Railroad projects need soil chemistry results mainly to judge corrosion of buried steel and concrete (soldier piles, H-piles, corrugated metal culverts, anchors, soil nails), sulfate attack and sulfate heave in treated soil (Chapter 2.12; Section 7.2.7), and contamination (Chapter 5.4). Chemistry results depend on how the test is run and on what happened to the sample between the hole and the laboratory far more than most geotechnical index tests do (Conklin 2014).
| Test | How it is measured | What to watch |
|---|---|---|
| pH | pH meter in a soil–water mix, commonly 1:1 by weight (for example 10 g soil and 10 mL distilled water) after standing about 10 minutes | Tests in a salt solution (KCl or CaCl2) release exchangeable acidity and read lower (more acidic) than water tests. Corrosivity criteria assume the method in the governing standard, so the report must state the method and ratio. Do not let the laboratory substitute its own procedure. |
| Redox potential (Eh) | Platinum and reference electrodes on a pH meter, reported in mV | Low Eh means reducing (oxygen-free) conditions, typical of saturated and organic soil; these favor sulfate-reducing bacteria and microbially influenced corrosion. Eh depends on pH, so report both. Exposure to air changes Eh quickly: measure in the field or on sealed, promptly tested samples. |
| Electrical conductivity (EC) | Conductivity cell on a saturated-paste extract or on a soil–water extract, in dS/m | EC rises with dissolved salts. Soils with pH below 8.5 and EC above 4 dS/m are saline; high sodium makes soils sodic, which disperses clay. Extract EC (1 dS/m corresponds to about 1,000 ohm-cm in the extract) is not the same as soil-box resistivity of the saturated soil, so do not interchange them. |
| Sulfate and chloride | Water extraction, then ion analysis | The extraction ratio and the drying temperature both change the result (see below). |
| Moisture state | Air-dry soil still holds about 1–2% water, more in organic soil | Results reported on an air-dry basis should state the residual water content. |
FHWA guidance for buried steel reinforcement and soil nails treats ground as aggressive when any of the following applies: pH below 5 or above 10; resistivity below 3,000 ohm-cm; chloride above 100 ppm; sulfate above 200 ppm; or organic content above 1%. Use the same screen for soldier piles, H-piles, culvert pipe and anchors, and apply the railroad’s own criteria where they are stricter. Sulfate also governs concrete exposure class and the risk of sulfate heave in lime- or cement-treated soil.
For railroad work: Take corrosivity samples from the borings at the depths of buried steel and below the water table, not only from the surface, and specify the test standards (for example, AASHTO T 288, T 289, T 290 and T 291, or ASTM G51 and G187) in the laboratory request. Seal and cool the samples, and ask for pH and redox to be run first. In saturated organic ground, cinders, or old fills beneath yards, measure redox and look for sulfides, because reducing conditions can make steel corrode quickly even when pH and resistivity look acceptable. Report the method, the extraction ratio and the drying temperature with every result so that later tests can be compared.
Source: Conklin (2014), Chapters 5–9; screening limits from FHWA corrosion guidance for MSE walls and soil nails. Full reference under Supplemental References.