Each question is worked in the same five parts as the examples. Questions 3.9-3 and 3.9-5 are planning questions, so their steps are a chain of reasoning rather than equations.
Question 3.9-1: Boring Count and Depth for a New Siding
Problem Statement
A Class I railroad located in the Mississippi Delta plans a 6,500-ft siding on flat alluvial ground, built on a 6-ft fill with a 60-ft base. The railroad’s standard (assumed here) calls for one boring per 1,500 ft and a 25-ft minimum depth. The geotechnical engineer must set the number and depth of borings for the proposal and show whether the owner’s minimum or the published embankment criteria govern.
Given and required for Question 3.9-1.
Given
Variable
Value
Description
L
6,500 ft
Siding length
Spacing
1 boring per 1,500 ft (owner minimum, assumed)
Owner depth
25 ft minimum (assumed)
H, B
6 ft; 60 ft
Fill height and base width
Soil
Silty clay and fine sand alluvium
Required
(a) Number of borings
(b) Depth from the embankment criteria
(c) Which governs
Equations
Eq. 1: N = L / s, rounded up, + 1
Steps
Step 1 · (a) Count
6,500 / 1,500 = 4.33 → 5 spaces
6 borings, one at each end
↓
Step 2 · (b) Embankment criteria
Das 0.5H to 2H = 3 to 12 ft; Li et al. 10 to 15 ft
12 to 15 ft
↓
Step 3 · (c) Compare
Owner 25 ft > 15 ft
Owner minimum governs: 25 ft, deeper through soft soil
↓
Step 4 · Spacing check
Li et al., about 200 ft on medium alluvium: 6,500/200 + 1
About 34 borings
↓
Solution
6 borings minimum, 25 ft deep.
Solution
(a) 6 borings. (b) 12 to 15 ft from the embankment criteria. (c) The owner’s 25-ft minimum governs.
The published spacing guidance would call for about 34 borings, so the owner’s 1,500-ft spacing is a floor, not a target. Where the first borings show variable alluvium, add borings rather than defend the minimum.
Question 3.9-2: Rock Coring for Drilled Shafts
Problem Statement
A railroad bridge over a creek is being replaced, and the new spans will sit on drilled shafts socketed into rock. The only record at the site is a 1967 boring that found weathered granite at 18 ft and auger refusal at 22 ft. The engineer must specify how deep the new borings go and what rock data the coring must deliver for socket design.
qu and joint condition, frequency and weathering grade
↓
Solution
At least 42 ft, with 20 ft of core and full rock logging.
Solution
At least 42 ft, including 20 ft of NX or NQ core below the rock surface, logged for RQD, recovery, strength, weathering and jointing.
A common criterion before calling a horizon competent bearing is at least 10 ft of core with RQD of 50% or more and recovery of 80% or more. Refusal at 22 ft may be a boulder or a weathered zone, which is why coring, not refusal, defines the top of rock.
Question 3.9-3: Expired Roadway Worker Certificates in an Emergency
Problem Statement
At 10:00 PM the railroad calls: a cut slope has failed onto a main track and it needs a geotechnical crew on site by 6:00 AM. Of the four available staff, two hold current roadway worker protection certificates and two let theirs lapse four months ago. The project manager must decide who can go onto the right-of-way and how to staff the response.
Given and required for Question 3.9-3.
Given
Variable
Value
Description
Crew
4; 2 with current RWP, 2 expired 4 months ago
Deadline
On site by 6:00 AM; now 10:00 PM
Rule
Each person who enters the right-of-way must hold a current certificate
Railroad RWP program
Required
Whether the expired personnel can enter under escort
The correct course of action
Equations
No equation is needed; the answer follows from the criteria listed under Given.
Steps
Step 1 · Can escort substitute for certification?
No. Escort covers visitors, not technical staff doing work on the right-of-way.
↓
Step 2 · Who mobilizes?
The two certified staff, immediately, as a two-person crew.
↓
Step 3 · What else?
Ask the railroad’s RWP coordinator whether an emergency process exists; enroll the other two in the next class; document the limitation in the project file.
↓
Solution
No: send the two certified staff, and fix the lapse.
Solution
No. Only the two staff with current certificates may enter the right-of-way. They mobilize now; the other two stay off the right-of-way.
Contact the railroad’s RWP training coordinator about any emergency provision, enroll the two in the next class, and record in the project file how the crew was deployed. A certificate should never be allowed to lapse during an active contract; track expiry dates with the project schedule.
Question 3.9-4: Borings Beyond the Toe for an Embankment Widening
Problem Statement
A Class I railroad is adding a second main track by widening a 20-ft embankment 12 ft on each side and raising it 4 ft. Existing borings are on the centerline only and reach 45 ft. Before the scope is priced, the engineer must decide whether borings are needed outside the existing toe and, if so, where they should go.
Given and required for Question 3.9-4.
Given
Variable
Value
Description
H
20 ft existing; 4-ft raise
Embankment
Widening
12 ft each side
Existing toe
About 60 ft from centerline
New toe about 72 ft out
Borings
Centerline to 45 ft
Existing data
Rule
Critical slip surfaces extend about 0.5H to 1.0H beyond the toe
Section 6.3
Required
Whether borings beyond the toe are needed, and where
Equations
Eq. 1: x = new toe + (0.5 to 1.0) H — reach of the critical slip surface
Eq. 2: q = γ H — load at the new toe area
Steps
Step 1 · Where is the new load?
Under the widening, outside the old toe, on ground that has never been loaded or sampled.
↓
Step 2 · Reach of the slip surface (Eq. 1)
72 + (10 to 20)
About 80 to 90 ft from centerline
↓
Step 3 · Data needed there
Strength of the natural foundation soil, which the centerline borings do not sample.
↓
Solution
Yes: borings about 20 to 30 ft beyond the new toe.
Solution
Yes. Place borings about 20 to 30 ft beyond the new toe, roughly 80 to 100 ft from centerline.
The centerline borings describe soil that has carried the embankment for decades and has consolidated under it; the soil under the widening has not. The stability of the widened slope depends on that unloaded soil, so without borings there the factor of safety is undocumented (AREMA Chapter 1, Part 1).
Question 3.9-5: Investigating Beside a High-Speed Passenger Corridor
Problem Statement
A signal bridge on a passenger corridor operated at FRA Class 7 (125 mph) is to be replaced. The engineer has scoped many freight bridge investigations on Class 4 track but none on a high-speed line. Before writing the work plan, the engineer must identify what makes this investigation different and list the planning requirements that follow.
Given and required for Question 3.9-5.
Given
Variable
Value
Description
Track
FRA Class 7, 125 mph
49 CFR 213, Subpart G
Work
Signal bridge replacement
Comparison
Class 4 freight bridge
Required
Five planning requirements that distinguish the investigation
Equations
No equation is needed; the answer follows from the criteria listed under Given.
Steps
Step 1 · Track time
Short overnight possessions; equipment that sets up and clears quickly; possession requests weeks ahead.
↓
Step 2 · Geometry tolerances
Class 7 limits (49 CFR 213.331) are tighter than Class 4 (213.63): 1 in. against 1¼ in. cross level, 1 in. against 2 in. profile on a 62-ft chord. Settlement must be predicted to that standard.
↓
Step 3 · Review
Formal owner review of 60% and 100% submissions; more documentation.
↓
Step 4 · Signals and power
Clearance from signal circuits for each boring near the track, and electrical clearance from the overhead catenary for the drill mast.
↓
Solution
Track time, tighter tolerances, owner review, signal clearance, catenary clearance.
Solution
The five are: short track possessions, Class 7 geometry tolerances, formal owner peer review, signal circuit clearance, and catenary electrical clearance.
The tolerances drive the technical scope: settlement predictions compared with a 1-in. limit usually need consolidation tests on every soft layer, not only the worst one. The other four drive cost and schedule and belong in the investigation plan memorandum before a price is given.
Empirical equation note · this section
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
RK-10 UCS from point load indexσ꜀Use: Hard, isotropic rock; quick strength index in field. Limits: K varies widely with rock type and anisotropy; calibrate with lab UCS. Unreliable in weak rock (σc < ~3,600 psi).