq. 6.1-17)
At 3D: θ = 18.4°, η = 0.728, 619 kips; at 4D: θ = 14.0°, η = 0.793, 674 kips
Both short of 800 kips
↓
Step 6 · 3×4 group at 4D
η = 1 − 14.0(17)/1,080 = 0.780; 12 × 94.4 × 0.780
883.5 kips ≥ 800 kips
↓
Solution
12 piles (3×4) at 4D spacing: 883 kips.

Solution

Qallow = 94.4 kips per pile; a 3×4 group of 12 piles at 4D spacing provides 883 kips against the 800-kip demand.

FHWA allows η = 1.0 for driven groups in sand that are not predrilled or jetted, because driving densifies the sand between piles, so the Converse-Labarre reduction here is conservative; with η = 1.0, nine piles would do. Set refusal criteria with WEAP, confirm capacity with CAPWAP on an agreed share of production piles, and confirm tip elevations in the field.

Example 6.1-3: Drilled Shaft for a Crane Rail Foundation

A rail-mounted gantry crane foundation for an intermodal facility on a Class I railroad located in Dallas, Texas. The shaft carries a heavy, repeated wheel load through stiff to very stiff clay. Side resistance is computed with the FHWA GEC 10 α-method, excluding the top 5 ft and the bottom diameter.

CSL Access Tube Requirements for Drilled Piles
CSL Access Tube Requirements for Drilled Piles

Given

VariableValueDescription
Load180 kips per rail per axle; DLF 1.20 (assumed)Demand 216 kips
SoilCL, su = 1,800 psf to 20 ft; CH, su = 3,200 psf to 35 ft
Shaft30 in. diameter, 35 ft deep (first trial)
FS2.5Assumes a load test
pa2,117 psf

Required

  • Allowable capacity of the 30-in. shaft
  • A shaft size that meets the demand

Equations

  1. Eq. 1 (GEC 10): α = 0.55 for su/pa ≤ 1.5; α = 0.55 − 0.1(su/pa − 1.5) up to 2.5 — side resistance factor
  2. Eq. 6.1-10: Qs = Σ α su πD Δz — side resistance, 5 ft to one diameter above the tip
  3. Eq. 3: Qp = 9 su Atip — tip in clay

Steps

Step 1 · α values
1,800/2,117 = 0.85; 3,200/2,117 = 1.51
α = 0.55 and 0.549
↓
Step 2 · 30-in. shaft
Qs1 = 990 × 7.854 × 15 = 116.6; Qs2 = 1,757 × 7.854 × 12.5 = 172.5; Qp = 28,800 × 4.909 = 141.4 kips
Qult = 430.5 kips; Qallow = 172.2 < 216 kips
↓
Step 3 · 36-in. shaft
Qs1 = 990 × 9.425 × 15 = 139.9; Qs2 = 1,757 × 9.425 × 12 = 198.7; Qp = 28,800 × 7.069 = 203.6 kips
Qult = 542.2 kips; Qallow = 216.9 ≥ 216 kips
Spot check: FS at the demand = 542.2/216 = 2.51.
↓
Solution
A 36-in. shaft just meets the demand (216.9 kips).

Solution

The 30-in. shaft provides 172 kips, short of 216 kips. A 36-in. shaft at 35 ft provides 216.9 kips, just meeting the demand at FS = 2.5.

With so little margin, a 42-in. shaft or a deeper tip is the prudent choice. FS = 2.5 assumes a load test, so confirm the owner’s load-test requirement (a static test to ASTM D1143 or a bidirectional test) before production shafts. Under repeated crane loading, the tip, which needs larger movement to mobilize, carries a larger share of the load than its 38% share of capacity suggests; settlement should be checked as well.

6.1.11 Practical Recommendations
  1. Always check both bearing capacity and settlement: Bearing capacity governs for short, stiff footings on soft clay; settlement governs for wide footings on compressible soils. Both must satisfy FRA track geometry tolerances (Chapter 6.2). Include both analyses in every bridge foundation submission.
  2. Apply client-specific dynamic load factors early: DLF differences between a short-line railroad (1.20) and a passenger railroad (1.50) can change the required pile count by 25% or more on an otherwise identical structure. Confirm the DLF with the client's bridge engineering group before finalizing pile layouts.
  3. Never rely on Meyerhof SPT correlations alone for production pile design: SPT N₆₀ scatter introduces ±30–40% uncertainty in predicted pile capacity. Plan dynamic or static load testing for production foundations. Budget load testing costs into the geotechnical scope from the start.
  4. Check eccentricity for all abutment footings: Longitudinal braking forces and earth pressure moments routinely push the resultant outside the middle third under service loading. AREMA Chapter 8 requires the middle-third check; failing this check forces redesign (wider footing, deeper embedment, or battered pile pair) that should be identified early.
  5. Group efficiency governs intermodal yard pile groups: RMG crane rail loads are high, pile groups are tight, and groups in soft clay commonly exhibit block failure governing over individual pile summation. Always check both mechanisms; Document the block failure check.
  6. Address frost depth in northern designs: In the Northern Plains, Rockies and Prairie provinces, embed footings at least to the local frost depth (often 6–8 ft), with any added margin the owner railroad requires. Frost-heave uplift on pile shafts through frozen soils requires bitumen coating of the pile in the active layer — confirm the owner railroad's requirements.
  7. Coordinate with the passenger railroad for underpinning: Passenger railroads commonly require that underpinning or deep foundation work near an active track (often within about 25 ft of track centerline; confirm the owner's distance) be reviewed by the railroad's Structures Engineering prior to design finalization. Micropile designs must include a pre-construction structural assessment of the existing footing being underpinned.
Project management · Jacob and Müller (2017)

Estimating Drilled Shafts from a Rig-Day Cost

Weinhold’s chapter on special foundation works prices bored piles from a working-unit day rate. The day rate is the full cost of one rig with its crew, tooling and site containers for one workday, divided by realistic daily production.

The example rig is a cased Kelly rig, rated to 47 in diameter and 59 ft depth, with a 3-person crew on a 10-hour day. Its day rate includes:

  • the crew;
  • the base machine, rotary drive and Kelly bar, at 70% of register rental rates;
  • a support loader and site containers;
  • fuel at 70% utilization;
  • casing sections, casing shoes, augers, a bucket and a core barrel.

Labor was about 28% of the day rate and the base machine about 40%.

The book’s shafts were 35 in diameter and 26–36 ft long, at a production rate of 164 ft per workday. Converted to US units, the cost per foot of shaft is made up of:

  • drilling = day rate ÷ 164 ft (about 60% of the total);
  • concrete at 0.242 CY/ft, plus 10% overrun (about 32%);
  • disposal of 0.242 CY/ft of cuttings (about 8%).

Reinforcing is a separate per-ton item. The other items are priced separately:

  • Mobilization and demobilization: two rig-days, special heavy transport, mileage and fixed costs.
  • Pile-top chipping: 1.6 ft of overpour on each of 64 shafts, subcontracted per CY with a disposal charge.
  • Obstruction removal: an hourly item at one-tenth of the day rate.

A flat 25% markup for overhead, risk and profit was considered acceptable, because bored piling is routine work for bidders.

The chapter lists the bid conditions that affect price:

  • quantities are “for calculation only” and the bidder must verify them;
  • the bidder must state reservations about specified methods in writing;
  • a site visit is mandatory, and known obstructions are to be itemized;
  • unit prices include all ancillary work.

It also notes that load tests on large projects can pay for themselves by allowing pile sizes to be optimized.

For railroad work: For bridge foundations and drilled-shaft retaining walls next to live track, the rig-day framework lets the engineer test how sensitive the cost is to geotechnical findings:

  • slower production in cobbles or rock sockets;
  • temporary versus permanent casing where groundwater or caving is expected;
  • cuttings disposal where railroad spoil handling rules apply;
  • standby hours when work stops for train movements.

Production per workday should reflect the track windows actually available. Obstruction and standby items give the railroad unit prices for those risks instead of leaving them to claims.

Source: Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn, pp. 180–192. Summarized and paraphrased. Full reference under Supplemental References.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
6.1.12 Foundation Engineering Checklist

Checklist · Part VI · Geotechnical Analysis

Foundation Engineering Checklist

Pre-Design0 of 6
Shallow Foundation Design0 of 5
Pile Foundation Design0 of 7
Deliverables0 of 6
Ticks are saved in this browser.
Plain text version

Pre-Design

  • [ ] Confirm design loads: DL, LL (Cooper E-80), DLF by client, wind/seismic
  • [ ] Review boring logs and laboratory data for all foundation zones
  • [ ] Identify groundwater conditions; obtain FEWL and SWL readings (Chapter 2.8)
  • [ ] Check scour potential at stream crossings (Chapter 2.8, Section 2.8.5.4)
  • [ ] Confirm the local frost penetration depth
  • [ ] Identify contaminated soil zones near existing industrial sites

Shallow Foundation Design

  • [ ] Compute q_ult using Vesić equation; verify all factor tables
  • [ ] Apply correct B' and L' for eccentric loading; verify middle-third rule
  • [ ] Check FS ≥ 3.0 or FS ≥ 2.5 (a short-line railroad with borings)
  • [ ] Cross-reference settlement analysis (Chapter 6.2) for serviceability
  • [ ] Verify D_f ≥ local frost depth

Pile Foundation Design

  • [ ] Select pile type and confirm it with the owner railroad (Table 6.1-3)
  • [ ] Compute Q_s by α- or β-method; compute Q_p; sum Q_ult
  • [ ] Verify FS against Table 6.1-3 for the testing program planned
  • [ ] Compute group efficiency (Converse-Labarre); check block failure in clay
  • [ ] Check uplift capacity for signal mast and wind-sensitive structures
  • [ ] Specify WEAP analysis
  • [ ] Specify load test type, quantity, and timing (before production driving)

Deliverables

  • [ ] Foundation analysis memo with all calculations
  • [ ] Boring log cross-section with pile tip elevations marked
  • [ ] Pile driving criteria table (set, stroke, cushion specifications)
  • [ ] Load test plan submitted to client Bridge/Structures Engineering
  • [ ] Settlement calculation summary (Chapter 6.2 cross-reference)
  • [ ] Coordination memo to the railroad's Bridge Engineering or the railroad's Structures as applicable
6.1.13 Practice Questions and Full Answers
Each question is worked in the same five parts as the examples. Questions 6.1-2 and 6.1-5 are reasoning questions.
Question 6.1-1: Square Footing on Clay, Undrained

Problem Statement

A short-line railroad is installing a new signal equipment house on a 6-ft-square spread footing at 3 ft depth, founded on stiff lean clay with the strength shown. The engineer must compute the ultimate and allowable bearing pressure, with the factor of safety shown, for the signal footing.

Given

VariableValueDescription
Footing6 ft × 6 ft; Df = 3 ft
SoilStiff lean clay; φ = 0; su = 1,500 psf; γ = 115 pcf
FS2.5

Required

  • qult and qallow

Equations

  1. Eq. 6.1-2: Nc = (Nq − 1) cotφ′; Nγ = 2(Nq + 1) tanφ′ — Nq from Table 6.1-1
  2. Eq. 6.1-3: Fcs = 1 + (B′/L′)(Nq/Nc); Fqs = 1 + (B′/L′) tanφ′; Fγs = 1 − 0.4 B′/L′ — shape
  3. Eq. 6.1-4: Fcd = 1 + 0.4 Df/B′; Fqd = 1 + 2 tanφ′(1 − sinφ′)² Df/B′; Fγd = 1 — depth, Df/B ≤ 1
  4. Eq. 6.1-1: qult = cNcFcsFcd + qNqFqsFqd + ½γB′NγFγsFγd — general bearing capacity
  5. Eq. 6.1-6: qallow = (qult − q)/FS + q

Steps

Step 1 · Factors at φ = 0
Nc = 5.14, Nq = 1.0, Nγ = 0
↓
Step 2 · Shape and depth
Fcs = 1 + 1.0/5.14; Fcd = 1 + 0.4(0.5)
Fcs = 1.195; Fcd = 1.20
↓
Step 3 · qult
1,500(5.14)(1.195)(1.20) + 345 = 11,056 + 345
qult = 11,400 psf
↓
Step 4 · qallow
11,056/2.5 + 345
4,770 psf = 2.38 tsf
↓
Solution
qult ≈ 11,400 psf; qallow ≈ 4,770 psf.

Solution

qult ≈ 11,400 psf; qallow ≈ 4,770 psf (2.38 tsf).

With φ = 0 the overburden term adds only q, so embedment helps mainly through the depth factor. The undrained case governs for a footing loaded quickly on clay.

Question 6.1-2: Effective Width and the Middle-Third Check

Problem Statement

A railroad retaining wall footing next to the track carries a vertical load and a moment from earth pressure and train surcharge. The designer reports a reduced effective width and asks whether the middle-third rule in AREMA Chapter 8 applies. The engineer must explain the effective width, when the middle-third check applies and what to do if the footing fails it.

Given

VariableValueDescription
LoadVertical load P with moment M
RuleAREMA Chapter 8: resultant within the middle third (e ≤ B/6) under unfactored load

Required

  • Meaning of B′
  • When the middle-third check applies and what to do if it fails

Equations

  1. Eq. 6.1-7: e = M/P; B′ = B − 2e

Steps

Step 1 · What does a moment do?
Moves the resultant off center by e = M/P.
↓
Step 2 · Effective width
B′ = B − 2e is the width that carries the load centrally; it replaces B in every bearing term.
↓
Step 3 · Middle third
e ≤ B/6 keeps the whole base in compression; if exceeded, widen the footing, re-center the load or deepen it.
↓
Solution
B′ = B − 2e; resultant must stay within B/6.

Solution

B′ = B − 2e is the reduced width that carries the load centrally, and it lowers the capacity. AREMA Chapter 8 requires e ≤ B/6 under unfactored loads so no part of the base goes into tension.

The check applies to every abutment footing and retaining wall base under earth pressure. Braking forces add to the moment on abutments, so check the case with braking as well.

Question 6.1-3: Pipe Pile Capacity by the Meyerhof SPT Method

Problem Statement

A Class I railroad is replacing a ballast-deck trestle with a new bridge on closed-end pipe piles driven into uniform sand. The piles will be 40 ft long with the tip 30 ft into the sand, and no load test is planned. The engineer must estimate the allowable pile capacity from SPT blow counts for the bent design.

Given

VariableValueDescription
Pile12 in. closed-end pipe; L = 40 ft; Db = 30 ft
N6018Uniform SP sand
FS3.0No load test

Required

  • Allowable capacity

Equations

  1. Eq. 6.1-15: fs = 0.02 N60 (tsf) — driven displacement pile
  2. Eq. 6.1-16: qp = 0.4 N60(Db/B) ≤ 4N60 (tsf)

Steps

Step 1 · Side (Eq. 6.1-15)
0.36 tsf × 3.14 × 40 = 0.36 × 125.7
Qs = 45.3 tons
↓
Step 2 · Tip (Eq. 6.1-16)
0.4 × 18 × 30 = 216 tsf; limit 72 tsf; 72 × 0.785
Qp = 56.5 tons
↓
Step 3 · Allowable
101.8 / 3.0
33.9 tons = 67.9 kips
↓
Solution
Qallow ≈ 34 tons (68 kips).

Solution

Qult = 101.8 tons; Qallow ≈ 34 tons (68 kips).

The tip limit governs, so driving deeper into the same sand adds only side resistance. Refine with WEAP and confirm with CAPWAP or a load test; SPT-based pile capacities carry ±30 to 40% uncertainty.

Question 6.1-4: Group Efficiency of a Concrete Pile Group

Problem Statement

A pier of a new railroad bridge is supported by a 4 × 3 group of 16-in. square concrete piles at 4-ft spacing, each with the allowable capacity shown. The engineer must compute the group efficiency and the capacity of the group to compare with the pier load from the design train.

Given

VariableValueDescription
D16 in. = 1.333 ft
S4.0 ft (S/D = 3.0)
m, n4 and 3
Qallow120 kips per pile

Required

  • Group efficiency and group capacity

Equations

  1. Eq. 6.1-17: η = 1 − θ[(n − 1)m + (m − 1)n] / (90 m n); θ = arctan(D/S) in degrees — Converse-Labarre group efficiency

Steps

Step 1 · θ
arctan(1.333/4.0)
18.4°
↓
Step 2 · η
1 − 18.4(8 + 9)/1,080 = 1 − 0.290
0.710
↓
Step 3 · Group
12 × 120 × 0.710
1,022 kips against 1,440 kips summed
↓
Solution
η = 0.71; group 1,022 kips.

Solution

η = 0.71; group capacity 1,022 kips, 29% below the sum of individual piles.

If the demand is close to the individual sum, spread the piles to S/D of 3.5 to 4 or add piles. In clay, check block failure as well; it can govern over the efficiency-reduced sum.

Question 6.1-5: Why Micropiles for Underpinning Passenger Structures

Problem Statement

A passenger railroad needs to underpin the foundations of a station canopy and an overhead bridge pier that sit within a few feet of high-speed track, where geometry tolerances are tight and track windows are short. The engineer must explain why micropiles are the preferred foundation and which parameters govern their design.

Given

VariableValueDescription
SettingUnderpinning existing structures on a passenger corridor
ConstraintsTight geometry limits (49 CFR 213 Subpart G); short track windows

Required

  • Why micropiles are preferred
  • Which parameters govern their design

Equations

  1. Eq. 1: Qult = fb π Ddrill Lb — bond-zone capacity

Steps

Step 1 · Vibration
Rotary or rotary-percussion drilling of small casings causes little vibration, protecting track geometry and existing foundations.
↓
Step 2 · Access
Compact rigs fit short track windows and low headroom.
↓
Step 3 · Load path
Load goes past soft fill to competent soil or rock.
↓
Step 4 · Design parameters
Grout-to-ground bond fb, bond length Lb, and the structural capacity of the bar or casing.
↓
Solution
Low vibration, small rigs, deep load transfer; designed on bond stress.

Solution

Micropiles install with little vibration from compact rigs that fit short track windows, and they carry load past soft fill. Their design is governed by grout-to-ground bond stress, bond length and the steel section.

Bond stresses come from the FHWA micropile manual and must be confirmed by load tests (ASTM D1143), commonly to 200% of design load on a share of piles agreed with the railroad.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
6.1.14 Cross-References
TopicChapter
SPT N₆₀ and (N₁)₆₀ correction proceduresChapter 4.1
CPTu tip resistance and friction ratio for soil profilingChapter 5.1
Soil classification for bearing capacity input (c, φ', γ)Chapter 2.2
Groundwater and effective stress; scour potentialChapter 2.8
Settlement analysis (companion to bearing capacity)Chapter 6.2
Slope stability of embankment around abutmentsChapter 6.3
Seismic and liquefaction effects on foundation capacityChapter 6.5
Ground improvement where bearing capacity is inadequateChapter 7.2
Retaining wall foundation designChapter 7.1
Track subgrade stress distribution below ballastChapter 2.3
Pile driving monitoring and CAPWAPChapter 5.3
Foundation analysis documentation in geotechnical reportsChapter 8.4
Consolidation and triaxial test data for c, φ', s_u inputChapter 5.2

End of Chapter 6.1 — Foundation Engineering: Bearing Capacity

Primary source: USACE EM 1110-1-1804, Geotechnical Investigations (January 2001). Bearing capacity equations follow Vesić (1973) as presented in FHWA GEC No. 5, AASHTO LRFD Bridge Design Specifications, and AREMA MRE Chapter 8.

6.1.15 Apps and Analytical Tools47

The web apps and the Geotechnical Analysis Suite calculators and workbook guides for this part of the analysis, gathered here from across the manual in the November 2026 restructure: 47 tools (20 interactive calculators). Where a tool applies to a particular section of this chapter it is also placed in that section in an orange tools strip. Each row lists the chapters and sections where the tool is used. Calculators open on dirtbert.com (sign-in required).

Apps

Each app runs in a web browser on a desktop or a phone, with nothing to install. How to use the apps (1.0.3).

Tools

Deep Foundations
DFAuger Cast Pile Design — ASD (GEC 8)Used in Chapter 6.1, 6.1.5 Deep Foundation Bearing Capacityguide onlyGuide
DFBroms Method — Lateral PileUsed in Chapter 6.1, 6.1.6 Pile Group Efficiencyguide onlyGuide
DFCSL Analysis (Crosshole Sonic Logging)Used in Chapter 5.3, 5.3.4 Pile Installation Monitoringguide onlyGuide
DFDrilled Shaft Design — Soils, LRFD (AASHTO 2018)Used in Chapter 6.1, 6.1.5 Deep Foundation Bearing CapacityCalculator ▸Guide
DFLPILE Lateral p-y MultiplierpreliminaryUsed in Chapter 6.1, 6.1.6 Pile Group EfficiencyCalculator ▸Guide
DFPile Driving with DowndragUsed in Chapter 6.1, 6.1.5 Deep Foundation Bearing CapacityCalculator ▸Guide
DFPile Length — LRFD Modified IDOT/ENR FormulaUsed in Chapter 6.1, 6.1.5 Deep Foundation Bearing CapacityCalculator ▸Guide
DFPile Load Test Calculations (Compression)Used in Chapter 5.3, 5.3.5 Static Axial Load Testing (ASTM D1143)guide onlyGuide
DFPile PDA Field Data ComputationsUsed in Chapter 5.3, 5.3.4 Pile Installation Monitoringguide onlyGuide
DFPipe Pile API AnalysisUsed in Chapter 6.1, 6.1.5 Deep Foundation Bearing CapacityCalculator ▸Guide
DFRock-Socket Drilled Shaft DesignUsed in Chapter 6.1, 6.1.5 Deep Foundation Bearing CapacityCalculator ▸Guide
Data Templates
DTData SpreadsheetUsed in Chapter 8.4, 8.4.8 Calculation Appendixguide onlyGuide
DTData — BridgeUsed in Chapter 8.4, 8.4.8 Calculation Appendixguide onlyGuide
DTData — MSE WallUsed in Chapter 8.4, 8.4.8 Calculation Appendixguide onlyGuide
DTData — TemplateUsed in Appendices A–C, APPENDIX B — LABORATORY TEST RESULTS TABLE TEMPLATEguide onlyGuide
DTSoil DataUsed in Chapter 5.2, Applies to the chapter as a whole; Chapter 8.4, 8.4.5 Laboratory Data Tablesguide onlyGuide
Earth Retaining Structures
ERAnchored Soldier Pile Wallneeds workUsed in Chapter 7.1, 7.1.4 Wall Types and SelectionCalculator ▸Guide
ERGeoGrid Bridge (GGB) v3.0Used in Chapter 7.2, 7.2.8 Geosynthetic Reinforcementguide onlyGuide
ERGeogrid CalculationsUsed in Chapter 7.2, Applies to the chapter as a wholeguide onlyGuide
ERLateral Earth Pressure — Coulomb & RankineUsed in Chapter 7.1, 7.1.2 Lateral Earth Pressure TheoryCalculator ▸Guide
ERLateral Earth Pressure — Rankine Equivalent-Fluid TablesUsed in Chapter 7.1, 7.1.2 Lateral Earth Pressure TheoryCalculator ▸Guide
ERLateral Pressures on StructuresUsed in Chapter 2.1, 2.1.7 Structural Foundations Supporting or Adjacent to the Track; Chapter 7.1, 7.1.3 Surcharge Loading — Cooper E-80 Train LoadCalculator ▸Guide
ERMSE Wall External StabilityUsed in Chapter 7.1, 7.1.4 Wall Types and SelectionCalculator ▸Guide
ERSheet Pile DesignUsed in Chapter 7.1, 7.1.4 Wall Types and SelectionCalculator ▸Guide
ERSoil Nail WallUsed in Chapter 7.1, 7.1.4 Wall Types and Selection; Chapter 7.2, 7.2.8 Geosynthetic Reinforcementguide onlyGuide
ERTrial Wedge MethodUsed in Chapter 7.1, 7.1.2 Lateral Earth Pressure Theoryguide onlyGuide
ERWall Soil Pressures Template for Shoring SuitesUsed in Chapter 7.1, 7.1.4 Wall Types and SelectionCalculator ▸Guide
Field Forms & Logs
FFBoring Data Summary SheetUsed in Appendices A–C, APPENDIX A — BOREHOLE LOG TEMPLATE; Chapter 4.1, 4.1.7 Annotated Sample Boring Logguide onlyGuide
FFDaily Log — Compaction Testing (Nuclear Gauge)Used in Chapter 5.3, 5.3.2 Compaction Testingguide onlyGuide
FFDaily Log — GeneralUsed in Chapter 4.1, 4.1.2 Drilling Method Selectionguide onlyGuide
FFDynamic Cone Field LogUsed in Chapter 5.1, 5.1.2 Cone Penetration Test (CPT and CPTu); Chapter 5.3, 5.3.2 Compaction TestingCalculator ▸Guide
FFNuclear Density — SoilUsed in Chapter 5.3, 5.3.2 Compaction Testingguide onlyGuide
FFOne Call FormUsed in Chapter 4.1, 4.1.2 Drilling Method Selectionguide onlyGuide
FFOne Call Utility ChecklistUsed in Chapter 3.9, 3.9.4 Boring Location Planning — Criteria by Project Typeguide onlyGuide
FFRR Boring Info (blank)Used in Appendices A–C, APPENDIX A — BOREHOLE LOG TEMPLATE; Chapter 4.1, 4.1.7 Annotated Sample Boring Logguide onlyGuide
FFRock Core Log & RQDUsed in Chapter 4.1, 4.1.5 Rock Core Recovery and RQDguide onlyGuide
Project Management & Checklists
PMCalculation Sheet (blank)Used in Appendices A–C, APPENDIX C — GEOTECHNICAL SPECIAL PROVISIONS (GSP) TEMPLATE; Chapter 8.4, 8.4.8 Calculation Appendixguide onlyGuide
PMRR Bridge Site Recon ChecklistUsed in Chapter 1.1, 1.1.10 Grade & Slope Stabilization Program — Roles and Processguide onlyGuide
PMRR Summary of FindingsUsed in Chapter 1.1, 1.1.12 Practical Recommendations; Chapter 8.4, 8.4.3 Report Structure — Required Sectionsguide onlyGuide
Shallow Foundations
SFBearing Capacity — AASHTO LRFDUsed in Chapter 6.1, 6.1.2 Shallow Foundation Bearing Capacity — Vesić General EquationCalculator ▸Guide
SFBearing Capacity — Terzaghi & VesićUsed in Chapter 6.1, 6.1.2 Shallow Foundation Bearing Capacity — Vesić General EquationCalculator ▸Guide
SFFooting on SlopeUsed in Chapter 6.1, 6.1.2 Shallow Foundation Bearing Capacity — Vesić General EquationCalculator ▸Guide
SFMachine Foundation Design & Dynamic Soil PropertiesUsed in Chapter 6.1, 6.1.2 Shallow Foundation Bearing Capacity — Vesić General EquationCalculator ▸Guide
SFRock — Shallow FoundationsUsed in Chapter 6.1, 6.1.2 Shallow Foundation Bearing Capacity — Vesić General EquationCalculator ▸Guide
Soil & Rock Properties
SPCPT–SPT CorrelationUsed in Chapter 5.1, 5.1.2 Cone Penetration Test (CPT and CPTu)guide onlyGuide
SPDynamic Cone PenetrometerUsed in Chapter 2.3, 2.3.6 Track Modulus; Chapter 5.1, 5.1.2 Cone Penetration Test (CPT and CPTu)Calculator ▸Guide
SPVane ShearUsed in Chapter 5.1, 5.1.3 Vane Shear Test (VST)guide onlyGuide

Calculator: Shallow Foundation Bearing Capacity (Section 6.1.2.6)

Calculator: Elastic Settlement of Footings (Section 6.2.3.1)

6.1.19 Laterally Loaded Piles and Shafts by Broms’ Method

Signal masts, catenary and communication poles, sign bridges, light towers and the piles of retaining walls and bridge bents along the track all carry horizontal load: wind on the structure and wires, braking and centrifugal forces, earth pressure and impact. Broms’ method (1964) is the standard hand check of the ultimate lateral load. It treats the soil reaction as a simple pressure diagram and asks which happens first: the soil around a short, stiff pile fails as the pile rotates or translates, or a long pile forms a plastic hinge at the yield moment of its section. It is quick, it brackets the answer, and it shows whether more embedment helps (short pile) or only a stronger section will (long pile). It gives no deflection; the working-load deflection still comes from p-y analysis (Section 6.1.6 tools).

6.1.19.1 Method

In clay the resistance is taken as zero over the top 1.5 diameters, where the soil can flow up and around the pile, and 9sub below. In sand the passive pressure on the pile is taken as three times the Rankine value, 3Kpγ′z, which allows for the three-dimensional wedge in front of a narrow pile. The two free-head cases used most along the track are:

Equation 6.1-26. Broms, free head, cohesive soil

Short: Hu(e + 1.5b + 0.5f) = 2.25 su b g²;   Long: Hu(e + 1.5b + 0.5f) = My;   f = Hu/(9sub),   L = 1.5b + f + g

f = depth below 1.5b to the point of zero shear (maximum moment); g = remaining length below it. The short-pile equation is solved by trial (the calculator uses bisection); the long-pile equation is a quadratic in Hu.

Equation 6.1-27. Broms, free head, cohesionless soil

Short: Hu = 0.5γ′bL³Kp/(e + L);   Long: Hu(e + 0.67f) = My,   f = 0.82√(Hu/(γ′bKp))

Kp = tan²(45° + φ′/2); γ′ = effective (buoyant below the water table) unit weight.

Table 6.1-7. Broms’ cases for a fixed head (cap restrains rotation, load at the ground surface)
BehaviorCohesive soilCohesionless soil
Short (translates)Hu = 9sub(L − 1.5b), if Hu(1.5b + 0.5f) ≤ MyHu = 1.5γ′bL²Kp, if (2/3)HuL ≤ My
Intermediate (hinge at head)Hu(1.5b + 0.5f) − My = 2.25subg²Hu = (0.5γ′bL³Kp + My)/L
Long (hinges at head and depth)Hu = 2My/(1.5b + 0.5f)Hu = 2My/(0.67f)

FHWA NHI-05-042 (superseded by GEC 12, FHWA-NHI-16-009 (2016)) recommends a factor of safety of about 2.5 on the Broms ultimate load. The yield moment is My = FyZ for a steel pile (plastic modulus Z) and the nominal flexural strength of the section for a reinforced concrete shaft.

6.1.19.2 Worked example

Example 6.1-4: Drilled Shaft for a Signal Mast in Stiff Clay

A cantilever signal mast on a Class I railroad located in Ohio sits on a 30-in. drilled shaft in stiff clay. Wind on the mast and signal heads gives a working lateral load of 12 kips whose resultant acts 20 ft above the ground. The shaft head is free to rotate.

H = 12 kips workinge = 20 ftL = 15 ftb = 30 in.stiff claysu = 1,500 psfGivenb = 30 in., L = 15 ft, e = 20 ftsu = 1,500 psf (stiff clay)My = 900 kip-ft; free headH = 12 kips; FS = 2.5RequiredHu (short or long), H allowShortest embedment for 12 kips
Free-head drilled shaft for a signal mast with the wind load acting 20 ft above the ground.

Given

VariableValueDescription
SoilStiff CL, su = 1,500 psfUU triaxial, upper 15 ft
b30 in. = 2.50 ftShaft diameter
L15 ftEmbedded length
e20 ftHeight of load resultant
My900 kip-ftNominal flexural strength of the shaft
H12 kipsWorking lateral load
FS2.5FHWA for Broms’ method

Required

  • Ultimate lateral load for short and long behavior, and which governs
  • Allowable lateral load and whether 15 ft of embedment is enough
  • Shortest embedment that carries the working load

Equations

  1. Eq. 6.1-26: f = Hu/(9sub); g = L − 1.5b − f — zone lengths
  2. Eq. 6.1-26: Hu(e + 1.5b + 0.5f) = 2.25subg² — short pile
  3. Eq. 6.1-26: Hu(e + 1.5b + 0.5f) = My — long pile
  4. Hallow = Hu/FS

Steps

Step 1 · Soil resistance
9sub = 9 × 1,500 × 2.50; 1.5b = 3.75 ft
33,750 lb/ft below 3.75 ft; L − 1.5b = 11.25 ft
↓
Step 2 · Short pile (Eq. 6.1-26)
Trial Hu = 36.0 kips: f = 36,026/33,750 = 1.067 ft; g = 11.25 − 1.067 = 10.18 ft
Hu,short = 36.0 kips
Spot check: Left side 36,026 × (20 + 3.75 + 0.53) = 874,800 ft-lb; right side 2.25 × 1,500 × 2.50 × 10.18² = 874,900 ft-lb. Balanced.
↓
Step 3 · Long pile (Eq. 6.1-26)
(1/(2 × 33,750))Hu² + 23.75Hu − 900,000 = 0
Hu,long = 37.0 kips
↓
Step 4 · Governing and allowable
min(36.0, 37.0) = 36.0 kips (short); 36.0/2.5
Hallow = 14.4 kips ≥ 12 kips
Spot check: The maximum moment at ultimate, 875 kip-ft, is just below My = 900 kip-ft, consistent with the short mode governing by a small margin.
↓
Step 5 · Minimum embedment
Find L with Hu = 2.5 × 12 = 30 kips
L = 13.9 ft
↓
Solution
Hallow = 14.4 kips; 15 ft of embedment is adequate in strength (13.9 ft minimum).

Solution

The 30-in. shaft 15 ft long has an ultimate lateral capacity of 36.0 kips (short-pile behavior) and an allowable load of 14.4 kips, above the 12-kip working load.

Because the short and long capacities are close, the design is balanced: a longer shaft gains little because the section would yield at about 37 kips. Deflection at 12 kips still needs a p-y check against the signal maintainer’s tolerance, and the top 1.5b of clay that the method ignores must not be disturbed by ditching or cable trenching beside the mast.

Open the laterally loaded pile calculator →
Broms’ short, intermediate and long modes for a free or fixed head in clay or sand, the governing ultimate and allowable lateral load, the embedment needed for a working load, and a capacity-versus-length chart.

6.1.19.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • FHWA NHI-05-042 (superseded by GEC 12, FHWA-NHI-16-009 (2016)), Design and Construction of Driven Pile Foundations, Vol. I (2006): Broms’ method for laterally loaded piles.Find source ↗
  • B.B. Broms (1964), Lateral resistance of piles in cohesive soils; Lateral resistance of piles in cohesionless soils. Journal of the Soil Mechanics and Foundations Division, ASCE, 90(SM2), 27–63, and 90(SM3), 123–156.Find source ↗
  • B.M. Das, Principles of Foundation Engineering: Broms’ ultimate lateral resistance.Find source ↗
6.1.20 Micropile Axial Capacity

Micropiles are small-diameter (typically 5 to 12 in.) drilled and grouted piles with a steel casing and a center bar. Along the track they are used where a conventional pile rig cannot work: underpinning a bridge pier or abutment, supporting a load-transfer platform over soft ground, stitching an unstable fill, and building the micropile and tieback walls placed from the shoulder during track windows (Chapter 7.1). Because the pile is slender, almost all of the load goes into the ground through grout-to-ground bond along the bond zone; end bearing is ignored. The capacity is the smaller of that bond capacity and the structural capacity of the steel and grout in the cased and uncased lengths.

6.1.20.1 Method

Equation 6.1-28. Allowable grout-to-ground bond capacity (FHWA NHI-05-039)

PG,allow = (αbond/FS) π Db Lb

αbond = ultimate grout-to-ground bond (Table 6.1-8); Db = drilled diameter of the bond zone; Lb = bond length; FS = 2.0 with load testing (2.5 for seismic loading or creep-susceptible soil).

Equation 6.1-29. Allowable structural capacity (FHWA ASD)

Compression: Pc,allow = 0.40f′cAgrout + 0.47Fy(Abar + Acasing);   Tension: Pt,allow = 0.55Fy(Abar + Acasing)

Fy = the lower of the bar and casing yield strengths (strain compatibility). In the uncased bond zone only the bar and grout count. Flush-threaded casing joints may carry less tension than the pipe; count the casing in tension only to the joint’s rated strength.

Table 6.1-8. Typical ultimate grout-to-ground bond, psi (FHWA NHI-05-039 Table 5-3, converted from kPa). Type A gravity grout; B pressure grout through the casing; C single global post-grout; D multiple post-grout
GroundType AType BType CType D
Silt and clay, soft to medium plastic5–105–147–177–21
Silt and clay, stiff, dense to very dense7–1710–2814–2814–28
Sand, fine, loose to medium dense10–2110–2814–2814–35
Sand and gravel, medium to very dense14–3117–5221–5221–56
Gravel, medium to very dense14–3817–5221–5221–56
Glacial till, medium to very dense, cemented14–2814–4517–4517–49
Soft shale30–80–––
Slate and hard shale75–200–––
Limestone150–300–––
Sandstone75–250–––
Granite and basalt200–610–––

Bond values vary with the drilling method, flushing and grouting pressure as much as with the soil, so the design value must be confirmed by a verification test to 2.0 times the design load on a sacrificial or production pile and by proof tests (typically to 1.67 times) on a share of the production piles.

6.1.20.2 Worked example

Example 6.1-5: Micropile Underpinning a Bridge Abutment

An abutment on a Class I railroad located in Pennsylvania is underpinned with micropiles drilled through the footing into dense sand and gravel. Each pile carries 80 kips in compression and 40 kips of uplift under the overturning case.

abutment footingPc = 80, Pt = 40 kipscasing 7.0 × 0.50 in.Lb = 20 ftDb = 8 in.dense sand and gravelGivenDb = 8 in., Lb = 20 ft; Type B groutαbond = 34.8 psi; FS = 2.0Casing 7.0 × 0.50 in., 80 ksi#14 bar, 75 ksi; f′c = 4,000 psiRequiredBond and structural capacityGoverning allowable loadsBond length needed
Micropile drilled through the abutment footing: cased through the upper soil, grouted bond zone in dense sand and gravel.

Given

VariableValueDescription
GroundDense sand and gravelBond zone
GroutingType B (pressure through casing)
αbond34.8 psiMid-range of 17.4–52.2 psi; to be verified by test
Db, Lb8 in.; 20 ftBond zone
Casing7.0 in. OD × 0.50 in. wall, Fy = 80 ksiCased length
Bar#14, A = 2.25 in.², Fy = 75 ksiFull length
f′c4,000 psiGrout
FS2.0With load testing
Pc, Pt80 kips; 40 kipsDesign loads

Required

  • Allowable bond capacity
  • Structural capacity of the cased and uncased lengths
  • Governing allowable compression and tension; bond length needed

Equations

  1. Eq. 6.1-28: PG = (αbond/FS)πDbLb
  2. Eq. 6.1-29: Pc = 0.40f′cAg + 0.47Fy(Abar + Acasing) — compression
  3. Eq. 6.1-29: Pt = 0.55FyAbar — tension, casing joints not counted
  4. Lb,req = P × FS/(αbondπDb)

Steps

Step 1 · Bond capacity (Eq. 6.1-28)
34.8 × π × 8 × 240 = 210,000 lb; /2.0
PG = 105.0 kips (5.25 kips per ft)
↓
Step 2 · Areas
Acasing = π/4(7.0² − 6.0²); grout in casing π/4(6.0²) − 2.25; grout in bond zone π/4(8²) − 2.25
10.21 in.²; 26.0 in.²; 48.0 in.²
↓
Step 3 · Structural compression (Eq. 6.1-29)
Cased: 0.40(4.0)(26.0) + 0.47(75)(2.25 + 10.21); uncased: 0.40(4.0)(48.0) + 0.47(75)(2.25)
Cased 480.9 kips; uncased 156.1 kips
Spot check: Fy = min(80, 75) = 75 ksi for strain compatibility; the steel term dominates the cased length (439 of 481 kips).
↓
Step 4 · Structural tension
0.55 × 75 × 2.25
92.8 kips (bar only)
↓
Step 5 · Governing
Compression min(105.0, 480.9, 156.1); tension min(105.0, 92.8)
105.0 kips (bond) and 92.8 kips (bar)
↓
Step 6 · Bond length
80,000 × 2.0 / (34.8 × π × 8 × 12)
Lb,req = 15.2 ft ≤ 20 ft
Spot check: Check: 15.2 ft × 5.25 kips/ft = 80 kips.
↓
Solution
Allowable 105.0 kips in compression and 92.8 kips in tension, both above the design loads.

Solution

The micropile carries 105 kips in compression, limited by grout-to-ground bond, and 92.8 kips in tension, limited by the bar in the uncased bond zone. The 20-ft bond length exceeds the 15.2 ft needed.

The bond value is the weak link and must be confirmed: run a verification test to 160 kips (2.0 × 80) before production, and proof-test about 5% of the production piles. If the test shows lower bond, lengthen the bond zone rather than changing the section.

Open the micropile calculator →
Grout-to-ground bond from the FHWA ranges for the ground and grouting method, cased and uncased structural capacity in compression and tension, the governing allowable loads and the bond length for a design load.

6.1.20.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • FHWA NHI-05-039, Micropile Design and Construction (Sabatini, Tanyu, Armour, Groneck and Keeley, 2005): Chapter 5, Table 5-3 and the allowable structural capacities; Chapter 7, load testing.Official page ↗
  • Library, Railroad / AREMA / AREMA Comm 1 / Micropile Retaining Walls: micropile and soil-nail walls built from the track for shoulder repairs (company and site names withheld).Find source ↗
6.1.21 Load Distribution in a Pile Group

Bridge piers and abutments, retaining walls on piles and signal bridge foundations carry eccentric loads: earth pressure, braking and wind tilt the resultant away from the center of the pile group. With a rigid cap the pile heads stay in a plane, so the group behaves like a beam cross-section in combined axial load and bending, in which each pile is a unit area. The pile loads then follow from P/n ± Mc/I. The check shows whether the most heavily loaded pile is within its allowable capacity and whether any pile goes into tension.

6.1.21.1 Method

Equation 6.1-30. Pile load in a group under a rigid cap

pi = P/n + My(xi − x̄)/Σ(x − x̄)² + Mx(yi − ȳ)/Σ(y − ȳ)²

n = number of piles; x̄, ȳ = centroid of the group; My, Mx = moments about the centroidal axes, including the eccentricity of P. Valid for vertical piles of equal stiffness in a layout symmetric about its centroidal axes.

For a long wall on several rows of piles at different spacings, analyze a “repeating length” that contains a whole pattern of piles and apply the wall load for that length.

6.1.21.2 Worked example

Example 6.1-6: Pile Loads Under a Retaining Wall Footing

A cantilever retaining wall along a Class I railroad located in Ohio is founded on three rows of piles 3 ft apart. Piles are at 4 ft centers in the front and middle rows and 6 ft in the rear row. The wall load is 20 kips per foot with its resultant 3 ft 3 in. from the front row (Hicks, 2000, load distribution in a pile group).

P = 240 kipsxP = 3.25 ft3 ft3 ft3 piles32GivenRows at x = 0, 3, 6 ft3 + 3 + 2 piles per 12-ft lengthP = 240 kips at xP = 3.25 ftAllowable 45 kips per pileRequiredLoad per pile in each rowTension check
Section through the wall footing over one 12-ft repeating length: three rows of piles under an eccentric wall load.

Given

VariableValueDescription
Rowsx = 0, 3 and 6 ftFront, middle, rear
Repeating length12 ftContains 3 + 3 + 2 piles
P20 kips/ft × 12 ft = 240 kipsLoad on the repeating length
xP3.25 ftFrom the front row
Allowable pile load45 kipsCompression

Required

  • Centroid and moment of inertia of the group
  • Load in each row
  • Equilibrium check

Equations

  1. Eq. 6.1-30: x̄ = Σx/n; I = Σ(x − x̄)²
  2. Eq. 6.1-30: M = P(xP − x̄)
  3. Eq. 6.1-30: p = P/n + M(x − x̄)/I

Steps

Step 1 · Centroid and I
x̄ = (3 × 0 + 3 × 3 + 2 × 6)/8; I = 3(2.625)² + 3(0.375)² + 2(3.375)²
x̄ = 2.625 ft; I = 43.9 ft²
↓
Step 2 · Moment
240 × (3.25 − 2.625)
M = 150 kip-ft
↓
Step 3 · Pile loads
240/8 = 30.0; M/I = 3.42 kips/ft; front 30.0 − 3.42 × 2.625; middle 30.0 + 3.42 × 0.375; rear 30.0 + 3.42 × 3.375
Front 21.0; middle 31.3; rear 41.5 kips
↓
Step 4 · Equilibrium
3(21.0) + 3(31.3) + 2(41.5); moments about the front row 3(31.3)(3) + 2(41.5)(6)
240 kips; 780 kip-ft = 240 × 3.25
Spot check: Both match the applied load and its moment, as in Hicks.
↓
Solution
Front 21.0, middle 31.3, rear 41.5 kips per pile; all in compression and within 45 kips.

Solution

The rear-row piles carry the most, 41.5 kips each, within the 45-kip allowable; no pile is in tension.

The heavier rear row is why it has wider spacing in plan but the most load per pile: moving the resultant 0.6 ft behind the centroid adds 11.5 kips to each rear pile. If train surcharge or seismic load moves the resultant further back, check the front row for uplift.

Open the pile group load calculator →
Pile loads under a rigid cap from any pile layout, an eccentric vertical load and applied moments about both axes, with tension and capacity flags and the equilibrium check.

6.1.21.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • T.G. Hicks (ed.), Handbook of Civil Engineering Calculations, McGraw-Hill (2000): Section 1, load distribution in a pile group; Section 4, load distribution among piles.Find source ↗Library entry
  • FHWA NHI-05-042 (superseded by GEC 12, FHWA-NHI-16-009 (2016)), Design and Construction of Driven Pile Foundations (2006): pile group load distribution.Find source ↗
6.1.22 Downdrag, Dragload and the Neutral Plane

When the ground around a pile settles more than the pile, the soil drags the pile down. The downward shear is called negative skin friction and the force it adds is the dragload. It can be as large as the design load. On railroads it most often comes from raising an approach embankment over soft clay at a bridge, widening an embankment beside an existing pile-supported structure, lowering the groundwater (dewatering, drainage improvements, pumping), and wetting of collapsible soil (Chapter 2.9). It needs part of the pile to be fixed: if the whole pile moves down with the soil, no dragload develops (Bowles 1996; Das and Sivakugan 2019).

6.1.22.1 The neutral plane

Above the neutral plane the soil moves down relative to the pile and the friction acts downward; below it the pile moves down relative to the soil and the friction acts upward. The axial load in the pile is greatest at the neutral plane, and there the pile and the soil settle by the same amount. For a pile bearing on rock or dense sand the neutral plane is close to the top of the bearing layer. For a floating pile it lies within the soft layer; measurements reviewed by Bowles place it between one-third and one-half of the embedded length above the pile point, with L/3 when the point carries much of the load.

Equation 6.1-31. Dragload, granular fill over consolidating clay (β method)

fn = K′σ′o tanδ′,   K′ = 1 − sinφ′,   σ′o = γfHf + γ′z
Qn = p K′ tanδ′ γfHf L1 + p K′ tanδ′ γ′ L1² / 2

p = pile perimeter; z measured down from the top of the clay; L1 = depth of the neutral plane below the top of the clay; δ′ = 0.5 to 0.7φ′. Use moist unit weights above the water table. For a clay fill over sand, integrate over the fill height only: Qn = p K′ tanδ′ γfHf²/2 (Das and Sivakugan 2019, Eqs. 12.130 and 12.133).

Equation 6.1-32. Depth of the neutral plane for a floating pile

L1² + (2γfHf/γ′) L1 − (L − Hf)[(L − Hf)/2 + γfHf/γ′] = 0

L = pile length measured from the top of the fill, so L − Hf is the embedment in clay. From equating downward friction above and upward friction below the neutral plane with no point load (Bowles 1996, Eq. 18-18; Das and Sivakugan 2019, Eq. 12.131). For an end-bearing pile take L1 = L − Hf.

Equation 6.1-33. Largest axial load in the pile

Pmax = PD + Qn   (at the neutral plane)

PD = permanent load only. Transient loads (live load, braking) are not added to the dragload: when they act, the pile moves down relative to the soil and the negative friction near the neutral plane reverses.

6.1.22.2 Pile groups

For closely spaced piles the soil between them moves with the group, and the dragload on the group can be less than the sum for single piles. Bowles recommends checking both and using the smaller: the sum of single-pile dragloads, and the shear on the perimeter of the block plus the weight of the soil trapped between the piles, Qn = fsLfPg + γLfA, where Pg and A are the perimeter and plan area of the group. Corner and edge piles carry more dragload than interior piles.

6.1.22.3 What to check and how to reduce it

  • Structural: PD + Qn at the neutral plane against the pile section, including driving damage allowances.
  • Geotechnical: count only resistance below the neutral plane toward the design capacity; resistance in the settling layers does not support the structure in the long term (Section 6.1.5.5 and Table 11-S2 exclusions).
  • Settlement: the pile head settles as much as the soil does at the neutral plane plus the elastic shortening of the pile. A low neutral plane in a stiff layer means small settlement; a floating pile in consolidating clay settles with the clay.
  • Cap: if the fill under a pile cap settles away from it, the cap weight goes onto the piles; in expansive clay the reverse (uplift on the cap and piles) needs a void form.
  • Reduction: place the fill and let it consolidate (with surcharge or wick drains) before driving piles; lightweight fill (Section 7.2); bitumen coating or casing in the downdrag zone; end-bearing piles sized for the dragload.

For railroad work: Most dragload on railroad bridges is self-inflicted: the approach is raised or widened at the same time as the abutment piles are driven. Sequence the work so the approach fill is placed and monitored (settlement plates, Chapter 5.3) before the piles go in wherever the schedule allows. Where track must stay in service and the fill must be placed later, design the piles for the dragload and expect the approach to settle relative to the back wall; plan for a transition (approach slab, graded ballast depth or geogrid-reinforced transition) and for surfacing. The Calculators table lists a driven pile downdrag tool for this check.

6.1.22.4 Worked example

Example 6.1-7: Dragload on Abutment Piles Behind a New Approach Fill

Problem Statement

A bridge on a Class I railroad located in Louisiana is being replaced, and the approach embankment is raised 6 ft with granular fill at the same time. The new abutment is on 14-in. steel pipe piles driven through 40 ft of soft clay into dense sand. The clay will consolidate under the new fill after the piles are driven, so the soil will move down past the piles. Estimate the dragload and the largest axial load in a pile (Section 6.1.22).

New granular fill, Hf = 6 ft, γ = 120 pcf Soft clay, 40 ftγsat = 112 pcf, φ′ = 26° Dense sand (pile bears here) GWT at original ground 14-in. pipe pile, PD = 110 kips soil settles neutral plane? L1 Required: (a) dragload Qn, end-bearing pile (b) L1 and Qn, floating pile (c) maximum axial load and stress Black = given; red = required
Figure 6.1-17. Given and required for Example 6.1-7: pile through new fill and soft clay.

Given

VariableValueDescription
Hf6 ft; γf = 120 pcfNew granular fill above the water table
Clay40 ft; γsat = 112 pcf; φ′ = 26°Groundwater at the original ground surface, so γ′ = 112 − 62.4 = 49.6 pcf
D14 in. (wall 0.375 in.)Steel pipe pile, fy = 45 ksi, As = 16.05 in.²
PD110 kipsPermanent (dead) load per pile
δ′0.6φ′Pile–soil friction angle (Das: 0.5 to 0.7φ′)

Required

  • (a) Dragload Qn if the pile is end-bearing (neutral plane at the top of the sand)
  • (b) Depth of the neutral plane L1 and Qn if the pile were floating in the clay
  • (c) Largest axial load and steel stress for case (a)

Equations

  1. Eq. 6.1-31: K′ = 1 − sin φ′; Qn = p K′ tanδ′ γfHf L1 + p K′ tanδ′ γ′ L1²/2
  2. Eq. 6.1-32: L1² + (2γfHf/γ′) L1 − (L − Hf)[(L − Hf)/2 + γfHf/γ′] = 0
  3. Eq. 6.1-33: Pmax = PD + Qn at the neutral plane

Steps

Step 1 · Coefficients
K′ = 1 − sin 26° = 0.562; δ′ = 15.6°, tanδ′ = 0.279; K′tanδ′ = 0.157; p = π × 14/12 = 3.67 ft
K′tanδ′ = 0.157
Spot check: Within the 0.15 to 0.30 range usually back-figured for soft clays; Das quotes 0.22 for the Oslo case.
↓
Step 2 · (a) End-bearing, L1 = 40 ft
3.67 × 0.157 × 120 × 6 × 40 = 16,550 lb; 3.67 × 0.157 × 49.6 × 40²/2 = 22,810 lb
Qn ≈ 39.4 kips
↓
Step 3 · (b) Floating pile, neutral plane
Coefficient 2(120)(6)/49.6 = 29.0; constant 40(20 + 14.5) = 1,381; L1 = [−29.0 + √(29.0² + 4 × 1,381)]/2
L1 = 25.4 ft below the clay surface; Qn ≈ 19.7 kips
Spot check: L1/40 = 0.63, inside the range Bowles gives from measurements (neutral point between L/3 and L/2 above the pile point, that is 0.50 to 0.67 of the length down).
↓
Step 4 · (c) Largest axial load
110 + 39.4
Pmax ≈ 149 kips at the top of the sand
↓
Step 5 · (c) Steel stress
149 / 16.05
f ≈ 9.3 ksi = 0.21 fy
Spot check: Below 0.5fy = 22.5 ksi, a common working-stress limit for unfilled steel pipe; confirm with the owner railroad’s structural criteria.
↓
Solution
Qn ≈ 39 kips for the end-bearing pile; neutral plane at about 25 ft and Qn ≈ 20 kips if floating; Pmax ≈ 149 kips, f ≈ 9.3 ksi.

Solution

(a) Qn ≈ 39 kips. (b) L1 ≈ 25 ft below the top of the clay; Qn ≈ 20 kips. (c) About 149 kips at the top of the sand; steel stress about 9.3 ksi.

The dragload is a third of the dead load, so it must be in the structural check and the drivability study (the pile has to be driven to a capacity that covers the dead load plus the dragload, because the clay contributes nothing). It does not add to the settlement of an end-bearing pile, but the fill settles while the abutment does not: the approach slab or the track at the back wall will drop. Options: build the fill and wait (or surcharge and wick-drain it) before driving piles, use lightweight fill, coat the piles in the clay zone with bitumen, or sleeve them. No credit should be taken for shaft resistance in the clay or the fill.

6.1.22.5 Sources

  1. Bowles, J. E. (1996). Foundation Analysis and Design, 5th ed. New York: McGraw-Hill.
  2. Das, B. M. and Sivakugan, N. (2019). Principles of Foundation Engineering, 9th ed., SI edition. Boston: Cengage Learning.
6.1.23 Footings at the Top of or on a Slope

Railroad foundations are often close to a slope: signal and communication bungalows, catenary and signal mast footings, retaining wall and wingwall footings, and culvert headwalls on embankment shoulders or at the tops of cuts. The slope removes part of the passive wedge on one side, so the bearing capacity drops as the footing gets closer to the crest and as the slope gets steeper. Two cases are treated separately (Das and Sivakugan 2019, Sections 7.8 and 7.9; Bowles 1996, Section 4.9).

6.1.23.1 Footing on top of a slope (setback b from the crest)

Equation 6.1-34. Meyerhof (1957) bearing capacity of a strip footing on top of a slope

qu = c′Ncq + ½γBNγq;   granular soil: qu = ½γBNγq;   clay (φ = 0): qu = cuNcq

Ncq and Nγq are read from Meyerhof’s charts as functions of β, b/B (or b/H), Df/B and φ′ or Ns (Das and Sivakugan 2019, Figs. 7.20 and 7.21). The factors rise with setback and reach the level-ground values at a setback of a few footing widths; read that limit from the chart for the case at hand.

Equation 6.1-35. Stability number for clay slopes

Ns = γH / cu

If B < H use the Ns = 0 curves with b/B; if B ≥ H use the curves for the calculated Ns with b/H.

6.1.23.2 Footing on the slope face

Where the footing is on the face of the slope with a level base, the general bearing capacity equation (Section 6.1.2.6) is multiplied by ground inclination factors. Vesić’s factors are gq = gγ = (1 − tanβ)² and, for φ = 0, gc = 1 − 2β/(π + 2) with β in radians; Hansen’s, given by Bowles, are similar. For β = 30°, gq = gγ = 0.18 and gc = 0.80, so in sand the slope removes over 80% of the γ and q terms. The equations do not apply if β exceeds φ′, and the overall slope stability usually governs before bearing does.

6.1.23.3 Lateral loads on poles and piles in slopes

Catenary poles, signal masts and transmission structures on embankment side slopes resist overturning by passive pressure on the downhill side, which is reduced by the slope. Bowles suggests reducing the face (bearing) part of the lateral subgrade modulus ks by the ratio RF of the passive force for the actual ground slope to that for level ground, while leaving the side-shear part unchanged. For example, with ks = 2,000 split equally between face and sides and RF = 0.6, the revised ks = 1,000 + 0.6 × 1,000 = 1,600. The same idea applies to Broms’ method (Section 6.1.19): use a reduced passive coefficient on the downhill side, or ignore the soil above a line drawn from the toe of the embedment out to the slope face.

For railroad work: Treat any foundation within about two footing widths of a crest, or on a slope face, as a slope problem first and a bearing problem second. Include the train surcharge in the global check, keep the foundation out of the zone that a future ditch cleaning or slope flattening will remove, and protect the crest from runoff. For mast and pole foundations on fill slopes, embed below the loose shoulder material (often 2 to 3 ft of ballast and side-cast spoil) and neglect it in the lateral analysis.

6.1.23.4 Worked example

Example 6.1-8: Signal Bungalow Footing at the Crest of a Clay Cut

Problem Statement

A continuous footing for a signal bungalow and cable trough on a Class I railroad located in Missouri has to sit at the top of a 20-ft-high cut slope in clay, set back only 2 ft 8 in. from the crest because of the track centers. Check the allowable bearing pressure using Meyerhof’s factors for a foundation on top of a slope (Section 6.1.23). This is Das and Sivakugan’s Example 7.8 restated in English units.

footing B = 4 ft Df = 4 ft b = 2.67 ft H = 20 ft β = 30° Clay: cu = 1,050 psf, φ = 0, γ = 111 pcf Required:stability number Ns qu and qall (FS = 4) overall slope check Black = given; red = required
Figure 6.1-18. Given and required for Example 6.1-8: strip footing near the crest of a clay slope.

Given

VariableValueDescription
B, Df4 ft, 4 ftFooting width and depth
b2.67 ftDistance from the footing edge to the crest
H, β20 ft, 30°Slope height and angle
cu, γ1,050 psf, 111 pcfUndrained shear strength (φ = 0) and unit weight
FS4Factor of safety on the slope-reduced capacity, as in Das’s example

Required

  • (a) Stability number Ns and which Ncq curve to use
  • (b) Ultimate and allowable bearing pressure
  • (c) What else must be checked

Equations

  1. Eq. 6.1-34: qu = cu Ncq (φ = 0)
  2. Eq. 6.1-35: Ns = γH / cu; use the Ns = 0 curves when B < H
  3. Eq. 3: qall = qu / FS

Steps

Step 1 · (a) Stability number
111 × 20 / 1,050
Ns = 2.1; but B = 4 ft < H = 20 ft, so use the Ns = 0 curves
↓
Step 2 · (a) Chart inputs
Df/B = 4/4 = 1; b/B = 2.67/4 = 0.67; β = 30°
Ncq = 6.3 (Das and Sivakugan 2019, Fig. 7.21)
Spot check: Same ratios as Das’s SI example (B = 1.2 m, b = 0.8 m), so the chart reading carries over.
↓
Step 3 · (b) Ultimate
1,050 × 6.3
qu = 6,615 psf
Spot check: Das’s SI answer 315 kN/m² = 6,580 psf; the difference is rounding of cu.
↓
Step 4 · (b) Allowable
6,615 / 4
qall ≈ 1,650 psf
↓
Step 5 · (c) Other checks
Overall stability of the slope with the footing load and train surcharge (Chapter 6.3); settlement; frost depth; erosion of the crest
Bearing alone does not clear the site
↓
Solution
Ns = 2.1 but B < H, so Ncq = 6.3 from the Ns = 0 curves; qu ≈ 6,600 psf; qall ≈ 1,650 psf.

Solution

(a) Ns = 2.1, but B < H so the Ns = 0 curve applies. (b) qu ≈ 6,600 psf, qall ≈ 1,650 psf. (c) Global stability with the train surcharge, settlement and crest erosion.

A bungalow footing usually bears well under 1,650 psf, so bearing is not the issue; the slope is. Run the global stability analysis with the footing load and the Cooper E-80 surcharge on the nearby track (Section 6.1.4 and Chapter 6.3), and keep surface water from the bungalow roof and cable trough away from the crest. If the setback cannot be increased, a short drilled shaft or helical piles that carry the load below the potential slip surface are often cheaper than a wider footing.

6.1.23.5 Sources

  1. Bowles, J. E. (1996). Foundation Analysis and Design, 5th ed. New York: McGraw-Hill.
  2. Das, B. M. and Sivakugan, N. (2019). Principles of Foundation Engineering, 9th ed., SI edition. Boston: Cengage Learning.
Author and Sources

Authors: Daniel P. Colwell and Mario Ruel. This chapter was written and compiled by Daniel P. Colwell and Mario Ruel for Railway Ground Hazard Risk Management.

Technical content is drawn from the published sources below, and credit for that material belongs to their authors and publishers. Tables, equations and figures taken from a specific source are also cited where they appear.

Primary sources

Supplemental references

File locations for these documents are listed under Supplemental References.

Project management sources

  • Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & SohnFind source ↗
Supplemental References

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After Selig & Waters (1994)” summarize item S7 for railroad clients; tables are condensed from the book and its figures are not reproduced. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. Naval Facilities Engineering Command (1986). Foundations and Earth Structures, Design Manual 7.02 (NAVFAC DM-7.02)Find source ↗
  2. U.S. Army Corps of Engineers (1994). Rock Foundations. EM 1110-1-2908Find source ↗Library entry
  3. Hannigan, P. J., Goble, G. G., Likins, G. E. and Rausche, F. (2006). Design and Construction of Driven Pile Foundations, Vol. I. FHWA NHI-05-042 (superseded by GEC 12, FHWA-NHI-16-009 (2016))Find source ↗
  4. Das, B. M. Principles of Foundation Engineering. Cengage LearningFind source ↗
  5. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)Find source ↗Library entry
  6. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. ColwellFind source ↗
  7. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: ch. 10Find source ↗Library entry
  8. Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn. Used on this page for project-management materialFind source ↗
  9. Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education. Used on this page: Section 6.1.5 (batter piles and underpinning)Find source ↗
  10. Das, B. M. and Sivakugan, N. (2019). Principles of Foundation Engineering, 9th ed., SI edition. Boston: Cengage Learning. Used on this page: Sections 6.1.22 and 6.1.23
  11. Bowles, J. E. (1996). Foundation Analysis and Design, 5th ed. New York: McGraw-Hill. Used on this page: Sections 6.1.22 and 6.1.23

Photograph credits

The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.

  1. Photo 6.1.5-1 — CFA pile rig From Brown et al. (2007) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  2. Photo 6.1.5-2 — Low headroom CFA pile application From Brown et al. (2007) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  3. Photo 6.1.5-3 — Installation of CFA pile reinforcement From Brown et al. (2007) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  4. Photo 6.1.5-4 — Group of CFA piles with form for pile cap From Brown et al. (2007) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  5. Photo 6.1.5-5 — Pilecaps on CFA piles for column-supported embankment From Brown et al. (2007) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  6. Photo 6.1.5-6 — CFA piles used for secant pile wall From Brown et al. (2007) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  7. Photo 6.1.5-7 — Micropile applications — foundation support, seismic retrofit, slope stabilization & earth retention From FHWA NHI-05-039 Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  8. Photo 6.1.5-8 — Micropile installation on a slope Courtesy of a specialty contractor, via FHWA / SHRP2 R02 Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  9. Photo 6.1.5-9 — Micropile installation with limited headroom Courtesy of a specialty contractor, via FHWA / SHRP2 R02 Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗