Each question is worked in the same five parts as the examples. Question 5.2-3 is a reasoning question.
Question 5.2-1: Compression Index, OCR and Which Settlement Equation
Problem Statement
A consolidation test was run on a tube sample from beneath a planned railroad embankment. The test gave the void ratios in the virgin range and the stresses shown. The engineer must compute the compression index and the overconsolidation ratio and decide which settlement equation applies to the embankment load.
Given and required for Question 5.2-1.
Given
Variable
Value
Description
Points
e = 1.42 at 1.0 tsf; e = 1.18 at 4.0 tsf
Virgin range
σ′v0
0.80 tsf
σ′p
1.60 tsf
Casagrande
Required
(a) Cc
(b) OCR
(c) Which Chapter 6.2 equation applies
Equations
Eq. 1: Cc = Δe / Δlog σ′
Eq. 2: OCR = σ′p/σ′v0
Steps
Step 1 · (a) Cc
0.24 / 0.602
0.399
↓
Step 2 · (b) OCR
1.60/0.80
2.0
↓
Step 3 · (c) Equation
Depends on the final stress: recompression only if it stays below 1.60 tsf; recompression plus virgin compression if it exceeds it
↓
Solution
Cc = 0.40; OCR = 2.0; equation depends on the final stress.
Solution
(a) Cc = 0.40. (b) OCR = 2.0. (c) The overconsolidated equations; which one depends on whether the final stress passes 1.60 tsf.
The new load decides the case, so compute σ′vf = σ′v0 + Δσ before choosing.
Question 5.2-2: Field Density Acceptance
Problem Statement
A nuclear gauge test on a lift of fill for a new railroad yard gave the field density and moisture shown. The railroad’s specification requires 95% of Modified Proctor and moisture within 3% of optimum. The inspector must decide whether the lift passes on density and on moisture.
Rework or dry the lift and retest before placing the next one. A wet-side lift that passes density can still rut and pump under construction traffic, which is why both criteria must be met.
Question 5.2-3: Choosing Between Two Consolidation Tests
Problem Statement
Two consolidation tests on the same clay stratum beneath a planned railroad bridge approach fill gave different compression indices, and the sample quality measurements differ as shown. The engineer must decide which compression index to use for the approach settlement and why.
Two tests on the same stratum disagree; sample quality decides which to trust.
Given and required for Question 5.2-3.
Given
Variable
Value
Description
Sample A
Cc = 0.45; Δe/e0 = 0.06, good to fair
Lunne et al. (1997) SQD
Sample B
Cc = 0.31; Δe/e0 = 0.12, poor
Required
Which Cc to use, and why
Equations
No equation is needed; the answer follows from the criteria listed under Given.
Steps
Step 1 · What does disturbance do?
It rounds the curve, hides σ′p and flattens the virgin line, lowering the measured Cc.
↓
Step 2 · Effect on design
The poor sample would underestimate settlement: unconservative.
↓
Step 3 · Choice
Use Sample A; record why Sample B was rejected.
↓
Solution
Use Cc = 0.45 from Sample A.
Solution
Use Cc = 0.45 from Sample A.
Disturbance always errs toward less compressible behavior beyond σ′p, so the lower value is the suspect one. Document the rejection with the SQD criteria in the report.
Question 5.2-4: Effective Friction Angle From Three CU Tests
Problem Statement
Three consolidated-undrained triaxial tests were run on clay from the foundation of a railroad embankment that is to be widened. The confining pressures, deviator stresses and pore pressures at failure are shown. The engineer must find the effective stresses at failure and the effective friction angle for the widening’s drained stability analysis.
(a) 550, 1,180 and 1,800 psf. (b) 2,390, 4,460 and 6,720 psf. (c) φ′ ≈ 33.5°.
The middle point lies close to the line through the outer two (predicted q = 920 + 0.552 × 1,350 = 1,665 psf against 1,640), so the three specimens are consistent.
Question 5.2-5: Reducing a Soaked CBR Test
Problem Statement
A soaked CBR test was run on the proposed subballast borrow for a Class I railroad siding. The test gave the loads shown at 0.1 and 0.2 in. of penetration, with a seating load. The engineer must correct the loads, compute the CBR and report the design value.
Given and required for Question 5.2-5.
Given
Variable
Value
Description
Loads
880 lb at 0.1 in.; 1,260 lb at 0.2 in.
Seating
15 lb at zero penetration
Standard loads
3,000 and 4,500 lb
Required
(a) Corrected loads
(b) CBR at 0.1 and 0.2 in.
(c) Design CBR
Equations
Eq. 1: CBR = (P − Pseat) / Pstd × 100%
Steps
Step 1 · (a) Corrected loads
865 lb and 1,245 lb
↓
Step 2 · (b) CBR
865/3,000; 1,245/4,500
28.8% and 27.7%
↓
Step 3 · (c) Design
0.1 in. governs: 28.8%
↓
Solution
Design CBR = 28.8%.
Solution
(a) 865 and 1,245 lb. (b) 28.8% and 27.7%. (c) Design CBR = 28.8%.
If the 0.2-in. value had been higher, ASTM D1883 calls for a repeat test; a higher value at 0.2 in. usually means a seating error at low penetration.
Question 5.2-6: Corrosivity Screening for a Soldier Pile Wall
Problem Statement
A soldier pile and lagging wall will support a cut beside a yard track for a Class I railroad located in Indiana. The piles pass through clean fill above the water table and old cinder fill below it. Corrosivity tests on one sample from each zone have come back from the laboratory. The engineer must decide whether either zone is aggressive to the steel piles, which results govern, and what to ask the laboratory about its procedure before finalizing the design (Section 5.2.30).
Figure 5.2-15. Question 5.2-6: soldier pile through two fill zones, with test results.
Low pH and resistivity drive general corrosion; Eh of −120 mV means reducing conditions in saturated organic cinders
Expect fast and possibly pitting corrosion by sulfate-reducing bacteria
Spot check: Even if drying had raised the sulfate result by 47%, the true value would be about 820/1.47 = 560 ppm, still well above 200 ppm: the classification does not change.
↓
Step 4 · (c) Procedure and response
Ask the method, extraction ratio and drying temperature; was B-2 sealed and tested promptly?
Design the piles for aggressive ground in the cinder zone
↓
Solution
B-1 not aggressive; B-2 aggressive on every criterion; design for aggressive ground below the water table.
Solution
(a) B-1 is not aggressive; B-2 is aggressive on all five criteria. (b) pH, resistivity and the reducing (low Eh) conditions govern; sulfate and chloride confirm it. (c) Question the oven-drying of the sulfate sample and confirm the methods, but the conclusion stands.
Design the steel for the cinder zone, not the average: options include a sacrificial thickness or heavier section based on an aggressive-ground loss rate, coatings over the length in the cinder fill, concrete encasement of the embedded pile, or a different wall type. Treat lagging and connections the same way. Take more samples along the wall alignment, because old cinder fills vary, and keep a sealed, unopened sample from below the water table for redox and sulfide testing. Disposal of excavated cinder fill may also need environmental testing (Chapter 5.4).