I.11 Quality Assurance — Peer Review Requirements by Deliverable and Client

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project.
Authors: Daniel P. Colwell and Mario Ruel
I.11 Quality Assurance — Peer Review Requirements by Deliverable and Client

Every signed-and-sealed geotechnical deliverable for any railroad client is subject to independent peer review before issuance. The standard for "independent" is clear: the reviewer had no involvement in the investigation, analysis, or previous drafts of the document being reviewed.

Table 1.0-4: Peer Review Requirements by Deliverable Type
DeliverableMinimum Reviewer QualificationReview Level RequiredPre-issuance Client Review
Desktop Review MemorandumSenior PE, same firm acceptableInternal QC checkNot required
Assessment ReportSenior PE, same firm acceptableInternal QC checkNot required
Reconnaissance ReportSenior PE, same firm acceptableInternal QC checkNot required
Preliminary Geotechnical ReportIndependent PE, 10 yr railroad GT experienceFull independent reviewRecommended
30% Geotechnical Design MemoIndependent PE, 10 yr railroad GT experienceFull independent review; signed seal requiredRequired — railroad engineering Dept.
60% Geotechnical Design ReportIndependent PE, 10 yr railroad GT experienceFull independent review; signed seal requiredRequired — railroad engineering Dept.
100% Final Geotechnical ReportIndependent PE, 10 yr railroad GT experienceFull independent review; signed seal requiredRequired — railroad engineering approval
Emergency Phase 2 Letter ReportSenior PE, same firm acceptableReview within 24 hours of issueNotify only; no formal approval
Permanent Emergency Repair ReportIndependent PE, 10 yr railroad GT experienceFull independent reviewRequired — railroad engineering Dept.

Client-specific peer review considerations:

  • A Class I railroad: The railroad's engineering department department conducts its own independent technical review of all 60% and 100% submissions. Our independent peer review must be completed and all comments resolved before we issue to a Class I railroad; do not submit a document to Class I railroad review with known open peer review comments.
  • High-speed passenger corridor: The railroad's engineering department conducts a formal technical review of all 60% and 100% submissions under the railroad's Quality Management Program. The passenger railroad applies its own criteria in that review, so the peer reviewer must know them.
  • Class I railroad operations located in Canada: TC RSA-regulated projects in Canada may require TC review of geotechnical findings that affect safety-critical infrastructure. The railroad's engineering department coordinates TC filings; our role is to provide technically complete documentation that supports the railroad's regulatory submission.
  • A Class I railroad: Post-merger the railroad is developing harmonized review processes. Confirm the current 60% and 100% review process with the railroad's engineering group at the beginning of each project.
  • A Class I railroad: Some railroads have internal review requirements for capital projects above set thresholds; confirm the current process with the owner railroad when the work is scoped. We confirm the railroad's current internal review process with the railroad's regional engineer at project initiation.
Project management · ASCE (2012)

When and How to Commission a Project Peer Review

ASCE (2012) defines peer review as an independent assessment by experienced professionals who have not worked on the project or organization being reviewed. It distinguishes organizational reviews (how faithfully a firm or agency follows its own policies; usually confidential and often oral) from project reviews, which examine the technical results of a project at its current stage and are reported in writing. Peer reviewers are advisory; they identify gaps and do not direct changes, and the original engineer keeps full legal responsibility. A peer review is also not value engineering: VE asks whether the right overall solution has been chosen, while design peer review asks whether the chosen solution is engineered correctly.

Engineering Ethics — Integrity, Responsibility, Public Trust
Engineering Ethics — Integrity, Responsibility, Public Trust

The Manual lists circumstances that suggest a project review: a project larger or more complex than the team usually handles; new technology; difficulties on similar past projects; changed objectives or disputes; many offices or organizations; a fast-track schedule; limited budgets; staffing concerns or recent departure of key people; large potential liability or unusual public risk; uncertain status of work to date; and special environmental concerns. Typical scope items are design assumptions and criteria, applicable codes, spot-checks of calculations, clarity and completeness of reports, alternatives considered, judgment, constructability, proposed construction means and methods, and prospects of meeting objectives.

The process has six steps: request, scoping, reviewer selection, preliminary document review, on-site document review and confidential interviews, and reporting, followed by follow-up actions with measurable goals. Reviews held at earlier milestones usually yield more benefit than a review only at final design. A project review report typically covers scope and limits, schedule and status, phase reviewed, needed corrective actions, and issues for further evaluation. The EJCDC publishes a standard agreement for independent project peer review.

For railroad work: Several of the Manual’s triggers are common on railroad ground-hazard projects: emergency slide repairs designed on a compressed schedule, novel stabilization methods, high consequence of failure under traffic, and work spread across several offices. For such deliverables, set the peer review scope at the concept stage (failure mechanism, design parameters, analysis method) rather than only at final plans, and keep reviewer comments and their disposition in the project file.

Source: American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE, pp. 213–222. Summarized and paraphrased. Full reference under Supplemental References.