3.9.13 Practice Questions

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project.
Authors: Daniel P. Colwell and Mario Ruel
3.9.13 Practice Questions
Each question is worked in the same five parts as the examples. Questions 3.9-3 and 3.9-5 are planning questions, so their steps are a chain of reasoning rather than equations.
Question 3.9-1: Boring Count and Depth for a New Siding

Problem Statement

A Class I railroad located in the Mississippi Delta plans a 6,500-ft siding on flat alluvial ground, built on a 6-ft fill with a 60-ft base. The railroad’s standard (assumed here) calls for one boring per 1,500 ft and a 25-ft minimum depth. The geotechnical engineer must set the number and depth of borings for the proposal and show whether the owner’s minimum or the published embankment criteria govern.

Alluvium: silty clay and fine sandSiding L = 6,500 ft6-ft fill, 60-ft base; owner: 1 per 1,500 ft, 25 ft min.Number = ? Depth = ? Which governs?GivenL = 6,500 ft1 boring per 1,500 ft (owner)25 ft minimum depth (owner)H = 6 ft; B = 60 ftSilty clay and fine sand alluviumRequired(a) Number of borings(b) Depth from embankment criteria(c) Which governsBlack = given; red = required
Given and required for Question 3.9-1.

Given

VariableValueDescription
L6,500 ftSiding length
Spacing1 boring per 1,500 ft (owner minimum, assumed)
Owner depth25 ft minimum (assumed)
H, B6 ft; 60 ftFill height and base width
SoilSilty clay and fine sand alluvium

Required

  • (a) Number of borings
  • (b) Depth from the embankment criteria
  • (c) Which governs

Equations

  1. Eq. 1: N = L / s, rounded up, + 1

Steps

Step 1 · (a) Count
6,500 / 1,500 = 4.33 → 5 spaces
6 borings, one at each end
↓
Step 2 · (b) Embankment criteria
Das 0.5H to 2H = 3 to 12 ft; Li et al. 10 to 15 ft
12 to 15 ft
↓
Step 3 · (c) Compare
Owner 25 ft > 15 ft
Owner minimum governs: 25 ft, deeper through soft soil
↓
Step 4 · Spacing check
Li et al., about 200 ft on medium alluvium: 6,500/200 + 1
About 34 borings
↓
Solution
6 borings minimum, 25 ft deep.

Solution

(a) 6 borings. (b) 12 to 15 ft from the embankment criteria. (c) The owner’s 25-ft minimum governs.

The published spacing guidance would call for about 34 borings, so the owner’s 1,500-ft spacing is a floor, not a target. Where the first borings show variable alluvium, add borings rather than defend the minimum.

Question 3.9-2: Rock Coring for Drilled Shafts

Problem Statement

A railroad bridge over a creek is being replaced, and the new spans will sit on drilled shafts socketed into rock. The only record at the site is a 1967 boring that found weathered granite at 18 ft and auger refusal at 22 ft. The engineer must specify how deep the new borings go and what rock data the coring must deliver for socket design.

OverburdenWeathered granite (1967 log)010203040Depth (ft)Rock at 18 ftAuger refusal 22 ftDepth = ? Rock data?Creek bridge, drilled shaft socketsGivenWeathered granite at 18 ftRefusal at 22 ft (1967 log)Drilled shafts socketed in rock≥ 20 ft of core below rock surfaceRequiredMinimum boring depthRock data the coring must provideBlack = given; red = required
Given and required for Question 3.9-2.

Given

VariableValueDescription
RockWeathered granite at 18 ft; refusal at 22 ft1967 boring log
FoundationDrilled shafts
RuleAt least 20 ft of core below the rock surfaceCommon practice for shaft sockets

Required

  • Minimum boring depth
  • Rock data the coring must provide

Equations

  1. Eq. 1: D = rock surface + 20 ft of core

Steps

Step 1 · Depth (Eq. 1)
22 + 20
At least 42 ft, with 20 ft of NX or NQ core
↓
Step 2 · Data (USACE EM 1110-1-1804)
RQD (ASTM D6032), core recovery, qu (laboratory or point load), weathering, fracture frequency, infilling and orientation
↓
Step 3 · Data for socket design (AREMA Chapter 8)
qu and joint condition, frequency and weathering grade
↓
Solution
At least 42 ft, with 20 ft of core and full rock logging.

Solution

At least 42 ft, including 20 ft of NX or NQ core below the rock surface, logged for RQD, recovery, strength, weathering and jointing.

A common criterion before calling a horizon competent bearing is at least 10 ft of core with RQD of 50% or more and recovery of 80% or more. Refusal at 22 ft may be a boulder or a weathered zone, which is why coring, not refusal, defines the top of rock.

Question 3.9-3: Expired Roadway Worker Certificates in an Emergency

Problem Statement

At 10:00 PM the railroad calls: a cut slope has failed onto a main track and it needs a geotechnical crew on site by 6:00 AM. Of the four available staff, two hold current roadway worker protection certificates and two let theirs lapse four months ago. The project manager must decide who can go onto the right-of-way and how to staff the response.

Main track blocked10:00 PM call → on site 6:00 AM2 current RWP, 2 expired 4 monthsEscort allowed? Course of action?GivenCrew of 4: 2 current RWP2 expired 4 months agoOn site 6:00 AM (now 10:00 PM)Rule: everyone on right-of-way must hold current certificateRequiredCan expired staff enter under escort?Correct course of actionBlack = given; red = required
Given and required for Question 3.9-3.

Given

VariableValueDescription
Crew4; 2 with current RWP, 2 expired 4 months ago
DeadlineOn site by 6:00 AM; now 10:00 PM
RuleEach person who enters the right-of-way must hold a current certificateRailroad RWP program

Required

  • Whether the expired personnel can enter under escort
  • The correct course of action

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · Can escort substitute for certification?
No. Escort covers visitors, not technical staff doing work on the right-of-way.
↓
Step 2 · Who mobilizes?
The two certified staff, immediately, as a two-person crew.
↓
Step 3 · What else?
Ask the railroad’s RWP coordinator whether an emergency process exists; enroll the other two in the next class; document the limitation in the project file.
↓
Solution
No: send the two certified staff, and fix the lapse.

Solution

No. Only the two staff with current certificates may enter the right-of-way. They mobilize now; the other two stay off the right-of-way.

Contact the railroad’s RWP training coordinator about any emergency provision, enroll the two in the next class, and record in the project file how the crew was deployed. A certificate should never be allowed to lapse during an active contract; track expiry dates with the project schedule.

Question 3.9-4: Borings Beyond the Toe for an Embankment Widening

Problem Statement

A Class I railroad is adding a second main track by widening a 20-ft embankment 12 ft on each side and raising it 4 ft. Existing borings are on the centerline only and reach 45 ft. Before the scope is priced, the engineer must decide whether borings are needed outside the existing toe and, if so, where they should go.

CL boring 45 ftold toenew toeslip surfaces 0.5H–1.0H beyond toeBorings beyond toe? Where?GivenH = 20 ft; raise 4 ftWiden 12 ft each sideToe ~60 ft → ~72 ft from CLCenterline borings to 45 ftSlip surfaces 0.5H–1.0H past toeRequiredAre borings beyond the toe needed?Where to put themBlack = given; red = required
Given and required for Question 3.9-4.

Given

VariableValueDescription
H20 ft existing; 4-ft raiseEmbankment
Widening12 ft each side
Existing toeAbout 60 ft from centerlineNew toe about 72 ft out
BoringsCenterline to 45 ftExisting data
RuleCritical slip surfaces extend about 0.5H to 1.0H beyond the toeSection 6.3

Required

  • Whether borings beyond the toe are needed, and where

Equations

  1. Eq. 1: x = new toe + (0.5 to 1.0) H — reach of the critical slip surface
  2. Eq. 2: q = γ H — load at the new toe area

Steps

Step 1 · Where is the new load?
Under the widening, outside the old toe, on ground that has never been loaded or sampled.
↓
Step 2 · Reach of the slip surface (Eq. 1)
72 + (10 to 20)
About 80 to 90 ft from centerline
↓
Step 3 · Data needed there
Strength of the natural foundation soil, which the centerline borings do not sample.
↓
Solution
Yes: borings about 20 to 30 ft beyond the new toe.

Solution

Yes. Place borings about 20 to 30 ft beyond the new toe, roughly 80 to 100 ft from centerline.

The centerline borings describe soil that has carried the embankment for decades and has consolidated under it; the soil under the widening has not. The stability of the widened slope depends on that unloaded soil, so without borings there the factor of safety is undocumented (AREMA Chapter 1, Part 1).

Question 3.9-5: Investigating Beside a High-Speed Passenger Corridor

Problem Statement

A signal bridge on a passenger corridor operated at FRA Class 7 (125 mph) is to be replaced. The engineer has scoped many freight bridge investigations on Class 4 track but none on a high-speed line. Before writing the work plan, the engineer must identify what makes this investigation different and list the planning requirements that follow.

Signal bridge (replace)FRA Class 7, 125 mphFive planning requirements that differ = ?Compared with: Class 4 freight bridgeGivenFRA Class 7, 125 mph49 CFR 213, Subpart GSignal bridge replacementComparison: Class 4 freight bridgeRequiredFive planning requirements that distinguish this investigationBlack = given; red = required
Given and required for Question 3.9-5.

Given

VariableValueDescription
TrackFRA Class 7, 125 mph49 CFR 213, Subpart G
WorkSignal bridge replacement
ComparisonClass 4 freight bridge

Required

  • Five planning requirements that distinguish the investigation

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · Track time
Short overnight possessions; equipment that sets up and clears quickly; possession requests weeks ahead.
↓
Step 2 · Geometry tolerances
Class 7 limits (49 CFR 213.331) are tighter than Class 4 (213.63): 1 in. against 1¼ in. cross level, 1 in. against 2 in. profile on a 62-ft chord. Settlement must be predicted to that standard.
↓
Step 3 · Review
Formal owner review of 60% and 100% submissions; more documentation.
↓
Step 4 · Signals and power
Clearance from signal circuits for each boring near the track, and electrical clearance from the overhead catenary for the drill mast.
↓
Solution
Track time, tighter tolerances, owner review, signal clearance, catenary clearance.

Solution

The five are: short track possessions, Class 7 geometry tolerances, formal owner peer review, signal circuit clearance, and catenary electrical clearance.

The tolerances drive the technical scope: settlement predictions compared with a 1-in. limit usually need consolidation tests on every soft layer, not only the worst one. The other four drive cost and schedule and belong in the investigation plan memorandum before a price is given.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • RK-10 UCS from point load index σ꜀Use: Hard, isotropic rock; quick strength index in field. Limits: K varies widely with rock type and anisotropy; calibrate with lab UCS. Unreliable in weak rock (σc < ~3,600 psi).