5.2.1 Background and Railroad Context

Laboratory testing is the scientific foundation of every geotechnical design.
Authors: Daniel P. Colwell and Mario Ruel
5.2.1 Background and Railroad Context

The laboratory testing program for a railroad geotechnical investigation must be:

  1. Purposeful. Every test must serve a defined analytical need. Ordering triaxial shear strength tests for a track subgrade investigation without a slope stability analysis to use them wastes budget and delays the schedule. Order only what the analysis matrix demands.
  2. Sufficient. Under-testing is the more common and more dangerous failure mode. A single consolidation test in a soft clay stratum extending over 500 ft is not statistically defensible. A minimum of one test per identified stratum per project segment, plus additional tests where variability is observed, is a reasonable minimum; confirm the owner railroad's expectations.
  3. QA-verified. Owner railroads that maintain laboratory accreditation requirements (see Section 5.2.8) will reject data produced by non-accredited laboratories. Confirm accreditation before awarding the laboratory subcontract.