Checklist · Part V · Subsurface Exploration
Use this checklist to verify planning completeness before submitting the Investigation Plan memorandum to the railroad client for approval.
Reference graphics
Levy (2010) recommends that owners prequalify contractors through a request for qualifications (RFQ) before bidding. His RFQ checklist asks for, among other things, years in business and any former company names, current backlog, three years of revenue, the largest recent projects, bonding capacity and insurance limits, projects not completed and why, any debarment, an attached quality control program, an attached safety program, and reportable accidents and OSHA violations for the past year. He recommends requesting the past five-year safety record and workers’ compensation experience modification rate (EMR), treating a rate below 1.0 as acceptable, and noting that a poor record takes about three years to work off. He also suggests calling past owners beyond the references listed, and asking them for other owners to contact.
For testing and inspection, Levy advises that certain inspections be contracted directly by the owner so the firm is impartial and works only for the owner. His list starts with inspecting soils before foundations are placed, inspecting compaction, and load testing piles. The testing RFQ should describe the project and schedule, list the services required, give an order-of-magnitude scope so firms can price it, and request hourly rates by staff level (regular and overtime) and unit prices for estimated test quantities.
At the preconstruction conference, the owner’s team should confirm the notice-to-proceed date, introduce the day-to-day staff, set communication channels and meeting protocol, verify insurance certificates for the contractor and each subcontractor, set procedures for questions and proposed change orders, and set the deadline for a baseline schedule and its update interval.
For railroad work: Add these points to the investigation planning checklist: confirm that the drilling subcontractor has railroad right-of-way experience, current contractor right-of-entry insurance, a safety program addressing roadway worker protection, and an acceptable EMR and OSHA history; confirm the testing laboratory’s accreditation and that acceptance testing during construction is contracted so that it reports to the railroad. Hold a short kickoff with the railroad’s representative to fix track access procedures, flagging requests, and the schedule for boring logs and lab data.
Source: Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier), pp. 21–24, 28–29, 113–116. Summarized and paraphrased. Full reference under Supplemental References.
Cretu et al. treat risk identification as a short, facilitated, multidiscipline session. One to two hours is usually enough on an ordinary project. It is best run with a risk breakdown structure (RBS) as a checklist so that no category is skipped. Their construction RBS has seven top-level branches: design, environmental, real estate, economic, schedule, contracting and construction. Each branch breaks down into items such as design coordination, resource agency reviews, utility issues, impacts to existing operations and force majeure. The facilitator records every idea where the whole group can see it and holds back editing until later. The facilitator draws out risks with Socratic questions. One of the authors’ own examples is “Did we run into geotechnical problems at this location when the original foundations were installed?” A SWOT framing (internal strengths and weaknesses, external opportunities and threats) is offered as an alternative prompt.
The results go into a risk register with these fields: ID, RBS category, threat or opportunity, short title, description, trigger, probability (initially high >75%, medium ≈50%, low <25%), impact description, owner, response strategy and status. Each description should be specific, measurable, attributable, relevant and time-bound (SMART). The register is then vetted. Duplicates are merged, and many small related items, such as several minor geotechnical uncertainties, may be grouped into one risk for management. Black-swan events are noted, but they are not modeled. The authors’ list of workshop questions includes several on ground conditions: what geotechnical work has been done, what is assumed for cut/fill reuse and haul, what is assumed for stability of cuts and temporary support, and whether perched water or dewatering permits are involved.
For railroad work: Hold this session during investigation planning, before the boring layout is fixed. Add railroad-specific branches to the RBS: track access and work windows, flagging and protection, slow-order or traffic interruption exposure, signal and communication cable conflicts, and right-of-way or permit-to-enter limits. Then trace every high or medium geotechnical risk to a specific exploration, test or monitoring item in the scope, or record it as a risk the client accepts. The register then becomes the written basis for the scope and fee, and it carries forward into the report and the construction documents.
Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 237–244, 249–250. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Use this checklist to verify planning completeness before submitting the Investigation Plan memorandum to the railroad client for approval.
Desktop Review:
Boring Layout:
Laboratory Testing:
Health and Safety / ROW Access:

Client Communication: