5.2.16 Case Studies

Laboratory testing is the scientific foundation of every geotechnical design.
Authors: Daniel P. Colwell and Mario Ruel
5.2.16 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S8 under Supplemental References.

Case Study 10.16.1 — Curing time changes compaction and CBR results
Case study · Look (2023) §5.8

Related section: 5.2.3 Test Methods — ASTM Standards and English Unit Outputs

Samples of Bundamba clay (plasticity index 47%, 97% passing No. 40, 69%–82% fines) were cured for 0, 1, 4 and 7 days before compaction and soaked and unsoaked CBR testing:

  • Short curing gave a higher maximum dry density, so the field material is more likely to fail its density ratio or need extra compactive effort.
  • Short curing gave higher CBR swell, which would trigger more remove-and-replace than is needed (typically 10 in. for the swell measured). Whether the sample arrived wet or dry also changed the swell when curing was inadequate.
  • Short curing gave a higher unsoaked CBR (thinner pavement, more long-term failures) and a lower soaked CBR (over-designed pavement).

For railroad work: plastic clay subgrade samples for CBR, resilient modulus or Proctor testing should be cured to the period the test standard requires, and the curing time should be reported. A test turned around too quickly can push the design either way.

Curing 0–1 days gave a higher MDD than 4–7 days for a high-plasticity clay.
Figure 10-LK1. Curing 0–1 days gave a higher MDD than 4–7 days for a high-plasticity clay. Source: Look (2023), Figure 5.8-1, p. 143.
Curing time against soaked CBR and swell: short curing lowers soaked CBR and raises swell.
Figure 10-LK2. Curing time against soaked CBR and swell: short curing lowers soaked CBR and raises swell. Source: Look (2023), Figure 5.9-1, p. 143.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §5.8, pp. 142. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 10.16.2 — Laboratory variation in Cooroy clay compaction curves
Case study · Look (2023) §7.9

Related section: 5.2.5 Laboratory QA/QC

Eleven standard compaction tests on clay from one project site at Cooroy, Queensland (55 compaction points) gave maximum dry densities from 97–104 pcf, median about 101 pcf, and optimum moisture contents from 18.6% to 24.5%, median 21.5%. The idea of a unique MDD and OMC does not hold for clays. The repeatability allowed in the Australian standard suggests 85%–115% of OMC as a realistic moisture window, yet many specifications ask for ±2% of OMC, which testing variation alone makes unachievable.

The real target is low air voids: much below 85% of OMC, air voids exceed about 10%. Look also warns that the compacted soil will not stay at its placement moisture, so the moisture target should guide field effort and not be a pass/fail criterion. Density is the pass/fail measure. Compaction well above MDD or dry of OMC raises suction, so the “stronger” material is more sensitive to later moisture change.

For railroad work: the ±2% moisture band suits processed granular materials such as subballast, not high-moisture clays in embankment or subgrade. Use a band that reflects the laboratory’s own repeatability.

Individual five-point compaction curves for 11 samples of Cooroy clay: MDD 97–104 pcf, OMC 18.6%–24.5%.
Figure 10-LK3. Individual five-point compaction curves for 11 samples of Cooroy clay: MDD 97–104 pcf, OMC 18.6%–24.5%. Source: Look (2023), Figure 7.9-1, p. 233.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §7.9, pp. 230–232. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.