↑ Parent Menu⌂ Main Menu
← Railway Ground Hazard Risk Management
GHRM
Railway Ground Hazard Risk Management · 3.0 · Risk Management
Sections · open a dropdown to go to a section or subsection

Chapter 3.5 — Site Conditions

Describing the physical setting of a site (ground, water, structures and track) so that everyone working on it starts from the same picture.
Author: Daniel P. Colwell

This chapter covers how site conditions are compiled from the desktop study, the reconnaissance and the borings, and how they are written up. A good site conditions section is short, factual and in a fixed order, and it separates what was observed from what is expected and from what is concluded.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
3.5.0 Purpose and Overview

The site conditions section is the bridge between the data and the recommendations. It tells a reader who has never been to the site what is there: the land and its history, the ground and the water, the structures and utilities, and the track and its traffic. It appears in the proposal (as expected conditions), in the reconnaissance report (as observed conditions) and in the final report (as conditions confirmed by the borings).

Table 3.5-1. Where site conditions come from at each stage
StageMain sourcesHow it is written
ProposalDesktop study: maps, legacy borings, soil survey, history (Chapter 3.2)Anticipated conditions, by area or reach, with the design concern for each
ReconnaissanceWalk-over, photographs, lidar (Chapter 3.4)Observed surface conditions and access
ReportBorings, laboratory tests, groundwater readingsSubsurface profile confirmed; differences from expected conditions noted
3.5.1 Topography and Landform

Describe the shape of the ground: elevations, relief, slopes, benches and drainage paths. Lidar (USGS 3DEP 1-m, about 3-ft, DEM) gives elevations at every boring and along every access route for planning; surveyed elevations at the time of drilling replace them in the report.

Example. Ground at the borings of a filled marsh site ranged from El. 581.8 ft to El. 598.5 ft, a relief of about 17 ft. The highest ground was a track-side drive; the wooded center was a hummocky fill surface at about El. 586 to 594 ft; ground fell to about El. 582 to 586 ft along an abandoned spur, where a ditch held standing water. Those few feet decided which borings needed mats and dry weather.

State the source and date of the elevations. Lidar collected years before the work will not show recent fill, stockpiles or ruts, and phone GPS altitudes can differ from lidar by several feet.

3.5.2 Geology and Stratigraphy

Give the regional geology in two or three sentences (bedrock formation and depth, surficial deposits) and then the expected or confirmed profile as a table. Where conditions change along a linear project, describe them by reach, each with its nearest data and its main design concern.

Track section placed on the prepared subgradeTopsoil, gravel or asphaltoften mixed with cindersSlag, cinder and urban fillvery dense to cemented; auger refusal possibleOrganic clay and peat (local)w over 100%; settlementLacustrine sand and siltvery loose to medium dense; saturated; N 2 to 8Glacial tillstiff to very stiff lean to fat clay; Qu 1.0 to 3.7 tsf05101520253035Depth (ft)
Figure 3.5-1. Idealized profile of a filled lake-plain site compiled from 43 legacy borings. Groundwater is typically 1 to 6 ft below grade. Depths are typical; the fill and organic layers vary over short distances.
Table 3.5-2. Example conditions by reach along a siding
ReachNearest dataExpected under the new slopeMain design concern
AHand auger: stiff sandy lean clay with gravel, N 8 to 25, dryLean clay embankment fill over alluvial clay; rock depth unknownNo data under the toe of the steepened slope
BBoring: thin cinder fill; very soft organic clay at 2.5 to 3 ft (N 3); stiff clay; limestone fragments at 8 ftSoft organic clay in the upper 2 to 4 ft; breccia from about 8 to 20 ft, highly variableUndercut depth; variable rock; possible voids
CHand auger: soft gray fat clay from 2 to 6+ ft (N 1 to 2); water at 4 ft; next to a wetlandSoft fat clay at least 6 ft thick, bottom not found; pondingCritical reach: stability on soft clay, settlement, undercut versus buttress
DShallow stiff lean clay; culvert under the trackThin clay over rock; ditch cuts may hit rockDitch grade in rock
Fractured rock exposed in a cut. Exposures like this one are the cheapest geology data on a site and belong in the site conditions section with their location.
Figure 3.5-2. Fractured rock exposed in a cut. Exposures like this one are the cheapest geology data on a site and belong in the site conditions section with their location.
3.5.3 Groundwater and Surface Water

Report groundwater as measured (at drilling, completion and 24 hours, with dates), and say what it means: depth below grade, relation to nearby lakes, rivers and ditches, perched water over clay or rock, and seasonal change. Describe surface water features (streams, ditches, swales, ponds) with their flow, condition and any odor or staining.

Table 3.5-3. Writing groundwater conditions
WriteAvoid
"Groundwater was measured at 4 ft below grade at completion of HA-14 on [date].""Groundwater is at 4 ft." (a single reading is not a design level)
"Ground surface is 5 to 13 ft above the lake; groundwater is expected within a few feet of the surface."Leaving out the reason groundwater is high
"Water levels in nearby wells are 145 to 200 ft deep and variable, typical of karst aquifers; perched water may occur over rock."Treating deep regional water as the design level for a fill on clay
3.5.4 Climate, Vegetation and Frost

Note what affects the work and the design: design frost depth, freeze-thaw cycling (rockfall, subgrade pumping), seasonal wetness, and vegetation. Vegetation matters twice: it controls access and clearing (Chapter 3.6), and it is evidence. Phragmites, cattails and reed canary grass mark wet ground; leaning trees mark creep; invasive thickets (buckthorn, bush honeysuckle) usually mean old disturbed fill.

A masonry arch culvert almost hidden by summer growth. Seasonal vegetation can hide drainage structures and slope features; reconnaissance in late fall or winter sees more.
Figure 3.5-3. A masonry arch culvert almost hidden by summer growth. Seasonal vegetation can hide drainage structures and slope features; reconnaissance in late fall or winter sees more.
3.5.5 Existing Structures and Utilities

List the structures and utilities that the work must avoid or that the design must account for: bridges and culverts (type, size, material, condition), retaining walls, signal masts and cabinets, buried cables and conduits, sewers and storm drains, overhead power. Take them from the railroad valuation maps and confirm them in the field.

Table 3.5-4. Structures and utilities to record
ItemRecord
CulvertsLocation (station), size, material, length, inlet and outlet condition, flow
Bridges and wallsLocation, type, foundation if known, condition
Signals and communicationsMasts, cabinets, foundations, conduits at grade; keep borings clear
Sewers and storm drainsSize and location from valuation maps and city atlases; relation to ditches and odors
Overhead linesClearance for the drill mast
A concrete headwall and drainage structure beside the track, with a fence line behind. Structures like this one set both a boring offset and the limits of the rig route.
Figure 3.5-4. A concrete headwall and drainage structure beside the track, with a fence line behind. Structures like this one set both a boring offset and the limits of the rig route.
3.5.6 Track and Traffic

Describe what the track carries, because it sets the consequence of failure (severity in Chapter 3.8) and the loads for design: main or siding, number of tracks, track class and speed, tonnage, passenger and hazardous materials traffic, and the importance of the route (redundancy, detours). Note the geometry-defect and slow-order history at the site and the condition of ballast, shoulder and ditches.

3.5.7 Environmental and Property Constraints
Table 3.5-5. Environmental and property constraints
ConstraintTypical sourcesEffect
WetlandsNational Wetlands Inventory; delineation if neededBoring offsets; clearing method; possible permit
Flood zoneFEMA flood mapsFloodplain permit for fill; seasonal access
Protected species and nesting birdsIPaC report; migratory bird windowsClearing outside the local migratory bird nesting season (the dates vary by region; the U.S. Fish and Wildlife Service field office gives them), or a nest check
Contaminated or regulated sitesState and federal databases; radius reportScreening, drummed cuttings, extra tests (pH, sulfate, chloride, resistivity)
Property lines and right-of-wayCounty parcels; railroad valuation mapsRight-of-entry; public-way permits for borings outside the railroad parcel
3.5.8 Site Conditions Summary

Close with a short summary that a reader could use on its own, in the order of this chapter, and a line on each condition that controls design. Keep observed, expected and concluded statements separate.

Template. The site is [location and use]. Ground is at El. [range] ft, [landform]. The geology is [regional summary]; the borings encountered [profile]. Groundwater was measured at [depths, dates]. Surface water: [features]. Structures and utilities: [list]. The track is [main/siding, traffic]. Constraints: [wetlands, flood zone, species, contamination, property]. The conditions that control design are [two or three items].
3.5.9 Cross-References
Table 3.5-6. Related chapters
TopicRefer to
Desktop studyChapter 3.2
ReconnaissanceChapter 3.4
Access studyChapter 3.6
Soil and rock classificationChapter 2.2
Problem soilsChapters 2.4 to 2.7
GroundwaterChapter 2.8
Severity and consequenceSection 3.8.20
Report preparationChapter 8.4
3.5.10 Drainage Area, Peak Flow and Culvert Headwater

Water is the most common trigger of track failure, and the culverts through an embankment set how much water it holds back. The site-conditions review should therefore establish the drainage area of each crossing, a design flow, and whether the existing opening is adequate. AREMA Chapter 1, Parts 3 and 4, give the rational method for small basins and the culvert design criteria; railroad culvert guidelines add a 100-year design storm, E80 loading, and a 36 in. minimum pipe.

3.5.10.1 Method and criteria

Equation 3.5-1. Peak flow and time of concentration

Q = C i A   Kirpich: tc = 0.0078 L0.77/S0.385   Kerby: tc = 0.83 (N L/S0.5)0.467

Q in cfs, i in in./hr for a duration equal to tc, A in acres; tc in minutes, L in ft, S in ft/ft. Use the rational method with caution above about 300 acres (Kirpich is intended for agricultural basins under 200 acres).

Table 3.5-7. Rural runoff coefficients (AREMA Table 1-3-1)
Vegetation and slopeOpen sandy loamClay and silt loamTight clay
Woodland: flat / rolling / hilly0.10 / 0.25 / 0.300.30 / 0.35 / 0.500.40 / 0.50 / 0.60
Pasture: flat / rolling / hilly0.10 / 0.16 / 0.220.30 / 0.36 / 0.420.40 / 0.55 / 0.60
Cultivated: flat / rolling / hilly0.30 / 0.40 / 0.520.50 / 0.60 / 0.720.60 / 0.70 / 0.82

Flat 0 to 5%, rolling 5 to 10%, hilly 10 to 30% slope. Urban values are in AREMA Table 1-3-2; a railroad yard is 0.20 to 0.35.

Table 3.5-8. AREMA culvert design criteria
FloodCriterion
25-yearDischarged without static head at the entrance (HW/D ≤ 1.0)
100-yearHeadwater no higher than the available head, 2 ft below base of rail, or 1.5 times the diameter, whichever is least

The calculator computes inlet-control headwater with the FHWA HDS-5 equations that underlie the charts AREMA cites. Outlet control (barrel friction and tailwater) should also be checked for long or flat culverts.

3.5.10.2 Worked example: 60-acre pasture basin

Table 3.5-9. C = 0.36, L = 3,000 ft, S = 0.015; i25 = 4.0 and i100 = 5.2 in./hr (calculator output)
ResultValue
Time of concentration (Kirpich)18.7 min
Q25 / Q10086 cfs / 112 cfs
60 in. corrugated metal pipe with headwall: HW/D at Q250.76
Headwater at Q100 (limit 7.5 ft)4.5 ft
Adequate (inlet control)yes

Rainfall intensities are illustrative; read them from the local intensity-duration-frequency curve at tc.

Open the culvert hydrology calculator →
Rational-method peak flows with Kirpich or Kerby time of concentration, and inlet-control headwater checked against the AREMA criteria.

3.5.10.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

Supplemental reference · Goswami (2015), Ch. 304

Runoff from Larger Basins: the NRCS Curve Number and Unit Hydrograph

The rational method in this section suits small basins. For larger or mixed-use basins, and wherever the runoff volume or the shape of the flood matters, the NRCS (formerly SCS) methods are used.

S = 1000 / CN − 10    Ia = 0.2 S    Q = (P − Ia)2 / (P − Ia + S) for P > Ia

  • CN = curve number (about 30 to 98) from land use, cover condition and hydrologic soil group A to D; S = potential maximum retention (in.); Ia = initial abstraction (in.); P = storm rainfall (in.); Q = runoff depth (in.).
  • TR-55 peak discharge: qp = qu Am Q Fp, with qu = unit peak discharge (csm/in.) from the time of concentration, Ia/P and the rainfall distribution type; Am = drainage area (mi²); Fp = adjustment for ponds and swamps.
  • NRCS synthetic unit hydrograph: qp = 484 A Q / Tp (cfs), with A in mi², Q = 1 in., and time to peak Tp = D/2 + 0.6 tc (hr) for a rainfall excess of duration D. Unit hydrographs can be lagged and summed to build the flood hydrograph for a design storm.
  • Time of concentration can be built up from sheet flow, shallow concentrated flow and channel flow segments, rather than one empirical formula.

For railroad work: Use the curve number method where a culvert or bridge drains more than a few hundred acres, where the basin is urbanizing (raise CN for future development, since railroad culverts outlast the land use around them), or where water ponds against the embankment and the volume matters for seepage and stability during the flood (Chapter 2.8, Chapter 6.3). A change in CN upstream is one of the triggers worth recording in the desktop study and the live rating (Chapter 3.8).

Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 304, Hydrology.

Larger basins, ponding and snowmelt: flood hydrographs, routing behind embankments and flood frequency are in Section 3.5.12; snowmelt and rain on snow in Section 3.5.13.

3.5.11 Riprap for Embankments, Channels and Culvert Outlets

Washouts are among the most frequent and costly ground hazards on a railroad: flood flow along an embankment toe, overtopping at a low point, and scour at a culvert outlet or bridge abutment can remove the support from under the track in hours. Riprap is the usual protection. The site conditions review (Sections 3.5.3 and 3.5.10) gives the design flow and velocity; this section turns them into a stone size, a stone weight and a layer thickness, so a field team can tell whether existing riprap is adequate and an estimate can carry the right stone class.

3.5.11.1 Method

Equation 3.5-2. Bank and channel riprap (FHWA HEC-11)

D50 = 0.001 CsgCsfVa³ / (davg0.5K11.5);   K1 = √(1 − sin²θ/sin²φ);   Csg = 2.12/(Ss − 1)1.5;   Csf = (SF/1.2)1.5

D50 and davg in ft, Va = average velocity in ft/s; θ = bank angle; φ = angle of repose of the stone (about 40° to 42° for angular rock); SF = stability factor (Table 3.5-10).

Equation 3.5-3. High-turbulence locations (Isbash)

D50 = V² / [2gC²(Ss − 1)],   C = 0.86 (high turbulence) or 1.20 (low turbulence)

For abutments, overtopping flow at the crest and shoulder, spur dikes and other locations where the local velocity is known but the flow is not uniform.

Equation 3.5-4. Culvert outlet apron (FHWA HEC-14 Eq. 10.4)

D50 = 0.2D [Q/(√g D2.5)]4/3 (D/TW)

D = culvert diameter (ft); Q in cfs; TW = tailwater depth, not less than 0.4D. Above a discharge intensity of about 6 use a riprap basin or energy dissipator.

Table 3.5-10. HEC-11 stability factor SF
ConditionSF
Uniform flow, straight or mildly curving reach (radius/width above about 30), little debris or wave impact1.0–1.2
Gradually varying flow, moderate bends (radius/width 10 to 30), some debris or waves1.3–1.6
Rapidly varying flow, sharp bends, flow impinging on the bank, heavy debris or ice1.6–2.0

A typical gradation has D100 about 2D50 and D15 about 0.5D50. The layer should be at least the larger of D100, 1.5D50 and 12 in., increased by half where it is placed under water, and it needs a granular or geotextile filter beneath it and a toe keyed below the expected scour depth. The stone weight is W50 = (π/6)γsD50³.

3.5.11.2 Worked example

Example 3.5-1: Riprap at an Embankment Toe on the Outside of a Bend

A fill on a Class I railroad located in Missouri runs along a river at the outside of a bend. The design flood gives an average velocity of 10 ft/s at a depth of 6 ft against the 2H:1V embankment slope. The existing protection is a scatter of 6-in. stone.

Va = 10 ft/sd = 6 ft2H:1Voutside of a bend: SF = 1.5D50 = ?GivenVa = 10 ft/s, d = 6 ftSlope 2H:1V; repose 41°SF = 1.5 (bend); Ss = 2.65Existing stone 6 in.RequiredD50 and W50Gradation and thicknessIs 6-in. stone adequate?
Embankment toe on the outside of a river bend during the design flood.

Given

VariableValueDescription
Va10 ft/sAverage velocity, design flood
davg6 ftAverage depth
Slope2H:1V (θ = 26.6°)Embankment
φ41°Angle of repose, angular stone
SF1.5Outside of a moderate bend (Table 3.5-10)
Ss2.65Quarried limestone

Required

  • Median stone size and weight
  • Gradation and layer thickness
  • Whether the existing 6-in. stone is adequate

Equations

  1. Eq. 3.5-2: K1 = √(1 − sin²θ/sin²φ)
  2. Eq. 3.5-2: Csg = 2.12/(Ss − 1)1.5; Csf = (SF/1.2)1.5
  3. Eq. 3.5-2: D50 = 0.001CsgCsfVa³/(davg0.5K11.5)
  4. W50 = (π/6)γsD50³; t = max(D100, 1.5D50, 12 in.)

Steps

Step 1 · Slope factor
sin 26.6° = 0.447; sin 41° = 0.656; 1 − (0.447/0.656)²
K1 = 0.732
↓
Step 2 · Corrections
2.12/1.651.5; (1.5/1.2)1.5
Csg = 1.00; Csf = 1.40
↓
Step 3 · Stone size (Eq. 3.5-2)
0.001 × 1.00 × 1.40 × 1,000 / (2.449 × 0.626)
D50 = 0.91 ft = 10.9 in.
Spot check: With SF = 1.2 (a straight reach) D50 would be 0.65 ft (7.8 in.); the bend raises it by the Csf factor of 1.40.
↓
Step 4 · Weight
0.524 × 165.4 × 0.912³
W50 = 66 lb
↓
Step 5 · Gradation and thickness
D100 = 2 × 10.9; D15 = 0.5 × 10.9; t = max(21.9, 16.4, 12)
D100 ≈ 22 in.; D15 ≈ 5 in.; t = 22 in.
↓
Solution
D50 about 11 in. (66 lb), a 22-in. layer on a filter; the existing 6-in. stone is undersized.

Solution

The toe needs riprap with a median size of about 11 in. (66 lb), graded to about 22 in., in a 22-in. layer on a filter, keyed below the scour depth.

The existing 6-in. stone is about half the required size and would move in the design flood; at 6 in. the slope is protected only to about 8 ft/s (the calculator’s chart). Rate the site in the risk assessment accordingly (Chapter 3.8), and specify the nearest standard stone class at or above D50 = 11 in. in the estimate.

Open the riprap calculator →
HEC-11 bank and channel riprap, the Isbash relation for turbulent locations, and HEC-14 culvert outlet aprons, with stone weight, gradation, layer thickness and a stone-size chart.

3.5.11.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • FHWA HEC-11, Design of Riprap Revetment (1989): riprap size equation with specific-gravity and stability-factor corrections; gradation and thickness.Find source ↗
  • FHWA HEC-14, Hydraulic Design of Energy Dissipators for Culverts and Channels (2006): Eq. 10.4, riprap aprons.Find source ↗
  • FHWA HEC-23, Bridge Scour and Stream Instability Countermeasures (2009): riprap at abutments; the Isbash relation.Find source ↗
  • AREMA Manual for Railway Engineering, Chapter 1: roadway drainage and culverts.Find source ↗
3.5.12 Flood Hydrographs, Routing and Flood Frequency

Section 3.5.10 gives the peak flow for a small basin. Larger basins, embankments that pond water behind them, and any crossing where the volume or timing of a flood matters need a flood hydrograph: losses, transformation of rainfall excess to runoff, routing through channels and storage, and a frequency for the result. The USACE manual Flood-Runoff Analysis (EM 1110-2-1417) sets out these methods and how to choose among them.

Table 3.5-11. Components of a flood-runoff model (after EM 1110-2-1417)
ComponentCommon methodsNotes for railroad basins
PrecipitationDesign storm from NOAA Atlas 14; historical storm; probable maximum precipitation (PMP) for dam-related studiesUse the storm duration that gives the highest peak for the basin, usually at least the time of concentration.
LossesInitial and constant loss rate; NRCS curve number; Green-Ampt; continuous soil-moisture accountingFrozen ground, saturated antecedent conditions and burned areas cut losses sharply.
Runoff transformationUnit hydrographs: Snyder, Clark, NRCS dimensionless; kinematic waveCalibrate parameters to gauged floods in the region where possible.
Channel routingMuskingum, Muskingum-Cunge, modified PulsFloodplain storage lowers and delays the peak downstream.
Storage routingLevel-pool (modified Puls) through the storage behind an embankment or reservoirAn embankment with a culvert is a small dam: ponding lowers the outflow peak but raises the headwater.
FrequencyGauged flood frequency (Log-Pearson Type III per USGS Bulletin 17C); regional regression (USGS StreamStats); frequency of the design stormCompare model results with regional regression estimates.

Snyder synthetic unit hydrograph HY-02

Eq. 3.5-5: tl = Ct (L Lca)0.3 (hr), the lag from the center of the rainfall excess to the peak, with L = main watercourse length to the divide (mi) and Lca = length to the point opposite the basin centroid (mi).

Eq. 3.5-6: tr = tl / 5.5 (standard duration); for another duration tR, tlR = tl + 0.25 (tR − tr).

Eq. 3.5-7: Qp = 640 Cp A / tlR (cfs per inch of excess), with A in mi².

Snyder’s original Ct and Cp came from the Appalachian region; values elsewhere differ substantially, so calibrate them with regional data or use a regional regression for lag (EM 1110-2-1417, Ch. 7).

Embankments as dams

Where a culvert is small compared with the flood, water ponds behind the embankment. Level-pool routing uses the storage-elevation curve upstream and the culvert rating curve to find the outflow hydrograph and the maximum headwater. The outflow peak is lower than the inflow peak, which helps downstream, but the embankment then holds water like a dam: it saturates, seeps, and can pipe or fail by rapid drawdown when the pond falls (Chapter 6.3, Section 6.3.8). If the culvert blocks with debris or ice, the pond can overtop the track. Dams near the line are covered in Chapter 2.8, Section 2.8.15.

Flood frequency

At a gauged site, fit annual peak flows with the Log-Pearson Type III distribution following USGS Bulletin 17C (published in 2018, current version 1.1 of 2019, the successor to Bulletin 17B). At ungauged sites, use the USGS regional regression equations through StreamStats, and transfer gauged results to the site by drainage-area ratio where a nearby gauge is on the same stream. A rainfall-runoff model run with a 100-year storm does not automatically give the 100-year flood; check it against the frequency estimates.

Example 3.5-2: Snyder Unit Hydrograph Check on a Culvert Basin

Problem Statement

A Class I railroad located in Kentucky is replacing a 72-in. culvert under a 30-ft embankment. The rational method of Section 3.5.10 is not suitable for the 4.2-mi² basin, so the engineer builds a Snyder unit hydrograph as a check on the hydrology consultant’s model. Regional studies give Ct = 2.0 and Cp = 0.60, and the 100-year storm gives 2.9 in. of rainfall excess by the curve number method.

centroid Embankmentand culvert L = 6.0 mi (to divide)Lca = 2.8 miA = 4.2 mi² GivenA = 4.2 mi²L = 6.0 mi, Lca = 2.8 miCt = 2.0, Cp = 0.60tR = 1.0 hr100-yr excess 2.9 in. Required(a) Lag tl and tr(b) 1-hr UH peak(c) Peak check value
Figure 3.5-5. Example 3.5-2: basin draining to a railroad embankment culvert (not to scale).

Given

VariableValueDescription
A4.2 mi²Drainage area
L6.0 miMain watercourse length to the divide
Lca2.8 miLength to the point opposite the centroid
Ct, Cp2.0, 0.60Regional Snyder coefficients
tR1.0 hrDesired unit hydrograph duration
Q2.9 in.100-year rainfall excess (curve number method)

Required

  • (a) Lag tl and standard duration tr
  • (b) Peak of the 1-hour unit hydrograph
  • (c) An upper-bound check on the 100-year peak

Equations

  1. Eq. 3.5-5: tl = Ct(L Lca)0.3
  2. Eq. 3.5-6: tr = tl/5.5; tlR = tl + 0.25(tR − tr)
  3. Eq. 3.5-7: Qp = 640 Cp A / tlR

Steps

Step 1 · (a) Lag
L Lca = 6.0 × 2.8 = 16.8; 16.80.3 = e0.3 × 2.821 = 2.331; 2.0 × 2.331
tl = 4.66 hr
↓
Step 2 · (a) Standard duration
4.66 / 5.5
tr = 0.85 hr
↓
Step 3 · (b) Adjust to 1 hr
4.66 + 0.25 (1.0 − 0.85)
tlR = 4.70 hr
↓
Step 4 · (b) Unit peak
640 × 0.60 × 4.2 / 4.70 = 1,613 / 4.70
Qp ≈ 343 cfs per inch
Spot check: 343 × 4.70 / 4.2 = 384 = 640 × 0.60 ✓.
↓
Step 5 · (c) Upper bound
343 × 2.9 (all excess in one hour)
≈ 995 cfs
↓
Solution
tl = 4.66 hr; the 1-hour unit hydrograph peaks at about 343 cfs per inch; the 100-year peak cannot exceed about 1,000 cfs, and will be lower because the excess falls over several hours.

Solution

tl = 4.66 hr; the 1-hour unit hydrograph peaks at about 343 cfs per inch; the 100-year peak cannot exceed about 1,000 cfs, and will be lower because the excess falls over several hours.

If all 2.9 in. of excess fell in one hour, the peak would be about 1,000 cfs. Real storms spread the excess over several hours, so the convolved peak will be lower; a value from the consultant’s model much above 1,000 cfs points to an error, and one far below (say under half) needs explaining. Compare the result with the USGS regional regression estimate for the site. Then route the hydrograph through the storage behind the 30-ft embankment: the pond may lower the outflow peak enough to allow a smaller pipe, but the design must then account for the headwater on the embankment and the risk of blockage.

Example 3.5-4: Ponding Behind an Embankment: Storage Routing Through a Culvert

Problem Statement

A Class I railroad located in Iowa has a 60-in. culvert under a 14-ft embankment in a broad valley. Base of rail is 12 ft above the culvert invert, so the railroad’s criterion of headwater at least 2 ft below base of rail limits headwater to 10 ft. The design flood hydrograph is triangular. Water ponds behind the fill, so the engineer must route the flood through the storage to find the peak outflow and the maximum headwater, and check what happens if debris blocks half of the culvert.

02004000246Time (hr)Flow (cfs)Inflow I (peak 400 cfs)Outflow O = ?GivenTriangular inflow: peak400 cfs at 2 hr, ends 5 hrStorage S = 30,000 H² ft³Culvert O = 25 H¹·⁵ cfsΔt = 0.5 hr; H limit 10 ftRequired(a) Peak outflow and time(b) Maximum headwater H(c) Culvert half blocked
Figure 3.5-7. Example 3.5-4: inflow hydrograph and routed outflow through the storage behind a railroad embankment.

Given

VariableValueDescription
I(t)0 to 400 cfs at 2.0 hr, back to 0 at 5.0 hrTriangular inflow hydrograph
S(H)30,000 H² ft³Storage upstream of the embankment, from the topography
O(H)25 H1.5 cfsCulvert rating (inlet control) fitted to HDS-5 headwater values
Δt0.5 hr (1,800 s)Routing time step
Hmax10 ftAllowable headwater

Required

  • (a) Peak outflow and its time
  • (b) Maximum headwater, compared with the 10-ft limit
  • (c) Peak outflow and headwater with the culvert half blocked (O = 12.5 H1.5)

Equations

  1. Eq. 3.5-11 (storage indication, modified Puls): 2S2/Δt + O2 = I1 + I2 + (2S1/Δt − O1)
  2. S = 30,000 H2; O = 25 H1.5

Steps

Step 1 · Storage-indication table
For a range of H, compute S, O and 2S/Δt + O (Table 3.5-13). At H = 5 ft: S = 750,000 ft³; O = 25 × 11.18 = 279.5 cfs; 2 × 750,000/1,800 + 279.5 = 1,112.8 cfs.
Table of 2S/Δt + O against H
↓
Step 2 · Route each step (Eq. 3.5-11)
Example, 2.0 to 2.5 hr: at 2.0 hr H = 4.64 ft, S = 645,900 ft³, O = 250.2 cfs, so 2S/Δt − O = 717.7 − 250.2 = 467.5. Then 400 + 333 + 467.5 = 1,200.5 cfs, which lies just above the H = 5.2-ft value of 1,197.8 in the table.
At 2.5 hr: H ≈ 5.21 ft, O ≈ 297 cfs
Spot check: 25 × 5.211.5 = 25 × 11.89 = 297 cfs ✓.
↓
Step 3 · (a) and (b) Complete the routing
Repeat for every step (Table 3.5-12)
Peak outflow ≈ 298 cfs at about 3.0 hr; maximum H ≈ 5.2 ft
Spot check: the outflow peak falls on the receding limb of the inflow, where the two hydrographs cross, as it must for level-pool storage.
↓
Step 4 · (c) Half-blocked culvert
Repeat with O = 12.5 H1.5
Peak outflow ≈ 227 cfs at about 3.5 hr; maximum H ≈ 6.9 ft
↓
Solution
Storage cuts the 400-cfs inflow peak to about 300 cfs and delays it an hour; headwater reaches 5.2 ft (6.9 ft half blocked), within the 10-ft limit.
Table 3.5-12. Example 3.5-4 routing results (storage-indication method, Δt = 0.5 hr)
t (hr)Inflow I (cfs)Outflow O (cfs)Headwater H (ft)
0.5100391.35
1.02001032.56
1.53001743.64
2.04002504.64
2.53332975.21
3.02672985.22
3.52002734.92
4.01332294.37
4.5671723.62
5.001052.61
5.50461.50
6.00140.68
Table 3.5-13. Storage-indication table: 2S/Δt + O against H
H (ft)S (ft³)O (cfs)2S/Δt + O (cfs)
130,00025.058.3
2120,00070.7204.0
3270,000129.9429.9
4480,000200.0733.3
5750,000279.51,112.8
61,080,000367.41,567.4

Solution

(a) About 298 cfs at about 3.0 hr, 25% below the inflow peak. (b) About 5.2 ft, within the 10-ft limit. (c) Half blocked: about 227 cfs and 6.9 ft, still within the limit but with about 1.4 million ft³ held against the fill.

The pond helps the culvert: the outflow peak is a quarter lower and an hour later than the inflow peak. The cost is that the embankment holds 5 to 7 ft of water for several hours. Check the fill for seepage and piping along the culvert barrel at that head, and for rapid drawdown as the pond falls (Chapter 6.3, Section 6.3.8). The half-blocked case shows how much headroom is left for debris or ice; full blockage would raise the pond toward the track, so keep the inlet clear and add a trash rack or debris deflector if the basin delivers woody debris. Real storage curves and culvert ratings come from survey and HDS-5 or HY-8; the fitted power-law forms here keep the hand calculation short.

Muskingum channel routing HY-05

Where the flood is measured or modeled upstream and the crossing is some distance down the valley, the hydrograph changes along the reach: storage in the channel and floodplain lowers the peak and delays it. The Muskingum method treats reach storage as S = K[XI + (1 − X)O], where K is the travel time of the flood wave through the reach and X (0 to 0.5) weights inflow against outflow. X near 0 means strong floodplain storage and attenuation; X near 0.5 means the wave passes almost unchanged. Solving the storage equation over a time step gives the routing equation:

Eq. 3.5-12: O2 = C0I2 + C1I1 + C2O1, with C0 = (Δt − 2KX)/D, C1 = (Δt + 2KX)/D, C2 = [2K(1 − X) − Δt]/D and D = 2K(1 − X) + Δt. The coefficients sum to 1.

Eq. 3.5-13: 2KX ≤ Δt ≤ 2K(1 − X), the time-step range that keeps all three coefficients positive. K and X are best calibrated from upstream and downstream gauged hydrographs; without them, K can be estimated as reach length divided by flood-wave celerity (about 1.5 times the mean velocity for a wide channel), and Muskingum-Cunge computes K and X from the channel geometry, slope and roughness (EM 1110-2-1417, Ch. 9).

Example 3.5-5: Muskingum Routing from an Upstream Gauge to a Railroad Bridge

Problem Statement

A Class I railroad located in Ohio crosses a creek on a ballast-deck bridge 3.0 mi downstream of a USGS stream gauge. During a storm the gauge records the hydrograph in Table 3.5-14, peaking at 1,000 cfs 4 hr after the start of the rise. The bridge waterway passes 900 cfs with 2 ft of freeboard to low chord. The railroad’s storm watch needs to know the peak flow and its arrival time at the bridge, and whether a slow order or closure is warranted.

Bridge waterway 900 cfs05001,0000481216Time (hr)Flow (cfs)Gauge inflow I (peak 1,000 cfs)Bridge outflow O = ?GivenReach 3.0 mi, gauge to bridgeWave celerity c = 2.2 ft/sWeighting factor X = 0.2Δt = 1 hr; base flow 100 cfsBridge passes 900 cfs with2 ft freeboardRequired(a) K, C0, C1, C2 and theΔt check(b) Peak at the bridge and time(c) Warning time and waterway
Figure 3.5-8. Example 3.5-5: flood hydrograph at an upstream gauge and the routed hydrograph at a railroad bridge 3 miles downstream.

Given

VariableValueDescription
L3.0 mi (15,840 ft)Reach length, gauge to bridge
c2.2 ft/sFlood-wave celerity (from the gauge rating and channel survey)
X0.2Weighting factor, moderate floodplain storage
Δt1 hrRouting time step (gauge reports hourly)
I(t)100 cfs base; peak 1,000 cfs at 4 hrGauge hydrograph (Table 3.5-14)
Qcap900 cfsBridge waterway capacity with 2 ft freeboard

Required

  • (a) K, the routing coefficients C0, C1, C2, and the Δt check
  • (b) Peak flow at the bridge and its time
  • (c) Warning time after the gauge peak, and whether the bridge waterway is exceeded

Equations

  1. K = L / c
  2. Eq. 3.5-12: O2 = C0I2 + C1I1 + C2O1
  3. Eq. 3.5-13: 2KX ≤ Δt ≤ 2K(1 − X)

Steps

Step 1 · (a) Travel time K
15,840 ft / 2.2 ft/s = 7,200 s
K = 2.0 hr
↓
Step 2 · (a) Time-step check (Eq. 3.5-13)
2KX = 2 × 2.0 × 0.2 = 0.8 hr; 2K(1 − X) = 2 × 2.0 × 0.8 = 3.2 hr
0.8 ≤ 1.0 ≤ 3.2 hr ✓
↓
Step 3 · (a) Coefficients
D = 3.2 + 1.0 = 4.2; C0 = (1.0 − 0.8)/4.2; C1 = (1.0 + 0.8)/4.2; C2 = (3.2 − 1.0)/4.2
C0 = 0.048; C1 = 0.429; C2 = 0.524
Spot check: 0.048 + 0.429 + 0.524 = 1.000 ✓.
↓
Step 4 · (b) Route hour by hour (Table 3.5-14)
Start with O = 100 cfs (base flow). At 6 hr: 0.048 × 650 + 0.429 × 850 + 0.524 × 809.2 = 31.0 + 364.3 + 423.9
Peak O ≈ 819 cfs at 6 hr
Spot check: the routed peak falls on the receding limb of the inflow, and its delay (2 hr) equals K, as expected for moderate X.
↓
Step 5 · (c) Warning time and waterway
Gauge peak at 4 hr, bridge peak at 6 hr; 819 against 900 cfs
About 2 hr of warning; peak 81 cfs (9%) below the waterway capacity
↓
Solution
The reach lowers the 1,000-cfs gauge peak to about 820 cfs at the bridge, arriving about 2 hr later, below the 900-cfs waterway.
Table 3.5-14. Example 3.5-5 Muskingum routing (K = 2.0 hr, X = 0.2, Δt = 1 hr)
t (hr)Inflow I (cfs)C0I2C1I1C2O1Outflow O (cfs)
0100–––100
130014.342.952.4110
260028.6128.657.4215
390042.9257.1112.4412
41,00047.6385.7216.0649
585040.5428.6340.1809
665031.0364.3423.9819
748022.9278.6429.0730
835016.7205.7382.6605
926012.4150.0316.9479
102009.5111.4251.1372
111607.685.7194.9288
121306.268.6151.0226
131105.255.7118.2179
141004.847.193.9146

Solution

(a) K = 2.0 hr; C0 = 0.048, C1 = 0.429, C2 = 0.524; a 1-hr step lies within 0.8 to 3.2 hr. (b) About 819 cfs at 6 hr, 18% below the gauge peak. (c) About 2 hr of warning after the gauge peaks; the routed peak stays 81 cfs below the 900-cfs waterway capacity.

The gauge gives the storm watch a real lead time: a gauge peak near 1,000 cfs means the bridge sees about 820 cfs two hours later, so the bridge can stay in service with an inspector watching for drift and scour at the piers. Routing the reach shows how much margin is left: a gauge peak of about 1,100 cfs would bring the bridge to its waterway capacity, and that is a practical trigger for a slow order or closure in the storm-watch plan (Chapter 7.4). Drift lodged on the piers reduces the waterway, so the capacity used for the trigger should allow for it. Muskingum routing assumes the reach has no large tributary inflow between the gauge and the bridge; add local inflow from the intervening area if it is more than a few percent of the gauged area. Where the reach is long, ungauged or the floodplain changes along it, use Muskingum-Cunge or HEC-RAS unsteady flow.

For railroad work: Ask for the full hydrograph, not only the peak, for any culvert or bridge draining more than a few hundred acres, and for any crossing where the embankment ponds water. Review the loss and unit hydrograph parameters against regional values and the frequency result against regional regression. Treat a high embankment with a small culvert as a dam: check seepage, piping and rapid drawdown at the maximum pond level, and plan for blockage by debris or ice.

Sources: USACE (1994), Flood-Runoff Analysis, EM 1110-2-1417, Chs. 6–9, 11 and 13. Official page ↗ England, J. F. et al. (2019), Guidelines for Determining Flood Flow Frequency, Bulletin 17C, USGS Techniques and Methods 4-B5. Official page ↗ USGS StreamStats. Official page ↗ Summarized and paraphrased.

3.5.13 Snowmelt and Rain-on-Snow Runoff

On many northern and mountain lines the largest floods, washouts and spring slope failures come from snowmelt, often with rain falling on the snow. The USACE manual Runoff from Snowmelt (EM 1110-2-1406) describes how snowmelt is measured, computed and turned into runoff.

How a snowpack produces runoff

  • The water stored in the snowpack is its snow water equivalent (SWE), measured at snow courses, snow pillows (for example the SNOTEL network) and by remote sensing.
  • A cold snowpack must first be warmed to 32°F (its cold content) and its pores filled to their liquid-water holding capacity before melt leaves the base. Early melt and rain can be absorbed with little runoff; once the pack is “ripe,” nearly all further melt and rain run off.
  • Frozen ground beneath the snow can make almost all water input run off, even from soils that are normally permeable.
  • Temperature falls with elevation, so melt moves up the basin through the season. Basins are modeled in elevation bands with a temperature lapse rate.

Temperature-index (degree-day) method HY-03

Eq. 3.5-8: Ms = Cm (Ta − Tb), where Ms = melt (in./day), Ta = air temperature (°F), Tb = base temperature (usually 32°F) and Cm = melt-rate factor. Cm is typically 0.04 to 0.08 in./°F-day for rain-free conditions and higher during rain on snow with wind; calibrate it for the basin, because it changes through the season with snow albedo and sun angle.

Energy budget: generalized rain-on-snow equations HY-04

During rain on snow the sky is overcast and the air saturated, and condensation of warm moist air on the snow, driven by wind, supplies most of the melt; the rain itself adds relatively little heat. The generalized equations (EM 1110-2-1406, Eqs. 5-19 and 5-20) give daily melt M (in./day):

Eq. 3.5-9 (open to partly forested, 10 to 80% canopy): M = (0.029 + 0.0084 k v + 0.007 Pr)(Ta − 32) + 0.09

Eq. 3.5-10 (heavily forested, over 80% canopy): M = (0.074 + 0.007 Pr)(Ta − 32) + 0.05

where k = basin wind exposure coefficient (1.0 for open plains, as low as 0.3 in forest), v = wind speed (mph, at 50 ft), Pr = rainfall (in./day) and Ta = temperature of the saturated air (°F, at 10 ft). The total water input to the ground is melt plus rain.

Example 3.5-3: Rain on Snow Above a Railroad Culvert

Problem Statement

A Class I railroad located in Montana has a culvert draining a 1.5-mi² partly forested basin. A warm Pacific storm is forecast to bring 2.0 in. of rain in 24 hours at about 45°F with 15-mph wind, onto a ripe snowpack holding more than 6 in. of SWE over frozen ground. The engineer must estimate the water reaching the culvert, to judge whether a slow order and culvert watch are needed.

frozen groundsnowpack (SWE) Rain 2.0 in./day Track GivenA = 1.5 mi², partly forestedk = 0.6, v = 15 mphTa = 45°F, Pr = 2.0 in./dayFrozen ground: allwater input runs off Required(a) Melt M, in./day(b) Water input(c) Mean daily flow vs rain alone
Figure 3.5-6. Example 3.5-3: rain on snow over frozen ground above a railroad culvert (not to scale).

Given

VariableValueDescription
A1.5 mi²Drainage area, partly forested
k0.6Basin wind exposure coefficient
v15 mphWind speed
Ta45°FAir temperature, saturated
Pr2.0 in./dayRainfall
Runoff100% of water inputRipe snowpack over frozen ground (assumption)

Required

  • (a) Snowmelt M for the day
  • (b) Total water input
  • (c) Mean daily flow at the culvert, compared with rain alone

Equations

  1. Eq. 3.5-9: M = (0.029 + 0.0084kv + 0.007Pr)(Ta − 32) + 0.09
  2. W = M + Pr (water input, in./day)
  3. Q̄ = (W / 12) A / 86,400 (cfs, A in ft²; 1 mi² = 27,878,400 ft²)

Steps

Step 1 · (a) Melt
0.029 + 0.0084 × 0.6 × 15 + 0.007 × 2.0 = 0.029 + 0.0756 + 0.014 = 0.1186; 0.1186 × (45 − 32) + 0.09 = 1.542 + 0.09
M ≈ 1.63 in./day
Spot check: for heavy forest, Eq. 3.5-10 gives (0.074 + 0.014) × 13 + 0.05 = 1.19 in./day, lower because wind is sheltered.
↓
Step 2 · (b) Water input
1.63 + 2.0
W ≈ 3.63 in./day
↓
Step 3 · (c) Mean daily flow
A = 1.5 × 27,878,400 = 41.8 × 106 ft²; (3.63 / 12) × 41.8 × 106 / 86,400
Q̄ ≈ 146 cfs (rain alone: 81 cfs)
Spot check: 146 / 81 = 1.8 = 3.63 / 2.0 ✓.
↓
Solution
Melt adds about 1.6 in. to the 2.0 in. of rain, for about 3.6 in. of water in a day and a mean flow near 146 cfs, about 1.8 times the flow from rain alone.

Solution

Melt adds about 1.6 in. to the 2.0 in. of rain, for about 3.6 in. of water in a day and a mean flow near 146 cfs, about 1.8 times the flow from rain alone.

The peak flow will be well above the 146-cfs daily mean, because the rain and melt are not uniform through the day. If the culvert was sized for rainfall alone, it may be overtopped or held at a high headwater, and snow and ice at the inlet can reduce its capacity further. Before the storm, clear the inlet and outlet of snow and ice, check the culvert’s rating for this flow, arrange a culvert watch, and set a slow order trigger through the live rating (Section 3.8.26). Calibrate the melt equation with past rain-on-snow events where gauge or SNOTEL data exist.

For railroad work: In snow country, include snowmelt and rain on snow in the hydrology for culverts, bridges and slopes, not only rainfall. Track SWE from nearby SNOTEL sites and forecast warm rain events through the live rating. Expect high runoff where the ground is frozen, and clear culvert inlets of snow and ice before thaws. Spring break-up hazards are covered in Chapter 3.8.

Sources: USACE (1998), Runoff from Snowmelt, EM 1110-2-1406, Chs. 2–6 (temperature index Eq. 6-1; rain-on-snow Eqs. 5-19 and 5-20; Table 5-1 forest classes). Official page ↗ NRCS SNOTEL network. Official page ↗ Summarized and paraphrased.

← Previous · 3.0 Risk Management Chapter 3.4 — Site Review and Reconnaissance
Next · 3.0 Risk Management → Chapter 3.6 — Site Accessibility Study