3.9.3 Regulatory and Client-Standard Requirements That Frame the Investigation

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project.
Authors: Daniel P. Colwell and Mario Ruel
3.9.3 Regulatory and Client-Standard Requirements That Frame the Investigation

Before finalizing boring locations and depths, we confirm which standards govern the investigation. Railroad clients do not all use the same standards; mixing them up is a professional error that creates review problems and can require costly revisions.

OSHA Top 10 Violations 2023–2026
OSHA Top 10 Violations 2023–2026

AREMA MRE Chapter 1 — Roadway and Ballast is the common technical baseline for subgrade-related investigations on owner railroads. AREMA MRE Chapter 1, Part 2 (Section 3.10) sizes the ballast and subballast from the strength and gradation of the subgrade, so the subgrade must be characterized before those thicknesses are set. AREMA MRE Chapter 8 — Structures governs foundation design for bridges, retaining walls, and culverts using Cooper E-80 design live load.

Each owner railroad also has its own engineering standards, and they differ in boring spacing and depth, log format, sample retention, review and track-access requirements. Obtain the current edition from the owner railroad when the work is scoped, record which edition was used, and follow it where it is stricter than the published guidance in this manual.

Supplemental reference

Utility and pipeline crossings — Class I railroad occupancy requirements

Pipeline and utility crossings are a frequent small task order, and the railroad’s occupancy specification — not the utility owner’s design standard — sets the investigation scope. The railroad's Pipeline Occupancies specification (rev. 2018) requires:

  • When borings are required: for every crossing with a casing 48 in. or larger under track; at the railroad's discretion for smaller casings and other right-of-way facilities.
  • Location: one boring each side of the track(s), on the pipe centerline and as close to track as practicable, with a scaled plan showing borings relative to track and pipe. A Right of Entry permit is needed before drilling.
  • Sampling: ASTM D1586 SPT, continuous from ground surface to 5 ft below the proposed invert. Rock is cored with an M-series double-tube diamond barrel (≥ 1⅝ in. core), runs ≤ 5 ft. Auger-cutting or washwater samples are not acceptable.
  • Closure: record groundwater, then grout the full depth with 4-3-1 bentonite–cement–sand grout.
  • Cover: casing under track ≥ 5.5 ft base of rail to top of pipe; uncased gas lines ≥ 10 ft. Longitudinal lines within 50 ft of centerline need 4 ft cover (non-flammable) or 6 ft (flammable).
  • Methods: bore-and-jack is standard; HDD is a variance considered only with ≥ 15 ft cover or in rock; open cut is not permitted under mainline, heavy-tonnage or passenger tracks.

Table 5-S1. Class I railroad live load on buried structures, Cooper E-80 including impact

Cover (ft)234568101216202530
Load (psf)3,8003,1502,8502,5502,2501,7001,3001,000625400250150

For lateral surcharge on sheet piling or pits beside the track, the railroad specifies a Boussinesq strip load 8.5 ft wide (tie length) with q = 80,000 / (8.5 × 5) = 1,882 psf per E-80 axle. Expect pushback on casings from pipeline owners: Miesner and Leffler explain that the industry has moved away from cased road and railroad crossings because the carrier must be electrically insulated from the casing to prevent galvanic corrosion, and shorted casings are a chronic corrosion problem. That is the reason owners ask for uncased crossings — which the railroad allows for gas lines only at 10 ft or more below base of rail.

Source: A Class I railroad (2018). Design and Construction Standard Specifications — Pipeline Occupancies. Office of VP–Engineering, Jacksonville, FL (rev. June 5, 2018) · Miesner, T. O. and Leffler, W. L. (2006). Oil and Gas Pipelines in Nontechnical Language. PennWell

Supplemental reference

Under-track culverts — Class I railroad criteria that drive the geotechnical scope

  • Design for Cooper E-80 and the 100-year storm; headwater limited to HW/D = 1.5 (inlet control) provided high water stays below the toe of ballast and the fill resists short-term infiltration.
  • Minimum culvert size 36 in.; Rational Method for basins under 500 acres, SCS unit hydrograph or regression methods for larger basins.
  • Coating selection follows soil and water pH: aluminized/bituminous galvanized for pH 5–8; fiber-bonded or plastic-coated where fertilizer runoff, acidic coal-field drainage, salt marsh or heavy-metal soils are present — so plan pH, resistivity and sulfate testing at culvert borings.
  • Smooth-wall casing by jack-and-bore where traffic prevents open cut or fill exceeds 10 ft; tunnel liner plate where diameter, length or rock make jacking impractical.
  • Precast or concrete pipe culverts are not permitted under railroad-owned track without Chief Engineer approval, because of differential settlement and joint separation.

Source: A Class I railroad. Guidelines for Under Track Culverts