I.8 Emergency Response — Client-Specific Protocols (continued)

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project.
Authors: Daniel P. Colwell and Mario Ruel
I.8 Emergency Response — Client-Specific Protocols (continued)

Table 1.0-3: Emergency Response Contact Structure by Railroad Client (completed)

Landslides After Rain
Landslides After Rain

These requirements vary by owner railroad. Confirm them against the owner railroad's current standards when the work is scoped, and record the edition used.

We establish and document these contact chains at the beginning of every PSA engagement — not when the emergency occurs. The geotechnical firm's project manager and the on-call geotechnical engineer must have direct mobile phone numbers for every contact in the chain. We verify these contacts annually and update them when railroad personnel change roles.

I.8.1 Emergency Response Timeline — Standard for All Railroad Clients

The following timeline applies to all railroad emergency geotechnical response, regardless of client. Individual client protocols may require faster response on specific corridors or for specific event types.

Hour 0 — Notification Received:

  • Geotechnical firm's on-call engineer accepts the call and confirms they will mobilize
  • Contacts the firm's emergency response coordinator to arrange field technician and equipment
  • Confirms RWP certification currency for all personnel being mobilized
  • Contacts railroad flagging coordinator to arrange RWIC for site entry

Hour 0–4 — Mobilization and Site Arrival:

  • Licensed geotechnical engineer and field technician on site
  • All personnel hold current RWP certification for the host railroad
  • Job Safety Briefing completed before entering the ROW
  • Field assessment of failure mechanism, extent, and movement status begins immediately

Hour 1–4 — First Professional Recommendation:

  • Verbal recommendation delivered to railroad operating officer while on site or immediately upon departure
  • Recommendation covers: track restriction (closure, slow order with mph basis, or flag-and-proceed), specific technical basis, and re-inspection interval
  • Confirmation of recommendation in writing by email within 2 hours of leaving the site

Day 1–5 — Emergency Investigation:

  • Drill rig mobilized under emergency track window scheduling within 24–48 hours
  • Three to five targeted borings at 15–25 ft depth
  • Expedited laboratory testing: 48-hour turnaround on moisture content, Atterberg limits, unconfined compression, and USCS classification
  • Written emergency recommendations issued in letter report format within 48–72 hours of completing field work

Month 1–6 — Permanent Repair:

  • Formal signed-and-sealed geotechnical report and construction documents produced following standard design-phase process
  • Geotechnical Special Provisions included in permanent repair bid package
I.8.2 Emergency Repair Guidance by Failure Type

We use the following framework when formulating emergency repair recommendations. Recommendations must be tailored to the specific conditions observed; this table provides starting points, not substitutes for engineering judgment.

Failure TypeAREMA MRE ReferenceTypical Emergency Repair Approach
Shallow slope failure (H < 10 ft)MRE Ch. 1, Section 1.4.3 (Maintenance of Earth Slopes)Slope regrading to stable angle; rock buttress at toe; surface drainage improvement; erosion control blanket
Deep slope failure (H > 10 ft)MRE Ch. 1, Section 1.4.3; MRE Ch. 8, Part 5 (Retaining Walls)Staged material removal; soldier pile wall; concrete block or gabion buttress; soil nail wall with geogrid facing
Embankment settlement or sinkholeMRE Ch. 1, Section 1.4.1 (Maintenance of Roadbed)Compaction grouting; flowable fill void filling; temporary timber cribbing or bridging between ties
Bridge scour — abutment or pierMRE Ch. 1, Part 3 (Natural Waterways); FHWA HEC-23Emergency riprap placement; geotextile bag placement; temporary sheet pile or H-pile; flow diversion
Subgrade failure or mud boilMRE Ch. 1, Section 1.4.1 (Maintenance of Roadbed)Undercutting and replacement with granular fill; ballast injection; geotextile/geogrid installation under ballast
Retaining wall distressMRE Ch. 8, Part 5 (Retaining Walls, Abutments and Piers)Temporary rock buttress at wall base; sheet pile wall parallel to track; soil anchor installation
Debris Flow Landslide
Debris Flow Landslide
Project management · Hutchings (2004)

Sustained Overtime, Productivity Loss and Acceleration During Extended Emergency Work

Hutchings summarizes research on scheduled overtime. In the first few weeks, total output per worker rises, though not in proportion to the added hours. After about 7 to 9 consecutive 50- or 60-hour weeks, weekly output falls to roughly what the same crew produces in a 40-hour week. After about eight more weeks, the losses cancel the early gains, so the whole overtime period produces no more work, and possibly less, than a normal schedule would have. Combined with premium pay, the productive value per wage dollar after several weeks drops below about 75% for five 10-hour days, below about 62% for six 10-hour days and below about 40% for seven 12-hour days. Productivity per hour recovers sharply when the crew returns to a 40-hour week. In his example claim on a public works job, lost labor productivity (about $2.4 million) was the largest single component of a total claim of about $7.4 million.

He distinguishes directed acceleration, where the owner orders the work sped up, from constructive acceleration. The latter requires an excusable delay, a request for an extension, refusal of the request, an order to finish on the original date anyway, and actual acceleration by the contractor. When a contractor is simply behind, he advises against an acceleration order. Instead, give written notice that the contract date will be enforced and ask for a revised schedule showing how the contractor will meet it. Means and methods, and responsibility for them, then stay with the contractor.

For railroad work: round-the-clock effort is appropriate in the first days of a slide or washout response, when restoring service drives every decision. Once the response becomes a permanent repair lasting weeks, plan for a sustainable pace: rotating crews, a defined second shift, or more equipment, rather than the same people working seven 12-hour days. Fatigue affects geotechnical observers as much as operators. Missed seepage, tension cracks or compaction problems late in a long shift carry a real cost. When the railroad sets a restoration date that cannot be met at normal production, record the instruction, any request for more time and the response, because those records determine later whether the extra cost was acceleration or part of the original scope.

Source: Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc., pp. 273–277. Summarized and paraphrased. Full reference under Supplemental References.