5.2.15 Practice Questions

Laboratory testing is the scientific foundation of every geotechnical design.
Authors: Daniel P. Colwell and Mario Ruel
5.2.15 Practice Questions
Each question is worked in the same five parts as the examples. Question 5.2-3 is a reasoning question.
Question 5.2-1: Compression Index, OCR and Which Settlement Equation

Problem Statement

A consolidation test was run on a tube sample from beneath a planned railroad embankment. The test gave the void ratios in the virgin range and the stresses shown. The engineer must compute the compression index and the overconsolidation ratio and decide which settlement equation applies to the embankment load.

1101.11.31.5σ′ (tsf, log scale)Void ratio e1.42 at 1.0 tsf1.18 at 4.0 tsfσ′v0 σ′p Cc = ?OCR = ? Which equation?Givene = 1.42 at 1.0 tsf (virgin)e = 1.18 at 4.0 tsf (virgin)σ′v0 = 0.80 tsfσ′p = 1.60 tsfRequired(a) Cc (b) OCR(c) Which Chapter 6.2 equationBlack = given; red = required
Given and required for Question 5.2-1.

Given

VariableValueDescription
Pointse = 1.42 at 1.0 tsf; e = 1.18 at 4.0 tsfVirgin range
σ′v00.80 tsf
σ′p1.60 tsfCasagrande

Required

  • (a) Cc
  • (b) OCR
  • (c) Which Chapter 6.2 equation applies

Equations

  1. Eq. 1: Cc = Δe / Δlog σ′
  2. Eq. 2: OCR = σ′p/σ′v0

Steps

Step 1 · (a) Cc
0.24 / 0.602
0.399
↓
Step 2 · (b) OCR
1.60/0.80
2.0
↓
Step 3 · (c) Equation
Depends on the final stress: recompression only if it stays below 1.60 tsf; recompression plus virgin compression if it exceeds it
↓
Solution
Cc = 0.40; OCR = 2.0; equation depends on the final stress.

Solution

(a) Cc = 0.40. (b) OCR = 2.0. (c) The overconsolidated equations; which one depends on whether the final stress passes 1.60 tsf.

The new load decides the case, so compute σ′vf = σ′v0 + Δσ before choosing.

Question 5.2-2: Field Density Acceptance

Problem Statement

A nuclear gauge test on a lift of fill for a new railroad yard gave the field density and moisture shown. The railroad’s specification requires 95% of Modified Proctor and moisture within 3% of optimum. The inspector must decide whether the lift passes on density and on moisture.

10141822110115120Water content w (%)γd (pcf)max 120.5 at 14.0%field 117.4 at 17.2%RC = ? Density and moisture pass?Givenγd,field = 117.4 pcfγd,max = 120.5 pcfw = 17.2%; wopt = 14.0%Spec: RC ≥ 95%; w ±3%Required(a) RC(b) Density pass or fail(c) Moisture pass or failBlack = given; red = required
Given and required for Question 5.2-2.

Given

VariableValueDescription
γd,field117.4 pcf
γd,max120.5 pcfModified Proctor
w, wopt17.2%; 14.0%
SpecRC ≥ 95%; w within ±3% of optimumRailroad requirement

Required

  • (a) RC
  • (b) Density pass or fail
  • (c) Moisture pass or fail

Equations

  1. Eq. 1: RC = γd,field/γd,max × 100%

Steps

Step 1 · (a) RC
117.4 / 120.5
97.4%
↓
Step 2 · (b) Density
97.4 ≥ 95
Pass
↓
Step 3 · (c) Moisture
Window 11.0 to 17.0%; field 17.2%
Fail, wet side
↓
Solution
RC 97.4% passes; moisture 17.2% fails.

Solution

(a) 97.4%. (b) Passes. (c) Fails: 0.2% above the wet limit.

Rework or dry the lift and retest before placing the next one. A wet-side lift that passes density can still rut and pump under construction traffic, which is why both criteria must be met.

Question 5.2-3: Choosing Between Two Consolidation Tests

Problem Statement

Two consolidation tests on the same clay stratum beneath a planned railroad bridge approach fill gave different compression indices, and the sample quality measurements differ as shown. The engineer must decide which compression index to use for the approach settlement and why.

Two tests on the same stratum disagree; sample quality decides which to trust.

0.1110σ′ (log scale)Void ratio eA: Cc = 0.45, Δe/e0 = 0.06B: Cc = 0.31, Δe/e0 = 0.12Which Cc to use, and why?GivenSample A: Cc = 0.45; Δe/e0 = 0.06 (good to fair)Sample B: Cc = 0.31; Δe/e0 = 0.12 (poor)Lunne et al. (1997) SQDRequiredWhich Cc to useWhyBlack = given; red = required
Given and required for Question 5.2-3.

Given

VariableValueDescription
Sample ACc = 0.45; Δe/e0 = 0.06, good to fairLunne et al. (1997) SQD
Sample BCc = 0.31; Δe/e0 = 0.12, poor

Required

  • Which Cc to use, and why

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · What does disturbance do?
It rounds the curve, hides σ′p and flattens the virgin line, lowering the measured Cc.
↓
Step 2 · Effect on design
The poor sample would underestimate settlement: unconservative.
↓
Step 3 · Choice
Use Sample A; record why Sample B was rejected.
↓
Solution
Use Cc = 0.45 from Sample A.

Solution

Use Cc = 0.45 from Sample A.

Disturbance always errs toward less compressible behavior beyond σ′p, so the lower value is the suspect one. Document the rejection with the SQD criteria in the report.

Question 5.2-4: Effective Friction Angle From Three CU Tests

Problem Statement

Three consolidated-undrained triaxial tests were run on clay from the foundation of a railroad embankment that is to be widened. The confining pressures, deviator stresses and pore pressures at failure are shown. The engineer must find the effective stresses at failure and the effective friction angle for the widening’s drained stability analysis.

The same method as Example 5.2-3.

0200040006000800001000200030004000Normal stress σ′ (psf)Shear stress (psf)σ′3, σ′1, φ′ = ?Givenσ3 = 1,000; 2,000; 3,000 psf(σ1−σ3)f = 1,840; 3,280; 4,920 psfuf = 450; 820; 1,200 psfRequired(a) σ′3 (b) σ′1 (c) φ′Black = given; red = required
Given and required for Question 5.2-4.

Given

VariableValueDescription
σ31,000; 2,000; 3,000 psf
(σ1 − σ3)f1,840; 3,280; 4,920 psf
uf450; 820; 1,200 psf

Required

  • (a) σ′3
  • (b) σ′1
  • (c) φ′

Equations

  1. Eq. 1: σ′3 = σ3 − uf; σ′1 = σ′3 + (σ1 − σ3)
  2. Eq. 2: sinφ′ = Δq / Δp′ — slope of the p′-q line

Steps

Step 1 · (a) σ′3
550; 1,180; 1,800 psf
↓
Step 2 · (b) σ′1
2,390; 4,460; 6,720 psf
↓
Step 3 · Radii and centers
q = 920, 1,640, 2,460; p′ = 1,470, 2,820, 4,260 psf
↓
Step 4 · (c) φ′
(2,460 − 920)/(4,260 − 1,470) = 1,540/2,790
sinφ′ = 0.552; φ′ = 33.5°
↓
Solution
φ′ ≈ 33.5°.

Solution

(a) 550, 1,180 and 1,800 psf. (b) 2,390, 4,460 and 6,720 psf. (c) φ′ ≈ 33.5°.

The middle point lies close to the line through the outer two (predicted q = 920 + 0.552 × 1,350 = 1,665 psf against 1,640), so the three specimens are consistent.

Question 5.2-5: Reducing a Soaked CBR Test

Problem Statement

A soaked CBR test was run on the proposed subballast borrow for a Class I railroad siding. The test gave the loads shown at 0.1 and 0.2 in. of penetration, with a seating load. The engineer must correct the loads, compute the CBR and report the design value.

0.10.20.30.450010001500Penetration (in.)Load (lb)880 lb1,260 lbseating 15 lbCorrected loads, CBR = ?Given880 lb at 0.1 in.; 1,260 lb at 0.2 in.Seating 15 lb at zero penetrationStandard 3,000 and 4,500 lbSubballast borrow, sidingRequired(a) Corrected loads(b) CBR at 0.1 and 0.2 in.(c) Design CBRBlack = given; red = required
Given and required for Question 5.2-5.

Given

VariableValueDescription
Loads880 lb at 0.1 in.; 1,260 lb at 0.2 in.
Seating15 lb at zero penetration
Standard loads3,000 and 4,500 lb

Required

  • (a) Corrected loads
  • (b) CBR at 0.1 and 0.2 in.
  • (c) Design CBR

Equations

  1. Eq. 1: CBR = (P − Pseat) / Pstd × 100%

Steps

Step 1 · (a) Corrected loads
865 lb and 1,245 lb
↓
Step 2 · (b) CBR
865/3,000; 1,245/4,500
28.8% and 27.7%
↓
Step 3 · (c) Design
0.1 in. governs: 28.8%
↓
Solution
Design CBR = 28.8%.

Solution

(a) 865 and 1,245 lb. (b) 28.8% and 27.7%. (c) Design CBR = 28.8%.

If the 0.2-in. value had been higher, ASTM D1883 calls for a repeat test; a higher value at 0.2 in. usually means a seating error at low penetration.

Question 5.2-6: Corrosivity Screening for a Soldier Pile Wall

Problem Statement

A soldier pile and lagging wall will support a cut beside a yard track for a Class I railroad located in Indiana. The piles pass through clean fill above the water table and old cinder fill below it. Corrosivity tests on one sample from each zone have come back from the laboratory. The engineer must decide whether either zone is aggressive to the steel piles, which results govern, and what to ask the laboratory about its procedure before finalizing the design (Section 5.2.30).

Upper fill,above water table Old cinder fill,below water table Soldier pile 12 Given: sample B-1 (upper fill) pH 6.8; resistivity 4,200 ohm-cmChloride 45 ppm; sulfate 150 ppmOrganic content 0.6% Given: sample B-2 (cinder fill) pH 4.6; resistivity 1,800 ohm-cmChloride 160 ppm; sulfate 820 ppm*Organic content 3.5%; Eh −120 mV *Sample oven-dried at 200°F before the sulfate test Required: classify each zone; response
Figure 5.2-15. Question 5.2-6: soldier pile through two fill zones, with test results.

Given

VariableValueDescription
B-1, upper fillpH 6.8; 4,200 ohm-cm; Cl 45 ppm; SO4 150 ppm; organics 0.6%Above the water table
B-2, cinder fillpH 4.6; 1,800 ohm-cm; Cl 160 ppm; SO4 820 ppm; organics 3.5%; Eh −120 mVBelow the water table; sulfate sample oven-dried at 200°F

Required

  • (a) Whether each zone is aggressive by the screening criteria
  • (b) Which results govern for B-2 and why redox matters
  • (c) What to question about the laboratory procedure, and the design response

Equations

  1. Screen (Section 5.2.30.3): aggressive if pH < 5 or pH > 10
  2. ρ < 3,000 ohm-cm
  3. Cl > 100 ppm
  4. SO4 > 200 ppm
  5. organic content > 1%

Steps

Step 1 · (a) B-1
pH 6.8 (5 to 10); 4,200 > 3,000; 45 < 100; 150 < 200; 0.6% < 1%
Not aggressive: passes all five
↓
Step 2 · (a) B-2
pH 4.6 < 5; 1,800 < 3,000; 160 > 100; 820 > 200; 3.5% > 1%
Aggressive: fails all five
↓
Step 3 · (b) Governing results
Low pH and resistivity drive general corrosion; Eh of −120 mV means reducing conditions in saturated organic cinders
Expect fast and possibly pitting corrosion by sulfate-reducing bacteria
Spot check: Even if drying had raised the sulfate result by 47%, the true value would be about 820/1.47 = 560 ppm, still well above 200 ppm: the classification does not change.
↓
Step 4 · (c) Procedure and response
Ask the method, extraction ratio and drying temperature; was B-2 sealed and tested promptly?
Design the piles for aggressive ground in the cinder zone
↓
Solution
B-1 not aggressive; B-2 aggressive on every criterion; design for aggressive ground below the water table.

Solution

(a) B-1 is not aggressive; B-2 is aggressive on all five criteria. (b) pH, resistivity and the reducing (low Eh) conditions govern; sulfate and chloride confirm it. (c) Question the oven-drying of the sulfate sample and confirm the methods, but the conclusion stands.

Design the steel for the cinder zone, not the average: options include a sacrificial thickness or heavier section based on an aggressive-ground loss rate, coatings over the length in the cinder fill, concrete encasement of the embedded pile, or a different wall type. Treat lagging and connections the same way. Take more samples along the wall alignment, because old cinder fills vary, and keep a sealed, unopened sample from below the water table for redox and sulfide testing. Disposal of excavated cinder fill may also need environmental testing (Chapter 5.4).