5.2.12 Practical Recommendations

Laboratory testing is the scientific foundation of every geotechnical design.
Authors: Daniel P. Colwell and Mario Ruel
5.2.12 Practical Recommendations
  1. Write the laboratory test program before the field crew mobilizes. A well-designed test program begins with the analysis matrix (Table 5.2-1). Know which tests are needed before drilling begins so that samples are collected, preserved, and shipped appropriately. Changing the test program after samples have dried or disturbed is expensive and unreliable.
  2. Confirm laboratory accreditation per-method, not per-lab. An AAP-accredited lab may be accredited for D2216 and D4318 but not for D4767 (CU triaxial). Always verify the accreditation scope certificate for every test method in the program. Owners that require accreditation may reject data produced outside its scope.
  3. Ship Shelby tubes within 72 hours of collection. Sample quality degrades with time, handling, and temperature cycling. The SQD classification (Section 5.2.4.1) will reveal disturbance — but by then the sample is consumed. Minimize handling, seal immediately, and ship promptly.
  4. Always run water content on all samples, even those not assigned to formal tests. Water content needs little labor and costs almost nothing. It documents the in-situ condition of every sample and supports stratigraphic correlation, parameter estimation, and QC. A boring with 20 samples and only 5 water contents is professionally incomplete.
  5. Request electronic data delivery in addition to PDF reports. All major geotechnical laboratories can deliver test data in CSV or Excel format. Request this at the time of laboratory subcontract award. Electronic data is essential for efficient entry into calculation spreadsheets and prevents transcription errors from PDF reports.
  6. Verify specific gravity before computing void ratio in consolidation analysis. The void ratio calculation (e = G_s × γ_w / γ_d − 1) is directly affected by G_s. Assuming G_s = 2.70 for a kaolin-rich clay (G_s may be 2.60–2.65) overestimates e₀, and because Δe scales with 1 + e₀ it also overstates C_c. Always measure G_s on the same material used for consolidation testing.
  7. For projects in Canada, confirm metric vs. English unit reporting requirements with the laboratory. Canadian laboratories report in SI units by default. Specify English unit output in the lab subcontract, or include a unit conversion table in the laboratory report appendix, and verify conversions before using values in design.
Geotechnical laboratory testing for earth dam clay cores
Geotechnical laboratory testing for earth dam clay cores
← Previous · 5.0 Testing Chapter 5.1 — In Situ Testing
Next · 5.0 Testing → Chapter 5.3 — Construction Monitoring and Field Testing