5.2.3 Test Methods — ASTM Standards and English Unit Outputs

Laboratory testing is the scientific foundation of every geotechnical design.
Authors: Daniel P. Colwell and Mario Ruel
5.2.3 Test Methods — ASTM Standards and English Unit Outputs
5.2.3.1 Water Content (ASTM D2216)

Method: Oven-dry at 230 ± 9°F for minimum 16 hours (peat and organic soils: 140°F).

Equation:

w = (M_water / M_dry) × 100%

where M_water = mass of water (mass_wet − mass_dry); M_dry = mass of dry soil.

Soil Index Properties
Soil Index Properties

Output: Water content w (%), dimensionless.

Minimum frequency: Every disturbed and undisturbed sample. Water content is the most fundamental test in the program — never omit it.

Water Content Test
Water Content Test
Inputs for the equations in this section (2)
SymbolWhat it isComes fromHow to get itTypical range
wwater content = ( M_water / M_dry ) × 100%Lab testOven-dry water content of samples (ASTM D2216); field check by microwave (D4643) or nuclear gauge (D6938).gravels/sands 3–25%, clays 15–70% · by USCS group
Mdrymass of dry soil.Field or lab measurementRecorded during the test or monitoring (readings, times, dimensions of the test setup).project-specific
5.2.3.2 Atterberg Limits (ASTM D4318)

Liquid Limit (LL): Casagrande cup method; flow curve plotted; LL at N = 25 blows.

Plastic Limit (PL): ⅛-in. thread rolling on glass plate.

Plasticity Index: PI = LL − PL

Liquidity Index: LI = (w − PL) / PI

Activity: A = PI / (% < 0.002 mm)

Output: LL, PL, PI (all %); LI and A dimensionless.

Minimum frequency: 1 per fine-grained stratum per boring; 1 per 5 ft depth in highly variable fine-grained profiles.

5.2.3.3 Grain Size Analysis

Sieve analysis (ASTM D6913): Applicable for material with particles retained on the No. 200 sieve. Sieves: 3 in., 2 in., 1½ in., 1 in., ¾ in., ½ in., No. 4, No. 10, No. 20, No. 40, No. 60, No. 100, No. 200.

Sieve Analysis Test
Sieve Analysis Test

Hydrometer analysis (ASTM D7928): For material passing No. 200 (clay and silt sizes). Combined with sieve for full gradation curve (ASTM D6913 + D7928).

Hydrometer Analysis
Hydrometer Analysis

Key outputs:

  • D₁₀, D₃₀, D₆₀ (in., or mm for reference): particle diameters at 10%, 30%, 60% passing
  • C_u = D₆₀ / D₁₀ (uniformity coefficient, dimensionless)
  • C_c = D₃₀² / (D₆₀ × D₁₀) (coefficient of curvature, dimensionless)
  • Fines content: % passing No. 200 sieve

Minimum frequency: 1 per stratum per boring for classification; additional tests for filter design and liquefaction susceptibility assessment.

Inputs for the equations in this section (2)
SymbolWhat it isComes fromHow to get itTypical range
CuD₆₀ / D₁₀ (uniformity coefficient, dimensionless)Lab testGrain-size curve: sieve (ASTM D6913) plus hydrometer for fines (ASTM D7928). Read D10, D30, D50, D60, D85 from the curve.by USCS group
CcD₃₀² / (D₆₀ × D₁₀) (coefficient of curvature, dimensionless)Lab testGrain-size curve: sieve (ASTM D6913) plus hydrometer for fines (ASTM D7928). Read D10, D30, D50, D60, D85 from the curve.by USCS group
5.2.3.4 Specific Gravity (ASTM D854)

Method: Pycnometer (volumetric flask) method; soil displaced volume in de-aired water.

Equation:

G_s = M_sd / (M_sd + M_pw − M_spw) (dimensionless)

where M_sd = mass of dry soil; M_pw = mass of pycnometer + water; M_spw = mass of pycnometer + soil + water.

Typical values: G_s = 2.60–2.75 (mineral soils); 2.60–2.65 (clean quartz sand); 2.70–2.80 (iron-rich soils).

Minimum frequency: 1 per soil type in each project; required for void ratio and consolidation calculations.

Why Soil Consolidation Happens
Why Soil Consolidation Happens
Soil Consolidation Testing
Soil Consolidation Testing
Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
Gsspecific gravity of solids = M_sd / ( M_sd + M_pw − M_spw ) (dimensionless)Lab testSpecific gravity of solids (ASTM D854). 2.65–2.70 is usually adequate for mineral soils when untested.2.64–2.80 mineral; lower if organic · by USCS group
Mpwmass of pycnometer + waterField or lab measurementRecorded during the test or monitoring (readings, times, dimensions of the test setup).project-specific
Mspwmass of pycnometer + soil + water.Field or lab measurementRecorded during the test or monitoring (readings, times, dimensions of the test setup).project-specific
5.2.3.5 Compaction Tests

Standard Proctor (ASTM D698):

  • Method A: material passing No. 4 sieve; 3 layers; 25 blows per layer; 5.5-lb hammer; 12-in. drop
  • Energy: 12,375 ft·lb/ft³

Modified Proctor (ASTM D1557):

  • Method A or C: 5 layers; 25 blows per layer; 10-lb hammer; 18-in. drop
  • Energy: 56,250 ft·lb/ft³

Output: Compaction curve (γ_d pcf vs. w %); γ_d,max (pcf); w_opt (%)

Zero-Air-Voids (ZAV) line: γ_d,ZAV = G_s × γ_w / (1 + G_s × w/100) (pcf)

Minimum frequency: 1 Modified Proctor per borrow source or fill material type (not per sample); repeat if source changes during construction.

5.2.3.6 California Bearing Ratio (ASTM D1883)

Method: Laboratory CBR at Modified Proctor density (95% RC minimum). Specimen soaked 96 hours at Standard loading conditions.

Penetration resistance equation:

CBR = (P_sample / P_standard) × 100%

where:

  • P_sample = measured force at 0.1 in. or 0.2 in. penetration (lb)
  • P_standard = standard force at same penetration; 0.1 in.: 3,000 lb; 0.2 in.: 4,500 lb

Use the higher CBR from 0.1 or 0.2 in. penetration (recheck if 0.2 in. governs).

Output: CBR (%); used directly for pavement design (Chapter 7.3, Section 7.3.1).

Minimum frequency: 1 per subgrade soil type per project; 3+ tests for intermodal yard pavement design.

Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
CBRCalifornia Bearing Ratio = ( P_sample / P_standard ) × 100%Lab or field testLab CBR (ASTM D1883, soaked) on compacted samples; field CBR (D4429); or from DCP (ASTM D6951) correlation.CL/CH ≤ 15; sands 10–40; gravels 20–80 · by USCS group
Psamplemeasured force at 0.1 inField or lab measurementRecorded during the test or monitoring (readings, times, dimensions of the test setup).project-specific
Pstandardstandard force at same penetrationConstantPhysical constant or standard value.project-specific
California Bearing Ratio (CBR) Test
California Bearing Ratio (CBR) Test
5.2.3.7 Resilient Modulus (AASHTO T307)

Method: Cyclic triaxial test with conditioning sequence (500 cycles at 4 psi deviator) followed by 15 stress states per AASHTO T 307 protocol.

M_r from regression (NCHRP 1-28A model):

M_r = k₁ × P_a × (θ/P_a)^k₂ × (τ_oct/P_a + 1)^k₃ (psi)

where:

  • P_a = atmospheric pressure = 2,117 psf = 14.7 psi
  • θ = bulk stress = σ₁ + σ₂ + σ₃ (psi)
  • τ_oct = octahedral shear stress (psi)
  • k₁, k₂, k₃ = regression constants from test

Minimum frequency: 1 test per subgrade soil type where the pavement or subgrade design uses M_r; confirm whether the owner requires it.

Repeated-load testing for track subgrade

Repeated-load triaxial (or simple shear) tests give two results that matter for track:

  • The resilient modulus, Er = cyclic deviator stress ÷ recoverable axial strain.
  • The rate at which plastic strain accumulates.

Tiny plastic strains per cycle add up to large settlement over millions of cycles, so report both.

What to look for.

  • In drained or unsaturated tests, the plastic increment shrinks with each cycle.
  • In saturated specimens, or at stresses near failure, the increment can grow. That is the runaway case.
  • Running a series of stress levels identifies the threshold stress used in Chapter 2.3, Section 2.3.4.2.
  • Er typically rises over the first cycles. Granular materials need several thousand cycles to stabilize, and their modulus is strongly dependent on confining pressure (Er = K1 θK2, where θ is bulk stress).

Test conditions. Test at the field moisture and density, including a wet-of-optimum case (Chapter 7.3). Fine-grained modulus falls steeply on the wet side.

After Selig & Waters (1994), chs. 3, 7 and 10. Full reference under Supplemental References.

Inputs for the equations in this section (4)
SymbolWhat it isComes fromHow to get itTypical range
Mrresilient modulus = k₁ × P_a × (θ/ P_a )^k₂ × ( τ_oct / P_a + 1)^k₃ (psi)Lab test (or correlation)Repeated-load triaxial (AASHTO T 307), or Mr ≈ 2,555·CBR0.64 (MEPDG).fine-grained 3,000–14,000 psi · by USCS group
Paatmospheric pressure = 2,117 psf = 14.7 psiConstantPhysical constant or standard value.project-specific
θbulk stress = σ₁ + σ₂ + σ₃ (psi)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
τoctoctahedral shear stress (psi)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Triaxial Shear Test
Triaxial Shear Test
Triaxial Shear Test Explained
Triaxial Shear Test Explained
5.2.3.8 One-Dimensional Consolidation (ASTM D2435)

Method A: Incremental load; load doubling each 24-hour interval; loads: 125–250–500–1,000–2,000–4,000–8,000 psf (standard); extend to 16,000 psf for deep or heavily preloaded sites.

Method B: Constant rate of strain (CRS); continuous loading at a controlled strain rate.

Key outputs (English units):

ParameterSymbolUnitsEquation
Compression indexC_cdimensionlessSlope of e-log σ'_v curve (NC range)
Recompression indexC_rdimensionlessSlope of e-log σ'_v curve (OC range); ≈ C_c/5 to C_c/10
Preconsolidation pressureσ'_ptsfCasagrande graphical construction
OCR—dimensionlessσ'_p / σ'_v0
Coefficient of consolidationc_vft²/dayc_v = T_v × H_dr² / t (see Chapter 6.2)
Secondary compression indexC_αdimensionlessΔe / Δ log t (secondary range)

Minimum frequency: 1 per fine-grained stratum per project; minimum 3 tests in any stratum requiring settlement analysis.

5.2.3.9 Unconsolidated-Undrained (UU) Triaxial (ASTM D2850)

Method: Undrained shear test on undisturbed sample; three specimens at different confining pressures (typically 500, 1,000, 2,000 psf); no drainage allowed during shear.

Unconsolidated–Undrained (UU) Triaxial Test
Unconsolidated–Undrained (UU) Triaxial Test

Output: s_u (psf or tsf) from Mohr circle at failure; φ_u ≈ 0° for saturated clay.

Note: For saturated clay, UU test gives s_u directly regardless of confining pressure — the Mohr circle diameter is constant. UU is appropriate for short-term (undrained) stability analysis only.

Minimum frequency: 1 per soft or medium clay stratum per boring at critical cross-sections (slope stability, embankment loading over soft clay).

Strength parameters: match the test to the drainage condition

  • CD tests give c′ ≈ 0 for both loose and dense soils. A small c′ appears only from a curved envelope or heavy overconsolidation. Use effective-stress parameters for drained problems.
  • CU tests. Dense sand develops negative excess pore pressure, so its undrained strength exceeds the drained strength (up to the limit of cavitation). Loose sand develops positive pore pressure, so its undrained strength is lower. φ′ is the same as from CD tests.
  • UU tests give φ = 0 and c = su, which depends only on the initial state. This is the convenient basis for short-term undrained loading.
  • Unconfined compression works only on fine soils that stand unsupported. Disturbance and unloading make it underestimate su.
  • Partially saturated subgrade. Pore pressure is rarely known, so analyze in total stress with both c and φ. Soil at low saturation behaves essentially drained in any test.
Drained vs Undrained Analysis
Drained vs Undrained Analysis
Triaxial Compression Test of Soil
Triaxial Compression Test of Soil
Unconfined Compression Test
Unconfined Compression Test
Figure 5.2-14. Bank, loose and compacted states of soil during earthwork.
Figure 5.2-14. Bank, loose and compacted states of soil during earthwork.

After Selig & Waters (1994), ch. 3. Full reference under Supplemental References.

5.2.3.10 Consolidated-Undrained (CU) Triaxial with Pore Pressure (ASTM D4767)

Method: Specimens consolidated to two or three effective confining pressures (σ'₃); sheared undrained with pore pressure measurement; effective stress Mohr circles give c' and φ'.

Output: c' (psf), φ' (degrees) — effective strength parameters for long-term (drained) analysis.

Minimum frequency: Required for all critical slope stability analyses (Class I railroad clay shale, Class I railroad clay located in the prairies, Class I railroad sensitive marine clay); 1 set (3 specimens) per stratum per project minimum.

5.2.3.11 Direct Shear (ASTM D3080)

Method: Specimen sheared at constant normal stress; three tests at different normal stresses.

Peak and residual strength:

τ_peak = c' + σ_n × tan φ'_peak (psf)

τ_residual = σ_n × tan φ'_r (psf, c' = 0 for residual)

Output: c' (psf), φ' (degrees), φ'_r (degrees).

Use cases: Residual strength for Class I railroad clay shale and Class I railroad weathered shale slope stability; rock joint shear strength for cut slope design.

Minimum frequency: 1 per stratum requiring residual strength parameters; rock joints: minimum 3 direct shear tests per joint set per project.

Inputs for the equations in this section (2)
SymbolWhat it isComes fromHow to get itTypical range
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
c'effective cohesionLab testEffective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more.0–300 psf · by USCS group
Direct Shear Test
Direct Shear Test
5.2.3.12 Unconfined Compression (ASTM D2166)

Method: Axial loading to failure at unconfined conditions (σ₃ = 0). Quick and inexpensive.

Output: q_u (psf or tsf); s_u = q_u / 2.

Limitation: UU triaxial provides more reliable s_u; unconfined compression can underestimate s_u in fissured or brittle clays. Use for screening; not for final design in critical applications.

Minimum frequency: Appropriate for routine s_u checks on Shelby tube samples; supplement with UU triaxial for design-level analysis.

5.2.3.13 Hydraulic Conductivity (Permeability)

Constant head (ASTM D2434): For coarse-grained soils (k above about 3 ft/day, 10⁻³ cm/s).

k = (Q × L) / (A × h × t) (ft/day)

where Q = flow volume (ft³); L = specimen length (ft); A = cross-sectional area (ft²); h = head differential (ft); t = test duration (day).

Flexible wall permeameter (ASTM D5084): For fine-grained soils (k below about 3 ft/day, 10⁻³ cm/s).

k = (a × L × ln(h₁/h₂)) / (A × t) (ft/day)

where a = standpipe area (ft²); L = specimen length (ft); h₁, h₂ = head at start and end; t = elapsed time (day).

Minimum frequency: 1 per stratum for drainage design; 3 per stratum for seepage analysis through embankments or dams.

Inputs for the equations in this section (5)
SymbolWhat it isComes fromHow to get itTypical range
k(Q × L) / (A × h × t) (ft/day)Field or lab testField: pumping test, slug test (ASTM D4044, withdrawn 2024) or packer test. Lab: constant head (D2434) for sands, flexible-wall (D5084) for clays. Hazen k ≈ C·D102 for clean sands only.clean sand 1–100, clay < 0.001 ft/day · by USCS group
Lspecimen length (ft)Test setupDimension of the test equipment or specimen: from the test standard or the lab/field test record.project-specific
Across-sectional area (ft²)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
hhead differential (ft)Field or lab measurementRecorded during the test or monitoring (readings, times, dimensions of the test setup).project-specific
ttest duration (day).TimeElapsed test time (recorded) or the analysis time chosen for design.project-specific
Constant Head Permeability Test
Constant Head Permeability Test
5.2.3.14 Point Load Index (ASTM D5731)

Method: Rock core or irregular lump loaded to failure between conical platens.

Point load strength index:

I_s = P / D_e² (psi or psf)

where P = failure load (lb); D_e = equivalent core diameter (in.).

Size-corrected index:

I_s(50) = F × I_s where F = (D_e/1.97 in.)^0.45

Estimated UCS of rock:

q_u(rock) ≈ 24 × I_s(50) (psi) [Broch & Franklin 1972; I_s in psi]

Minimum frequency: at least 10 valid tests per rock unit (ASTM D5731, withdrawn 2025); not a substitute for UCS testing for critical rock foundation designs.

Rock Triaxial Testing
Rock Triaxial Testing
Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
IsP / D_e² (psi or psf)Lab testUniaxial compression of rock core (ASTM D7012); point load index (D5731) for screening.shale 1,000–15,000; sandstone 5,000–25,000; granite 15,000–40,000 psi
Deequivalent core diameter (in.).Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Is(50)F × I_s where F = ( D_e /1.97 in.)^0.45Lab testUniaxial compression of rock core (ASTM D7012); point load index (D5731) for screening.shale 1,000–15,000; sandstone 5,000–25,000; granite 15,000–40,000 psi
Supplemental reference

USACE Q / R / S nomenclature and common triaxial errors

USACE manuals (EM 1110-2-1902 slope stability, EM 1110-2-2504 sheet piles, and others cited in this manual) use letter names for the basic triaxial tests: Q = unconsolidated-undrained (UU); R = consolidated-undrained (CU); S = consolidated-drained (CD), which is also the long-term drained case. The Q test applies only to soils that are not free-draining, and R-test specimens should generally be fully saturated before shear. Errors EM 1110-2-1906 lists for R tests: back-pressure increments too large or applied too fast; chamber and back pressure not held precisely (which can overconsolidate the specimen); shearing before consolidation is complete; too fast a strain rate; temperature drift; and water absorbed from the porous inserts after the test, which biases the final water content. For S tests the main errors are strain rate and volume-change measurement. In pervious soils, water redistributes even in a quick Q test, so measure the water content of the middle third separately from the ends.

Details of a typical triaxial compression chamber for 1.4-in.-diameter specimens (EM 1110-2-1906).
Supplemental Figure 10-S2. Details of a typical triaxial compression chamber for 1.4-in.-diameter specimens (EM 1110-2-1906). Source: U.S. Army Corps of Engineers (1970, with changes). Laboratory Soils Testing. EM 1110-2-1906, p. X-4.

Picking t50 and t90 from each load increment

Section 5.2.3.8 gives cv = TvHdr2/t but not how t is found. The two standard curve-fitting methods (Das lab manual) are:

  • Square-root-of-time (Taylor, 1942): plot dial reading against √t, extend the initial straight line, draw a second line from the same origin with abscissas 1.15 times larger, and read t90 where it cuts the curve. Then cv = 0.848 Hdr2/t90.
  • Log-of-time (Casagrande and Fadum, 1940): d100 is the intersection of the primary and secondary straight lines. For d0, pick t1 and t2 = 4t1 in the early curved part and step up by their difference. t50 is at d50 = (d0 + d100)/2. Then cv = 0.197 Hdr2/t50, and Cα comes from the slope after d100.

With double drainage, Hdr is half the average specimen height during the increment. Report which method was used. The two methods commonly give different cv values for the same increment, and the report should say which one the settlement-time analysis in Chapter 6.2 used.

Source: U.S. Army Corps of Engineers (1970, with changes). Laboratory Soils Testing. EM 1110-2-1906 · Das, B. M. (2002). Soil Mechanics Laboratory Manual, 6th ed. Oxford University Press

Schematic of fixed-ring and floating-ring consolidometers (EM 1110-2-1906). Apparatus compression in either type must be calibrated out for stiff soils.
Supplemental Figure 10-S1. Schematic of fixed-ring and floating-ring consolidometers (EM 1110-2-1906). Apparatus compression in either type must be calibrated out for stiff soils. Source: U.S. Army Corps of Engineers (1970, with changes). Laboratory Soils Testing. EM 1110-2-1906, p. VIII-2.
Supplemental reference

Tests for shale and mudstone: preparation effects and slake durability

Railroad cuts in Appalachian and prairie shales (Chapter 6.3) need durability as well as strength data, and Atterberg limits of clay shale depend on how the sample was processed. EM 1110-2-1906 therefore standardizes three preparations: blenderized (the primary reference — dried below 122°F at < 30% RH, soaked at least 48 hr, then blended as a slurry above 300% water content or twice the LL); undried (shaved directly into distilled water); and air-dried (one drying–soaking cycle). The spread among the three indicates the strength of interparticle bonds. Report which method produced the limits used for design.

Atterberg Limits
Atterberg Limits

Slake durability (Franklin and Chandra, 1972; ASTM D4644, withdrawn 2025): oven-dried rock lumps are rotated for 10 minutes in a sieve-mesh drum half immersed in 68°F water. Id is the percentage of the initial dry mass retained. Nagaraj reports reproducibility within 5% at 95% confidence, and the test discriminates well between mudstones that otherwise look alike.

Id (%)0–2525–5050–7575–9090–9595–100
DurabilityVery lowLowMediumHighVery highExtremely high

After Franklin and Chandra (1972). As printed in Nagaraj’s Table 9.7, the 75–90 and 90–95 labels are transposed; the order shown here is the original.

For clay shales, Nagaraj also reproduces the Morgenstern and Eigenbrod (1974) classification, which combines the amount of slaking (by the liquid limit of the slaked material: < 20 very low to > 140 very high) with the rate (change in liquidity index in the first cycle: < 0.75 slow, 0.75–1.25 fast, > 1.25 very fast). Add slake durability to the rock column of Table 5.2-1 for every cut in shale, mudstone or claystone and for any rock proposed as riprap or fill.

Source: U.S. Army Corps of Engineers (1970, with changes). Laboratory Soils Testing. EM 1110-2-1906 · Nagaraj, T. S. (1993). Principles of Testing Soils, Rocks and Concrete. Elsevier (Developments in Geotechnical Engineering)

Physico-Mechanical Properties of Rocks
Physico-Mechanical Properties of Rocks

Ballast and subballast abrasion tests (Deval, Los Angeles, Micro-Deval)

Table 5.2-7. Abrasion tests for railway aggregates as described by Profillidis
TestEquipment and procedureResult
Deval (1896)11-lb sample in cylinders 8 in. dia. × 13 in., inclined 30°; 10,000 revolutions at 2,000 rev/h (about 5 h); dry or wetDeval coefficient from % attrition. Typical minimums: > 12 (limestone), > 14 (hard rock), some railways > 16
Los Angeles (1926)Drum 28 in. dia. × 20 in.; 11-lb sample with 12 steel balls of 15 oz each; 500 revolutions at 30–33 rpm (about 15 min). EN version: 22-lb sample, 1,000 revolutions% passing No. 12 (French) or No. 8 (British) sieve. Many specifications: LA < 25. EN reference test
Micro-Deval1.1 lb of ⅜–½ in. gravel with 11 lb of small steel balls (about ⅜ in.) and 2.6 qt of water in an 8-in. cylinder; 12,000 revolutions at 100 rpm. EN version: 22 lb, 14,000 revolutionsMDE = % finer than No. 12. Used mainly for subballast; subballast MDE < 15–20
Figure 5.2-11. Deval attrition machine. Profillidis Fig. 12.4.
Figure 5.2-11. Deval attrition machine. Profillidis Fig. 12.4.

North American ballast specifications (AREMA Chapter 1) use the ASTM Los Angeles test for large coarse aggregate (ASTM C535). Results from the European methods are not interchangeable with ASTM results without correlation.

Cyclic behavior. Ballast takes a large permanent set on first loading as stones rearrange, then accumulates strain slowly: εN = ε1(1 + c·log N), with c ≈ 0.2 (European ORE and British Rail research) or 0.25–0.40 (American research). On that basis it takes 100,000–300,000 cycles to double the first-cycle plastic strain. Ballast modulus roughly doubles over the first 1,000 cycles and then stays nearly constant; gravel subballast modulus does not change with cycles. Repeated-load triaxial programs should run long enough to get past this initial bedding-in.

Figure 5.2-12. Elastic deformation of ballast vs. number of loading cycles N. Profillidis Fig. 12.3.
Figure 5.2-12. Elastic deformation of ballast vs. number of loading cycles N. Profillidis Fig. 12.3.

After Profillidis (2014), §12.3–12.4, Eq. 12.1, Figs. 12.3–12.4. Full reference under Supplemental References.

Standard index tests for subgrade samples

Table 5.2-8. Standard laboratory battery for subgrade samples (course summary)
TestStandardWhat it gives
Atterberg limitsASTM D4318Liquid limit, plastic limit, plasticity index; classifies fines
Particle-size distributionASTM D6913 (sieve), D7928 (hydrometer)Sieve gradation, % finer than No. 200, hydrometer split of silt and clay
Moisture contentASTM D2216 (oven); D4643 (microwave, for quick checks)Water content by drying
Unconfined compressive strengthASTM D2166Direct strength of cohesive samples
Proctor compactionASTM D698 / D1557Target density and optimum moisture for fill and subgrade
Compressive Strength Test of Cement
Compressive Strength Test of Cement
Core Test Compressive Strength Test
Core Test Compressive Strength Test
Triaxial Compressive Strength test
Triaxial Compressive Strength test
Uniaxial Compressive Strength
Uniaxial Compressive Strength
Liquid Limit and Plastic Limit Tests
Liquid Limit and Plastic Limit Tests
Standard Proctor Test
Standard Proctor Test
Proctor Compaction Test
Proctor Compaction Test
Soil Compaction and Maximum Dry Density
Soil Compaction and Maximum Dry Density
Figure 5.2-13. Proctor compaction device.
Figure 5.2-13. Proctor compaction device.

Compaction can roughly double a soil’s strength. The fines content of granular fill controls its drainage, frost susceptibility and strength after rain, so specify and test fines on ballast and sub-ballast deliveries rather than accepting material that only looks good dry.

After Geotechnology for Railroaders Program, Module 2; §09–10. Full reference under Supplemental References.

Case study: 5.2.16.1 Curing time changes compaction and CBR results (Look 2023), in Section 5.2.16 Case Studies.