5.2.18 Ballast Acceptance Testing to AREMA Limits

Laboratory testing is the scientific foundation of every geotechnical design.
Authors: Daniel P. Colwell and Mario Ruel
5.2.18 Ballast Acceptance Testing to AREMA Limits

Ballast is bought to a specification, and acceptance rests on two sets of laboratory results: the gradation, compared with the recommended band for the specified size number, and the physical tests, compared with limiting values that depend on the rock type. AREMA Chapter 1, Part 2, publishes both tables. The tests screen out rock that breaks down, absorbs water, carries clay or fines into the track, or packs poorly. Conference papers in the library show how petrography and field imaging extend these tests where a quarry's rock is marginal.

5.2.18.1 Limits

Table 5.2-10. Recommended ballast gradations (AREMA Table 1-2-2), percent passing
Size No.3 in.2 1/221 1/213/41/23/8No. 4No. 8
2410090–10025–600–100–5
2510080–10060–8550–7025–505–200–100–3
310095–10035–700–150–5
4A10090–10060–9010–350–100–3
410090–10020–550–150–5
510090–10040–7515–350–150–5
5710095–10025–600–100–5

Nos. 24, 25, 3, 4A and 4 are main line ballast; Nos. 5 and 57 are yard ballast.

Table 5.2-11. Limiting test values (AREMA Table 1-2-1)
Property (ASTM)Granite, traprockQuartziteLimestoneDolomitic limestone
Passing No. 200, max (C 117)1.0%1.0%1.0%1.0%
Bulk specific gravity, min (C 127)2.602.602.602.65
Absorption, max (C 127)1.0%1.0%2.0%2.0%
Clay lumps and friable particles, max (C 142)0.5%0.5%0.5%0.5%
LA abrasion, max (C 535 or C 131)35%30%30%30%
Sodium sulfate soundness, 5 cycles, max (C 88)5.0%5.0%5.0%5.0%
Flat or elongated, max (D 4791 Method A)5.0%5.0%5.0%5.0%

Use ASTM C535 for gradations with particles retained on the 1 in. sieve and C 131 for gradations passing 1 in. For concrete tie track AREMA excludes carbonate rock and gradation No. 57.

5.2.18.2 Worked example: two shipments of No. 4A

Table 5.2-12. Calculator results
SampleGradationTestsResult
Granite: 96% passing 2 in., 72% at 1 1/2, 22% at 1, 6% at 3/4, 2% at 3/8; LA 24%conformsall within limitsacceptable
Limestone, finer: 40% passing 1 in., 12% at 3/4, 3% at 3/8; LA 32%does not conform (1 in. and 3/4 in. sieves high)LA abrasion over 30%not acceptable

The second shipment fails on both counts: it is too fine for No. 4A and the limestone is softer than the 30% LA limit allows. Fine, soft ballast breaks down faster and fouls sooner (Chapter 6.4), so rejection at the quarry costs far less than early undercutting.

Open the ballast acceptance calculator →
Sieve analysis against the AREMA band for the size number, plus the limiting test values for the rock type and the concrete-tie exclusions.

5.2.18.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • AREMA Manual for Railway Engineering, Chapter 1 (2019 edition), Part 2 Ballast: Tables 1-2-1 and 1-2-2, concrete tie restrictions.Official page ↗
  • AREMA conference paper (2014): petrographic evaluation of ballast suitability, a case study.Find source ↗
  • AREMA conference paper (2021): testing and characterization of dolomite aggregate for ballasted track on a new passenger line.Find source ↗
  • AREMA conference papers (2015, 2018): ballast properties and degradation trends; principles of degraded ballast and track safety.Find source ↗