A new 4,800-ft siding needs a 12-ft fill. Boring depth for an embankment is often set with the stress rule written for structures, and the example shows why that gives an absurd answer for a wide fill, and what to use instead.
| Variable | Value | Description |
|---|---|---|
| H | 12 ft | Embankment height |
| γfill | 125 pcf | Compacted granular fill (assumed) |
| B | 80 ft | Base width; 2H:1V slopes, two tracks at 14-ft centers |
| γ | 118 pcf | Residual sandy clay |
| zw | 15 ft | Depth to water; γ′ = 55.6 pcf below it |
| Criteria | Section 3.9.5.3.3 | Stress rule (D1: Δσ = 10% q; D2: Δσ = 5% σ′v); embankment rules of Das (0.5 to 2H), Li et al. (10 to 15 ft) and Look (through compressible soil) |
The stress rule gives 162 ft, which no one would drill for a 12-ft fill. Take the centerline boring to about 25 ft below existing ground (2H) and extend it through any soft or compressible soil found.
The stress rule was written for structures with modest footprints; under an 80-ft-wide strip the stress decays so slowly that the rule runs to absurd depths. For embankments the published embankment criteria govern. Record the basis of the depth in the boring plan, so the reviewer sees it was chosen, not guessed.
A bridge replacement on a Class I railroad main line needs a new pile-supported abutment. Old borings show where the existing piles stopped, which is the best first guess at where the new ones will.
| Variable | Value | Description |
|---|---|---|
| Refusal (1962 borings) | 45 ft | Existing HP piles assumed to stop near here |
| New pile tip | 40 to 55 ft | Range for the new load |
| Rule | 20 ft below the estimated pile tip | Section 3.9.5.2 |
| Owner rule (assumed) | At least 20 ft into competent bearing material, or refusal, whichever is deeper | Confirm with the railroad’s engineer |
Drill to at least 75 ft, or 5 ft below the first refusal horizon, whichever is deeper.
Using the deep end of the tip range protects against a second mobilization if the design load pushes the piles deeper than the old ones. Refusal in 1962 may have been on a boulder or a hard layer over softer soil, so the new borings should core or sample through it rather than stop.
A first-pass boring count and footage for a new intermodal yard expansion, built up zone by zone. The total drives the drilling budget in Chapter 3.7.
| Variable | Value | Description |
|---|---|---|
| Footprint | 2,200 ft × 800 ft | Yard area |
| Cranes | 3 parallel crane rails, each 2,100 ft | Borings at 200-ft spacing, 65 ft deep (20 ft below a 45-ft pile tip) |
| Pavement | 20 acres | 1 boring per 2 acres, 20 ft deep |
| Building | 100 ft × 200 ft | 4 corners + center, 60 ft deep (piles assumed) |
| Other | Drainage, gate, utilities | 6 borings, 15 ft deep |
About 54 borings totaling 2,735 linear feet.
The crane rails take over three-quarters of the footage, because their pile foundations need deep borings at close spacing. That is where scope negotiation should focus: if the crane design allows 300-ft spacing, the count drops by about 10 borings and 650 ft.