This chapter covers how site conditions are compiled from the desktop study, the reconnaissance and the borings, and how they are written up. A good site conditions section is short, factual and in a fixed order, and it separates what was observed from what is expected and from what is concluded.
The site conditions section is the bridge between the data and the recommendations. It tells a reader who has never been to the site what is there: the land and its history, the ground and the water, the structures and utilities, and the track and its traffic. It appears in the proposal (as expected conditions), in the reconnaissance report (as observed conditions) and in the final report (as conditions confirmed by the borings).
| Stage | Main sources | How it is written |
|---|---|---|
| Proposal | Desktop study: maps, legacy borings, soil survey, history (Chapter 3.2) | Anticipated conditions, by area or reach, with the design concern for each |
| Reconnaissance | Walk-over, photographs, lidar (Chapter 3.4) | Observed surface conditions and access |
| Report | Borings, laboratory tests, groundwater readings | Subsurface profile confirmed; differences from expected conditions noted |
Describe the shape of the ground: elevations, relief, slopes, benches and drainage paths. Lidar (USGS 3DEP 1-m, about 3-ft, DEM) gives elevations at every boring and along every access route for planning; surveyed elevations at the time of drilling replace them in the report.
State the source and date of the elevations. Lidar collected years before the work will not show recent fill, stockpiles or ruts, and phone GPS altitudes can differ from lidar by several feet.
Give the regional geology in two or three sentences (bedrock formation and depth, surficial deposits) and then the expected or confirmed profile as a table. Where conditions change along a linear project, describe them by reach, each with its nearest data and its main design concern.
| Reach | Nearest data | Expected under the new slope | Main design concern |
|---|---|---|---|
| A | Hand auger: stiff sandy lean clay with gravel, N 8 to 25, dry | Lean clay embankment fill over alluvial clay; rock depth unknown | No data under the toe of the steepened slope |
| B | Boring: thin cinder fill; very soft organic clay at 2.5 to 3 ft (N 3); stiff clay; limestone fragments at 8 ft | Soft organic clay in the upper 2 to 4 ft; breccia from about 8 to 20 ft, highly variable | Undercut depth; variable rock; possible voids |
| C | Hand auger: soft gray fat clay from 2 to 6+ ft (N 1 to 2); water at 4 ft; next to a wetland | Soft fat clay at least 6 ft thick, bottom not found; ponding | Critical reach: stability on soft clay, settlement, undercut versus buttress |
| D | Shallow stiff lean clay; culvert under the track | Thin clay over rock; ditch cuts may hit rock | Ditch grade in rock |

Report groundwater as measured (at drilling, completion and 24 hours, with dates), and say what it means: depth below grade, relation to nearby lakes, rivers and ditches, perched water over clay or rock, and seasonal change. Describe surface water features (streams, ditches, swales, ponds) with their flow, condition and any odor or staining.
| Write | Avoid |
|---|---|
| "Groundwater was measured at 4 ft below grade at completion of HA-14 on [date]." | "Groundwater is at 4 ft." (a single reading is not a design level) |
| "Ground surface is 5 to 13 ft above the lake; groundwater is expected within a few feet of the surface." | Leaving out the reason groundwater is high |
| "Water levels in nearby wells are 145 to 200 ft deep and variable, typical of karst aquifers; perched water may occur over rock." | Treating deep regional water as the design level for a fill on clay |
Note what affects the work and the design: design frost depth, freeze-thaw cycling (rockfall, subgrade pumping), seasonal wetness, and vegetation. Vegetation matters twice: it controls access and clearing (Chapter 3.6), and it is evidence. Phragmites, cattails and reed canary grass mark wet ground; leaning trees mark creep; invasive thickets (buckthorn, bush honeysuckle) usually mean old disturbed fill.

List the structures and utilities that the work must avoid or that the design must account for: bridges and culverts (type, size, material, condition), retaining walls, signal masts and cabinets, buried cables and conduits, sewers and storm drains, overhead power. Take them from the railroad valuation maps and confirm them in the field.
| Item | Record |
|---|---|
| Culverts | Location (station), size, material, length, inlet and outlet condition, flow |
| Bridges and walls | Location, type, foundation if known, condition |
| Signals and communications | Masts, cabinets, foundations, conduits at grade; keep borings clear |
| Sewers and storm drains | Size and location from valuation maps and city atlases; relation to ditches and odors |
| Overhead lines | Clearance for the drill mast |

Describe what the track carries, because it sets the consequence of failure (severity in Chapter 3.8) and the loads for design: main or siding, number of tracks, track class and speed, tonnage, passenger and hazardous materials traffic, and the importance of the route (redundancy, detours). Note the geometry-defect and slow-order history at the site and the condition of ballast, shoulder and ditches.
| Constraint | Typical sources | Effect |
|---|---|---|
| Wetlands | National Wetlands Inventory; delineation if needed | Boring offsets; clearing method; possible permit |
| Flood zone | FEMA flood maps | Floodplain permit for fill; seasonal access |
| Protected species and nesting birds | IPaC report; migratory bird windows | Clearing outside the local migratory bird nesting season (the dates vary by region; the U.S. Fish and Wildlife Service field office gives them), or a nest check |
| Contaminated or regulated sites | State and federal databases; radius report | Screening, drummed cuttings, extra tests (pH, sulfate, chloride, resistivity) |
| Property lines and right-of-way | County parcels; railroad valuation maps | Right-of-entry; public-way permits for borings outside the railroad parcel |
Close with a short summary that a reader could use on its own, in the order of this chapter, and a line on each condition that controls design. Keep observed, expected and concluded statements separate.
| Topic | Refer to |
|---|---|
| Desktop study | Chapter 3.2 |
| Reconnaissance | Chapter 3.4 |
| Access study | Chapter 3.6 |
| Soil and rock classification | Chapter 2.2 |
| Problem soils | Chapters 2.4 to 2.7 |
| Groundwater | Chapter 2.8 |
| Severity and consequence | Section 3.8.20 |
| Report preparation | Chapter 8.4 |
Water is the most common trigger of track failure, and the culverts through an embankment set how much water it holds back. The site-conditions review should therefore establish the drainage area of each crossing, a design flow, and whether the existing opening is adequate. AREMA Chapter 1, Parts 3 and 4, give the rational method for small basins and the culvert design criteria; railroad culvert guidelines add a 100-year design storm, E80 loading, and a 36 in. minimum pipe.
Equation 3.5-1. Peak flow and time of concentration
Q in cfs, i in in./hr for a duration equal to tc, A in acres; tc in minutes, L in ft, S in ft/ft. Use the rational method with caution above about 300 acres (Kirpich is intended for agricultural basins under 200 acres).
| Vegetation and slope | Open sandy loam | Clay and silt loam | Tight clay |
|---|---|---|---|
| Woodland: flat / rolling / hilly | 0.10 / 0.25 / 0.30 | 0.30 / 0.35 / 0.50 | 0.40 / 0.50 / 0.60 |
| Pasture: flat / rolling / hilly | 0.10 / 0.16 / 0.22 | 0.30 / 0.36 / 0.42 | 0.40 / 0.55 / 0.60 |
| Cultivated: flat / rolling / hilly | 0.30 / 0.40 / 0.52 | 0.50 / 0.60 / 0.72 | 0.60 / 0.70 / 0.82 |
Flat 0 to 5%, rolling 5 to 10%, hilly 10 to 30% slope. Urban values are in AREMA Table 1-3-2; a railroad yard is 0.20 to 0.35.
| Flood | Criterion |
|---|---|
| 25-year | Discharged without static head at the entrance (HW/D ≤ 1.0) |
| 100-year | Headwater no higher than the available head, 2 ft below base of rail, or 1.5 times the diameter, whichever is least |
The calculator computes inlet-control headwater with the FHWA HDS-5 equations that underlie the charts AREMA cites. Outlet control (barrel friction and tailwater) should also be checked for long or flat culverts.
| Result | Value |
|---|---|
| Time of concentration (Kirpich) | 18.7 min |
| Q25 / Q100 | 86 cfs / 112 cfs |
| 60 in. corrugated metal pipe with headwall: HW/D at Q25 | 0.76 |
| Headwater at Q100 (limit 7.5 ft) | 4.5 ft |
| Adequate (inlet control) | yes |
Rainfall intensities are illustrative; read them from the local intensity-duration-frequency curve at tc.
Open the culvert hydrology calculator →
Rational-method peak flows with Kirpich or Kerby time of concentration, and inlet-control headwater checked against the AREMA criteria.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.
The rational method in this section suits small basins. For larger or mixed-use basins, and wherever the runoff volume or the shape of the flood matters, the NRCS (formerly SCS) methods are used.
S = 1000 / CN − 10 Ia = 0.2 S Q = (P − Ia)2 / (P − Ia + S) for P > Ia
For railroad work: Use the curve number method where a culvert or bridge drains more than a few hundred acres, where the basin is urbanizing (raise CN for future development, since railroad culverts outlast the land use around them), or where water ponds against the embankment and the volume matters for seepage and stability during the flood (Chapter 2.8, Chapter 6.3). A change in CN upstream is one of the triggers worth recording in the desktop study and the live rating (Chapter 3.8).
Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 304, Hydrology.
Larger basins, ponding and snowmelt: flood hydrographs, routing behind embankments and flood frequency are in Section 3.5.12; snowmelt and rain on snow in Section 3.5.13.
Washouts are among the most frequent and costly ground hazards on a railroad: flood flow along an embankment toe, overtopping at a low point, and scour at a culvert outlet or bridge abutment can remove the support from under the track in hours. Riprap is the usual protection. The site conditions review (Sections 3.5.3 and 3.5.10) gives the design flow and velocity; this section turns them into a stone size, a stone weight and a layer thickness, so a field team can tell whether existing riprap is adequate and an estimate can carry the right stone class.
Equation 3.5-2. Bank and channel riprap (FHWA HEC-11)
D50 and davg in ft, Va = average velocity in ft/s; θ = bank angle; φ = angle of repose of the stone (about 40° to 42° for angular rock); SF = stability factor (Table 3.5-10).
Equation 3.5-3. High-turbulence locations (Isbash)
For abutments, overtopping flow at the crest and shoulder, spur dikes and other locations where the local velocity is known but the flow is not uniform.
Equation 3.5-4. Culvert outlet apron (FHWA HEC-14 Eq. 10.4)
D = culvert diameter (ft); Q in cfs; TW = tailwater depth, not less than 0.4D. Above a discharge intensity of about 6 use a riprap basin or energy dissipator.
| Condition | SF |
|---|---|
| Uniform flow, straight or mildly curving reach (radius/width above about 30), little debris or wave impact | 1.0–1.2 |
| Gradually varying flow, moderate bends (radius/width 10 to 30), some debris or waves | 1.3–1.6 |
| Rapidly varying flow, sharp bends, flow impinging on the bank, heavy debris or ice | 1.6–2.0 |
A typical gradation has D100 about 2D50 and D15 about 0.5D50. The layer should be at least the larger of D100, 1.5D50 and 12 in., increased by half where it is placed under water, and it needs a granular or geotextile filter beneath it and a toe keyed below the expected scour depth. The stone weight is W50 = (π/6)γsD50³.
A fill on a Class I railroad located in Missouri runs along a river at the outside of a bend. The design flood gives an average velocity of 10 ft/s at a depth of 6 ft against the 2H:1V embankment slope. The existing protection is a scatter of 6-in. stone.
| Variable | Value | Description |
|---|---|---|
| Va | 10 ft/s | Average velocity, design flood |
| davg | 6 ft | Average depth |
| Slope | 2H:1V (θ = 26.6°) | Embankment |
| φ | 41° | Angle of repose, angular stone |
| SF | 1.5 | Outside of a moderate bend (Table 3.5-10) |
| Ss | 2.65 | Quarried limestone |
The toe needs riprap with a median size of about 11 in. (66 lb), graded to about 22 in., in a 22-in. layer on a filter, keyed below the scour depth.
The existing 6-in. stone is about half the required size and would move in the design flood; at 6 in. the slope is protected only to about 8 ft/s (the calculator’s chart). Rate the site in the risk assessment accordingly (Chapter 3.8), and specify the nearest standard stone class at or above D50 = 11 in. in the estimate.
Open the riprap calculator →
HEC-11 bank and channel riprap, the Isbash relation for turbulent locations, and HEC-14 culvert outlet aprons, with stone weight, gradation, layer thickness and a stone-size chart.
The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.
Section 3.5.10 gives the peak flow for a small basin. Larger basins, embankments that pond water behind them, and any crossing where the volume or timing of a flood matters need a flood hydrograph: losses, transformation of rainfall excess to runoff, routing through channels and storage, and a frequency for the result. The USACE manual Flood-Runoff Analysis (EM 1110-2-1417) sets out these methods and how to choose among them.
| Component | Common methods | Notes for railroad basins |
|---|---|---|
| Precipitation | Design storm from NOAA Atlas 14; historical storm; probable maximum precipitation (PMP) for dam-related studies | Use the storm duration that gives the highest peak for the basin, usually at least the time of concentration. |
| Losses | Initial and constant loss rate; NRCS curve number; Green-Ampt; continuous soil-moisture accounting | Frozen ground, saturated antecedent conditions and burned areas cut losses sharply. |
| Runoff transformation | Unit hydrographs: Snyder, Clark, NRCS dimensionless; kinematic wave | Calibrate parameters to gauged floods in the region where possible. |
| Channel routing | Muskingum, Muskingum-Cunge, modified Puls | Floodplain storage lowers and delays the peak downstream. |
| Storage routing | Level-pool (modified Puls) through the storage behind an embankment or reservoir | An embankment with a culvert is a small dam: ponding lowers the outflow peak but raises the headwater. |
| Frequency | Gauged flood frequency (Log-Pearson Type III per USGS Bulletin 17C); regional regression (USGS StreamStats); frequency of the design storm | Compare model results with regional regression estimates. |
Eq. 3.5-5: tl = Ct (L Lca)0.3 (hr), the lag from the center of the rainfall excess to the peak, with L = main watercourse length to the divide (mi) and Lca = length to the point opposite the basin centroid (mi).
Eq. 3.5-6: tr = tl / 5.5 (standard duration); for another duration tR, tlR = tl + 0.25 (tR − tr).
Eq. 3.5-7: Qp = 640 Cp A / tlR (cfs per inch of excess), with A in mi².
Snyder’s original Ct and Cp came from the Appalachian region; values elsewhere differ substantially, so calibrate them with regional data or use a regional regression for lag (EM 1110-2-1417, Ch. 7).
Where a culvert is small compared with the flood, water ponds behind the embankment. Level-pool routing uses the storage-elevation curve upstream and the culvert rating curve to find the outflow hydrograph and the maximum headwater. The outflow peak is lower than the inflow peak, which helps downstream, but the embankment then holds water like a dam: it saturates, seeps, and can pipe or fail by rapid drawdown when the pond falls (Chapter 6.3, Section 6.3.8). If the culvert blocks with debris or ice, the pond can overtop the track. Dams near the line are covered in Chapter 2.8, Section 2.8.15.
At a gauged site, fit annual peak flows with the Log-Pearson Type III distribution following USGS Bulletin 17C (published in 2018, current version 1.1 of 2019, the successor to Bulletin 17B). At ungauged sites, use the USGS regional regression equations through StreamStats, and transfer gauged results to the site by drainage-area ratio where a nearby gauge is on the same stream. A rainfall-runoff model run with a 100-year storm does not automatically give the 100-year flood; check it against the frequency estimates.
A Class I railroad located in Kentucky is replacing a 72-in. culvert under a 30-ft embankment. The rational method of Section 3.5.10 is not suitable for the 4.2-mi² basin, so the engineer builds a Snyder unit hydrograph as a check on the hydrology consultant’s model. Regional studies give Ct = 2.0 and Cp = 0.60, and the 100-year storm gives 2.9 in. of rainfall excess by the curve number method.
| Variable | Value | Description |
|---|---|---|
| A | 4.2 mi² | Drainage area |
| L | 6.0 mi | Main watercourse length to the divide |
| Lca | 2.8 mi | Length to the point opposite the centroid |
| Ct, Cp | 2.0, 0.60 | Regional Snyder coefficients |
| tR | 1.0 hr | Desired unit hydrograph duration |
| Q | 2.9 in. | 100-year rainfall excess (curve number method) |
tl = 4.66 hr; the 1-hour unit hydrograph peaks at about 343 cfs per inch; the 100-year peak cannot exceed about 1,000 cfs, and will be lower because the excess falls over several hours.
If all 2.9 in. of excess fell in one hour, the peak would be about 1,000 cfs. Real storms spread the excess over several hours, so the convolved peak will be lower; a value from the consultant’s model much above 1,000 cfs points to an error, and one far below (say under half) needs explaining. Compare the result with the USGS regional regression estimate for the site. Then route the hydrograph through the storage behind the 30-ft embankment: the pond may lower the outflow peak enough to allow a smaller pipe, but the design must then account for the headwater on the embankment and the risk of blockage.
A Class I railroad located in Iowa has a 60-in. culvert under a 14-ft embankment in a broad valley. Base of rail is 12 ft above the culvert invert, so the railroad’s criterion of headwater at least 2 ft below base of rail limits headwater to 10 ft. The design flood hydrograph is triangular. Water ponds behind the fill, so the engineer must route the flood through the storage to find the peak outflow and the maximum headwater, and check what happens if debris blocks half of the culvert.
| Variable | Value | Description |
|---|---|---|
| I(t) | 0 to 400 cfs at 2.0 hr, back to 0 at 5.0 hr | Triangular inflow hydrograph |
| S(H) | 30,000 H² ft³ | Storage upstream of the embankment, from the topography |
| O(H) | 25 H1.5 cfs | Culvert rating (inlet control) fitted to HDS-5 headwater values |
| Δt | 0.5 hr (1,800 s) | Routing time step |
| Hmax | 10 ft | Allowable headwater |
| t (hr) | Inflow I (cfs) | Outflow O (cfs) | Headwater H (ft) |
|---|---|---|---|
| 0.5 | 100 | 39 | 1.35 |
| 1.0 | 200 | 103 | 2.56 |
| 1.5 | 300 | 174 | 3.64 |
| 2.0 | 400 | 250 | 4.64 |
| 2.5 | 333 | 297 | 5.21 |
| 3.0 | 267 | 298 | 5.22 |
| 3.5 | 200 | 273 | 4.92 |
| 4.0 | 133 | 229 | 4.37 |
| 4.5 | 67 | 172 | 3.62 |
| 5.0 | 0 | 105 | 2.61 |
| 5.5 | 0 | 46 | 1.50 |
| 6.0 | 0 | 14 | 0.68 |
| H (ft) | S (ft³) | O (cfs) | 2S/Δt + O (cfs) |
|---|---|---|---|
| 1 | 30,000 | 25.0 | 58.3 |
| 2 | 120,000 | 70.7 | 204.0 |
| 3 | 270,000 | 129.9 | 429.9 |
| 4 | 480,000 | 200.0 | 733.3 |
| 5 | 750,000 | 279.5 | 1,112.8 |
| 6 | 1,080,000 | 367.4 | 1,567.4 |
(a) About 298 cfs at about 3.0 hr, 25% below the inflow peak. (b) About 5.2 ft, within the 10-ft limit. (c) Half blocked: about 227 cfs and 6.9 ft, still within the limit but with about 1.4 million ft³ held against the fill.
The pond helps the culvert: the outflow peak is a quarter lower and an hour later than the inflow peak. The cost is that the embankment holds 5 to 7 ft of water for several hours. Check the fill for seepage and piping along the culvert barrel at that head, and for rapid drawdown as the pond falls (Chapter 6.3, Section 6.3.8). The half-blocked case shows how much headroom is left for debris or ice; full blockage would raise the pond toward the track, so keep the inlet clear and add a trash rack or debris deflector if the basin delivers woody debris. Real storage curves and culvert ratings come from survey and HDS-5 or HY-8; the fitted power-law forms here keep the hand calculation short.
Where the flood is measured or modeled upstream and the crossing is some distance down the valley, the hydrograph changes along the reach: storage in the channel and floodplain lowers the peak and delays it. The Muskingum method treats reach storage as S = K[XI + (1 − X)O], where K is the travel time of the flood wave through the reach and X (0 to 0.5) weights inflow against outflow. X near 0 means strong floodplain storage and attenuation; X near 0.5 means the wave passes almost unchanged. Solving the storage equation over a time step gives the routing equation:
Eq. 3.5-12: O2 = C0I2 + C1I1 + C2O1, with C0 = (Δt − 2KX)/D, C1 = (Δt + 2KX)/D, C2 = [2K(1 − X) − Δt]/D and D = 2K(1 − X) + Δt. The coefficients sum to 1.
Eq. 3.5-13: 2KX ≤ Δt ≤ 2K(1 − X), the time-step range that keeps all three coefficients positive. K and X are best calibrated from upstream and downstream gauged hydrographs; without them, K can be estimated as reach length divided by flood-wave celerity (about 1.5 times the mean velocity for a wide channel), and Muskingum-Cunge computes K and X from the channel geometry, slope and roughness (EM 1110-2-1417, Ch. 9).
A Class I railroad located in Ohio crosses a creek on a ballast-deck bridge 3.0 mi downstream of a USGS stream gauge. During a storm the gauge records the hydrograph in Table 3.5-14, peaking at 1,000 cfs 4 hr after the start of the rise. The bridge waterway passes 900 cfs with 2 ft of freeboard to low chord. The railroad’s storm watch needs to know the peak flow and its arrival time at the bridge, and whether a slow order or closure is warranted.
| Variable | Value | Description |
|---|---|---|
| L | 3.0 mi (15,840 ft) | Reach length, gauge to bridge |
| c | 2.2 ft/s | Flood-wave celerity (from the gauge rating and channel survey) |
| X | 0.2 | Weighting factor, moderate floodplain storage |
| Δt | 1 hr | Routing time step (gauge reports hourly) |
| I(t) | 100 cfs base; peak 1,000 cfs at 4 hr | Gauge hydrograph (Table 3.5-14) |
| Qcap | 900 cfs | Bridge waterway capacity with 2 ft freeboard |
| t (hr) | Inflow I (cfs) | C0I2 | C1I1 | C2O1 | Outflow O (cfs) |
|---|---|---|---|---|---|
| 0 | 100 | – | – | – | 100 |
| 1 | 300 | 14.3 | 42.9 | 52.4 | 110 |
| 2 | 600 | 28.6 | 128.6 | 57.4 | 215 |
| 3 | 900 | 42.9 | 257.1 | 112.4 | 412 |
| 4 | 1,000 | 47.6 | 385.7 | 216.0 | 649 |
| 5 | 850 | 40.5 | 428.6 | 340.1 | 809 |
| 6 | 650 | 31.0 | 364.3 | 423.9 | 819 |
| 7 | 480 | 22.9 | 278.6 | 429.0 | 730 |
| 8 | 350 | 16.7 | 205.7 | 382.6 | 605 |
| 9 | 260 | 12.4 | 150.0 | 316.9 | 479 |
| 10 | 200 | 9.5 | 111.4 | 251.1 | 372 |
| 11 | 160 | 7.6 | 85.7 | 194.9 | 288 |
| 12 | 130 | 6.2 | 68.6 | 151.0 | 226 |
| 13 | 110 | 5.2 | 55.7 | 118.2 | 179 |
| 14 | 100 | 4.8 | 47.1 | 93.9 | 146 |
(a) K = 2.0 hr; C0 = 0.048, C1 = 0.429, C2 = 0.524; a 1-hr step lies within 0.8 to 3.2 hr. (b) About 819 cfs at 6 hr, 18% below the gauge peak. (c) About 2 hr of warning after the gauge peaks; the routed peak stays 81 cfs below the 900-cfs waterway capacity.
The gauge gives the storm watch a real lead time: a gauge peak near 1,000 cfs means the bridge sees about 820 cfs two hours later, so the bridge can stay in service with an inspector watching for drift and scour at the piers. Routing the reach shows how much margin is left: a gauge peak of about 1,100 cfs would bring the bridge to its waterway capacity, and that is a practical trigger for a slow order or closure in the storm-watch plan (Chapter 7.4). Drift lodged on the piers reduces the waterway, so the capacity used for the trigger should allow for it. Muskingum routing assumes the reach has no large tributary inflow between the gauge and the bridge; add local inflow from the intervening area if it is more than a few percent of the gauged area. Where the reach is long, ungauged or the floodplain changes along it, use Muskingum-Cunge or HEC-RAS unsteady flow.
For railroad work: Ask for the full hydrograph, not only the peak, for any culvert or bridge draining more than a few hundred acres, and for any crossing where the embankment ponds water. Review the loss and unit hydrograph parameters against regional values and the frequency result against regional regression. Treat a high embankment with a small culvert as a dam: check seepage, piping and rapid drawdown at the maximum pond level, and plan for blockage by debris or ice.
Sources: USACE (1994), Flood-Runoff Analysis, EM 1110-2-1417, Chs. 6–9, 11 and 13. Official page ↗ England, J. F. et al. (2019), Guidelines for Determining Flood Flow Frequency, Bulletin 17C, USGS Techniques and Methods 4-B5. Official page ↗ USGS StreamStats. Official page ↗ Summarized and paraphrased.
On many northern and mountain lines the largest floods, washouts and spring slope failures come from snowmelt, often with rain falling on the snow. The USACE manual Runoff from Snowmelt (EM 1110-2-1406) describes how snowmelt is measured, computed and turned into runoff.
Eq. 3.5-8: Ms = Cm (Ta − Tb), where Ms = melt (in./day), Ta = air temperature (°F), Tb = base temperature (usually 32°F) and Cm = melt-rate factor. Cm is typically 0.04 to 0.08 in./°F-day for rain-free conditions and higher during rain on snow with wind; calibrate it for the basin, because it changes through the season with snow albedo and sun angle.
During rain on snow the sky is overcast and the air saturated, and condensation of warm moist air on the snow, driven by wind, supplies most of the melt; the rain itself adds relatively little heat. The generalized equations (EM 1110-2-1406, Eqs. 5-19 and 5-20) give daily melt M (in./day):
Eq. 3.5-9 (open to partly forested, 10 to 80% canopy): M = (0.029 + 0.0084 k v + 0.007 Pr)(Ta − 32) + 0.09
Eq. 3.5-10 (heavily forested, over 80% canopy): M = (0.074 + 0.007 Pr)(Ta − 32) + 0.05
where k = basin wind exposure coefficient (1.0 for open plains, as low as 0.3 in forest), v = wind speed (mph, at 50 ft), Pr = rainfall (in./day) and Ta = temperature of the saturated air (°F, at 10 ft). The total water input to the ground is melt plus rain.
A Class I railroad located in Montana has a culvert draining a 1.5-mi² partly forested basin. A warm Pacific storm is forecast to bring 2.0 in. of rain in 24 hours at about 45°F with 15-mph wind, onto a ripe snowpack holding more than 6 in. of SWE over frozen ground. The engineer must estimate the water reaching the culvert, to judge whether a slow order and culvert watch are needed.
| Variable | Value | Description |
|---|---|---|
| A | 1.5 mi² | Drainage area, partly forested |
| k | 0.6 | Basin wind exposure coefficient |
| v | 15 mph | Wind speed |
| Ta | 45°F | Air temperature, saturated |
| Pr | 2.0 in./day | Rainfall |
| Runoff | 100% of water input | Ripe snowpack over frozen ground (assumption) |
Melt adds about 1.6 in. to the 2.0 in. of rain, for about 3.6 in. of water in a day and a mean flow near 146 cfs, about 1.8 times the flow from rain alone.
The peak flow will be well above the 146-cfs daily mean, because the rain and melt are not uniform through the day. If the culvert was sized for rainfall alone, it may be overtopped or held at a high headwater, and snow and ice at the inlet can reduce its capacity further. Before the storm, clear the inlet and outlet of snow and ice, check the culvert’s rating for this flow, arrange a culvert watch, and set a slow order trigger through the live rating (Section 3.8.26). Calibrate the melt equation with past rain-on-snow events where gauge or SNOTEL data exist.
For railroad work: In snow country, include snowmelt and rain on snow in the hydrology for culverts, bridges and slopes, not only rainfall. Track SWE from nearby SNOTEL sites and forecast warm rain events through the live rating. Expect high runoff where the ground is frozen, and clear culvert inlets of snow and ice before thaws. Spring break-up hazards are covered in Chapter 3.8.
Sources: USACE (1998), Runoff from Snowmelt, EM 1110-2-1406, Chs. 2–6 (temperature index Eq. 6-1; rain-on-snow Eqs. 5-19 and 5-20; Table 5-1 forest classes). Official page ↗ NRCS SNOTEL network. Official page ↗ Summarized and paraphrased.