5.1.14 Practice Questions

In situ testing provides continuous or near-continuous soil and rock characterization without the inherent sample disturbance associated with laboratory testing.
Authors: Daniel P. Colwell and Mario Ruel
5.1.14 Practice Questions
Each question is worked in the same five parts as the examples.
Question 5.1-1: Corrected Tip Resistance and su

Problem Statement

A bridge approach fill on a Class I railroad has been settling, and the abutment is to be checked for bearing on the clay beneath it. A piezocone sounding through the fill reached the clay, and at 30 ft it recorded the tip resistance and pore pressure shown. The engineer must correct the tip resistance and estimate the undrained strength of the clay for the abutment bearing check.

Approach fillClay0510152025303540Depth (ft)qc = 6.80 tsf, u2 = 0.95 tsfqt, su = ?Piezocone below the approach fillGivenqc = 6.80 tsf; u2 = 0.95 tsfa = 0.82σv = 1.95 tsfNkt = 13Required(a) qt (b) su Black = given; red = required
Given and required for Question 5.1-1.

Given

VariableValueDescription
qc, u26.80 tsf; 0.95 tsf
a0.82
σv1.95 tsf
Nkt13

Required

  • (a) qt
  • (b) su

Equations

  1. Eq. 5.1-1: qt = qc + u2(1 − a) — corrected tip resistance
  2. Eq. 5.1-3: su = (qt − σv) / Nkt — undrained strength

Steps

Step 1 · (a) qt
6.80 + 0.95 × 0.18 = 6.80 + 0.171
6.971 tsf
↓
Step 2 · (b) su
(6.971 − 1.95) / 13 = 5.021 / 13
0.386 tsf = 772 psf
↓
Solution
qt = 6.97 tsf; su = 772 psf.

Solution

(a) qt = 6.97 tsf. (b) su = 0.386 tsf (772 psf), a medium clay.

The value is suitable input for abutment bearing capacity (Chapter 6.1) once Nkt is confirmed for this clay.

Question 5.1-2: Vane Strength, Sensitivity and Design Strength

Problem Statement

A Class I railroad embankment along a lakeshore is to be widened for a passing track, over a highly plastic lacustrine clay. Field vane tests at 12 ft gave the peak and remolded torques shown. The engineer must convert the readings to strength, find the sensitivity, and give the design strength for the widening, noting whether the clay triggers an enhanced seismic review.

CrustLacustrine clay, PI 70%05101520Depth (ft)Tpeak / Trem = 8.6 / 1.4 lb·ftsu, St, design su = ?Field vane, D = 2.24 in., H/D = 2GivenTpeak = 8.6; Trem = 1.4 lb·ftD = 0.187 ftPI = 70%Required(a) Peak su (b) Sensitivity(c) Design su (d) Enhanced seismic review?Black = given; red = required
Given and required for Question 5.1-2.

Given

VariableValueDescription
Tpeak, Trem8.6 and 1.4 lb·ftAt 12 ft
D0.187 ft
PI70%

Required

  • (a) Peak su
  • (b) Sensitivity
  • (c) Design su
  • (d) Whether enhanced seismic review is triggered

Equations

  1. Eq. 5.1-6: su = 6T / (7πD³) — vane strength, H/D = 2
  2. Eq. 5.1-8: St = su,peak / su,remolded — sensitivity
  3. Eq. 5.1-7: su,design = μ su,peak — Bjerrum; μ = 0.85 at PI 40, 0.75 at PI 60, 0.65 at PI 80

Steps

Step 1 · (a) Peak
6 × 8.6 / 0.1438
359 psf
↓
Step 2 · (b) St
Remolded 6 × 1.4 / 0.1438 = 58 psf; 359 / 58
St = 6.1
↓
Step 3 · (c) Design
μ at PI 70% = 0.70; 0.70 × 359
251 psf
↓
Step 4 · (d) Trigger
6.1 < 8
Not triggered
↓
Solution
Design su ≈ 250 psf; St = 6.1.

Solution

(a) 359 psf. (b) St = 6.1. (c) 250 psf. (d) Not triggered.

The clay is sensitive: it will lose most of its strength if disturbed. Load it in stages with piezometer control rather than relying on the design value at one placement.

Question 5.1-3: Site Class and Gmax of a Soft Site

Problem Statement

A new intermodal ramp track is planned on soft ground beside a river. An MASW survey gave the average shear wave velocity of the upper 100 ft and the velocity and unit weight of the upper layer shown. The engineer must assign the seismic site class, find the small-strain modulus of the upper layer, and explain what the results mean for the track and structures.

Vs = 410 ft/s, γ = 110 pcfAverage to 100 ft: Vs,30 = 580 ft/s0102030405060708090100Depth (ft)Site class = ? Significance?MASW at intermodal ramp, beside riverGmax = ?GivenVs,30 = 580 ft/sUpper layer: γ = 110 pcf, Vs = 410 ft/sRequired(a) Site class(b) Gmax of the upper layer(c) SignificanceBlack = given; red = required
Given and required for Question 5.1-3.

Given

VariableValueDescription
Vs,30580 ft/s
γ, Vs110 pcf; 410 ft/sUpper layer

Required

  • (a) Site class
  • (b) Gmax of the upper layer
  • (c) Significance

Equations

  1. Eq. 1: Gmax = (γ/g) Vs²

Steps

Step 1 · (a) Class
580 < 600 ft/s
Site Class E
↓
Step 2 · (b) Gmax
(110/32.2) × 410² = 3.416 × 168,100
574,000 psf = 287 tsf
↓
Solution
Class E; Gmax = 287 tsf.

Solution

(a) Site Class E. (b) Gmax ≈ 287 tsf. (c) Large amplification and a soft subgrade.

Class E carries the largest code amplification factors at low to moderate shaking, and a site-specific response analysis is advisable. The low stiffness also suggests the subgrade may need improvement (Chapter 7.2) to meet track modulus requirements.

Question 5.1-4: Depth to Rock From Seismic Refraction

Problem Statement

A Class I railroad plans to widen a rock cut to add a second track. A two-layer seismic refraction line along the cut gave the overburden and rock velocities and the crossover distance shown. The engineer must estimate the depth to rock and say whether the rock can be ripped or will need blasting next to the operating track.

Overburden V1 = 3,800 ft/sRock V2 = 9,200 ft/sSourcexc = 48 ft (crossover)h = ?Rip or blast?GivenV1 = 3,800 ft/s; V2 = 9,200 ft/sxc = 48 ftRippability difficult: 8,000–12,000 ft/sRequired(a) Depth to rock(b) Is blasting likely?Black = given; red = required
Given and required for Question 5.1-4.

Given

VariableValueDescription
V1, V23,800 and 9,200 ft/sOverburden and rock
xc48 ftCrossover distance
RippabilityDifficult: 8,000 to 12,000 ft/sTable in Section 5.1

Required

  • (a) Depth to rock
  • (b) Whether blasting is likely

Equations

  1. Eq. 5.1-18: h = (xc/2) √[(V2 − V1)/(V2 + V1)]

Steps

Step 1 · (a) h
24 × √(5,400/13,000) = 24 × 0.6445
h = 15.5 ft
↓
Step 2 · (b) Rippability
9,200 ft/s
Difficult: blasting likely
↓
Solution
About 15.5 ft to rock; blasting likely.

Solution

(a) About 15.5 ft. (b) Blasting is likely.

Blasting near active track needs advance notice to the railroad, state explosive permits and a vibration limit agreed with the railroad. Confirm the rock depth with a boring before the excavation is priced.

Question 5.1-5: Dilatometer Parameters and Constrained Modulus

Problem Statement

A dilatometer sounding was made through the foundation of a railroad embankment that is to be raised 4 ft. At 14 ft, above the water table, the corrected pressures and effective stress are as shown. The engineer must compute the dilatometer indices, identify the soil type and find the constrained modulus to be used in the settlement estimate for the raise.

EmbankmentFoundation soil051015202530Depth (ft)p0 = 1,240; p1 = 3,860 psfID, KD, ED, M = ?Flat dilatometer soundingGivenp0 = 1,240 psf; p1 = 3,860 psfσ′v = 780 psfu0 = 0 (above GWT)Embankment raise of 4 ftRequired(a) ID (b) KD (c) ED (d) MDMT and soil typeBlack = given; red = required
Given and required for Question 5.1-5.

Given

VariableValueDescription
p0, p11,240 and 3,860 psfCorrected pressures at 14 ft
σ′v780 psf
u00Above the water table

Required

  • (a) ID
  • (b) KD
  • (c) ED
  • (d) MDMT, and soil type

Equations

  1. Eq. 1: ID = (p1 − p0)/(p0 − u0); KD = (p0 − u0)/σ′v; ED = 34.7(p1 − p0) — Marchetti
  2. Eq. 2: RM0 = 0.14 + 0.15(ID − 0.6); RM = RM0 + (2.5 − RM0) log KD ≥ 0.85; M = RM ED — for 0.6 < ID < 3

Steps

Step 1 · (a) ID
2,620 / 1,240
2.11: sand (> 1.8)
↓
Step 2 · (b) KD
1,240 / 780
1.59
↓
Step 3 · (c) ED
34.7 × 2,620
90,900 psf
↓
Step 4 · (d) RM and M
RM0 = 0.37; RM = 0.37 + 2.13 × 0.201 = 0.80, raised to 0.85; 0.85 × 90,900
MDMT ≈ 77,300 psf (38.6 tsf)
↓
Solution
Sand; ID 2.11, KD 1.59, ED 90,900 psf, M 77,300 psf.

Solution

(a) ID = 2.11, sand. (b) KD = 1.59. (c) ED ≈ 90,900 psf. (d) MDMT ≈ 77,300 psf (38.6 tsf).

A KD this low is typical of loose, normally consolidated sand. ED is not a design modulus; MDMT is, and it feeds the immediate settlement estimate for the widening (Chapter 6.2). The OCR correlation is for clays (ID < 1.2) and is not used here.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-12 Corrected cone resistance qₜUse: All piezocone (CPTu) soundings; essential in soft clays and silts. Limits: Correction negligible in clean sands; critical in soft fine-grained soils. Requires u2 filter position.
  • IS-14 Undrained shear strength from CPT SᵤUse: Fine-grained soils penetrated undrained (Ic > ~2.6). Limits: Nkt depends on reference test (vane, CIUC, DSS) and plasticity; calibrate locally. Use Nkt toward upper end for conservative Su.
  • IS-23 Flat dilatometer (DMT) intermediate parameters I_D, K_D, E_DUse: All soils penetrable by the blade; ID < 0.6 clay, 0.6–1.8 silt, >1.8 sand. Limits: ED is not a design modulus; convert with MDMT = RM · ED (Marchetti 1980).
  • IS-25 Field vane strength correction Sᵤ (field)Use: Soft clays, embankment stability on soft ground; based on back-analyzed failures. Typical PI 5–100%. Limits: Not applicable to fissured, varved, or organic clays without local calibration. Scatter about ±25%.
  • IX-09 At-rest earth pressure coefficient K₀Use: Uncemented soils on primary unloading. Limits: Not valid on reloading or for compacted fills, where K0 is governed by compaction stresses. Cap at passive limit.
  • IX-13 Small-strain shear modulus (Hardin) G_maxUse: Uncemented clays and sands; lab resonant-column basis. Limits: Underestimates aged/cemented soils; field Vs (Gmax = ρVs2) is preferred.
Question 5.1-6: Time-Zero Drift in a Hi-Rail GPR Ballast Survey

Problem Statement

A Class I railroad located in Kansas ran a hi-rail GPR survey to map ballast thickness over a mile of track with recurring surface defects. The contractor’s section shows the ballast–subballast interface getting deeper toward the end of the line. Reviewing the raw data, the engineer finds that the air-wave first break (time zero) also arrives later toward the end of the line, as it does when the electronics warm up. A test pit at the start of the line found the interface 22 in. below the top of tie. The engineer must calibrate the velocity and decide whether the ballast really thickens (Section 5.1.15.4).

051015 Two-way time (ns) Distance along track Start (test pit)End of line Air wave (time zero) Ballast–subballast interface 1.8 ns2.6 ns 9.4 ns10.2 ns Pit: interface at 22 in. GivenAir-wave time zero driftsfrom 1.8 to 2.6 nsInterface: 9.4 ns (start),10.2 ns (end)Test pit at start: 22 in.c = 11.8 in./ns Requiredv, εᵣ, depth at end withand without time-zero correction
Figure 5.1-17. Question 5.1-6: schematic radargram with time-zero drift.

Given

VariableValueDescription
t01.8 ns at start; 2.6 ns at endAir-wave first break (time zero)
tr9.4 ns at start; 10.2 ns at endInterface reflection, raw two-way time
dpit22 in.Interface depth at the test pit (start of line)
c11.8 in./nsSpeed of light in air

Required

  • (a) Wave velocity v in the ballast from the test pit
  • (b) Relative dielectric constant εr
  • (c) Interface depth at the end of the line with time-zero correction
  • (d) Apparent depth at the end if the drift is ignored, and the error

Equations

  1. Eq. 1: d = v (tr − t0) / 2
  2. Eq. 2: εr = (c / v)² (Section 5.1.15)

Steps

Step 1 · (a) Velocity
t = 9.4 − 1.8 = 7.6 ns; v = 2 × 22 / 7.6
v = 5.79 in./ns
↓
Step 2 · (b) Dielectric constant
(11.8 / 5.79)² = 2.04²
εr = 4.2
Spot check: A value of about 4 is typical of clean, fairly dry ballast; fouled or wet ballast reads higher.
↓
Step 3 · (c) Corrected depth at end
t = 10.2 − 2.6 = 7.6 ns; d = 5.79 × 7.6 / 2
d = 22.0 in.: no change in thickness
↓
Step 4 · (d) Uncorrected depth at end
Using the start time zero: t = 10.2 − 1.8 = 8.4 ns; d = 5.79 × 8.4 / 2
d = 24.3 in.: an apparent 2.3 in. of thickening
Spot check: The 0.8 ns drift times v/2 = 0.8 × 2.9 = 2.3 in., the same error.
↓
Solution
v = 5.79 in./ns; εr ≈ 4.2; corrected depth 22 in. at both ends; the apparent thickening is a 2.3-in. artifact of time-zero drift.

Solution

(a) v ≈ 5.8 in./ns. (b) εr ≈ 4.2. (c) 22 in., the same as at the test pit. (d) 24.3 in. if the drift is ignored: a false 2.3 in. of thickening.

The ballast does not thicken; the trend in the contractor’s section is a processing error. Ask for the data to be reprocessed with time zero picked trace by trace (or at least per file), and for a second test pit or core toward the end of the line to confirm the velocity, because a change in fouling or moisture also changes εr and the depth. Look for the cause of the surface defects elsewhere, for example in the subballast or subgrade (Chapter 2.3).