3.9.6 Worked Calculation Examples

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project.
Authors: Daniel P. Colwell and Mario Ruel
3.9.6 Worked Calculation Examples
The three examples set boring depth for an embankment and a bridge abutment, and build a boring scope for a yard. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 3.9-1: Boring Depth for a New Siding Embankment

A new 4,800-ft siding needs a 12-ft fill. Boring depth for an embankment is often set with the stress rule written for structures, and the example shows why that gives an absurd answer for a wide fill, and what to use instead.

Residual sandy clay, γ = 118 pcfFill 12 ft, γ = 125 pcfB = 80 ftGWT 15 ftD1, D2 = ?Boring depth = ?14-ft track centersGivenH = 12 ft; γfill = 125 pcfB = 80 ft; 2H:1V; two tracksClay γ = 118 pcf; GWT 15 ftD1: Δσ = 10% qD2: Δσ = 5% σ′v Das, Li et al., Look rulesRequiredStress-rule depths D1 and D2 Recommended centerline depthBlack = given; red = required
Given and required for Example 3.9-1.

Given

VariableValueDescription
H12 ftEmbankment height
γfill125 pcfCompacted granular fill (assumed)
B80 ftBase width; 2H:1V slopes, two tracks at 14-ft centers
γ118 pcfResidual sandy clay
zw15 ftDepth to water; γ′ = 55.6 pcf below it
CriteriaSection 3.9.5.3.3Stress rule (D1: Δσ = 10% q; D2: Δσ = 5% σ′v); embankment rules of Das (0.5 to 2H), Li et al. (10 to 15 ft) and Look (through compressible soil)

Required

  • Stress-rule depths D1 and D2
  • Recommended centerline boring depth

Equations

  1. Eq. 1: q = γfill H — applied stress
  2. Eq. 2: Δσz = q B / (B + z) — 2:1 method, strip
  3. Eq. 3: D1: B/(B + z) = 0.10; D2: q B/(B + z) = 0.05 σ′v(z) — stress rule

Steps

Step 1 · Applied stress (Eq. 1)
125 × 12
q = 1,500 psf
↓
Step 2 · D1 (Eq. 3)
80/(80 + z) = 0.10
z = 720 ft
↓
Step 3 · D2 (Eq. 3)
120,000/(80 + z) = 0.05[1,770 + 55.6(z − 15)]
z ≈ 162 ft
Spot check: At 162 ft: Δσ = 120,000/242 = 496 psf; 5% of (1,770 + 55.6 × 147) = 5% of 9,943 = 497 psf.
↓
Step 4 · Embankment criteria
Das: 0.5H to 2H = 6 to 24 ft; Li et al.: 10 to 15 ft; Look: through compressible soil
About 25 ft (2H), extended through any soft soil
↓
Solution
Drill about 25 ft below grade, deeper through any soft soil.

Solution

The stress rule gives 162 ft, which no one would drill for a 12-ft fill. Take the centerline boring to about 25 ft below existing ground (2H) and extend it through any soft or compressible soil found.

The stress rule was written for structures with modest footprints; under an 80-ft-wide strip the stress decays so slowly that the rule runs to absurd depths. For embankments the published embankment criteria govern. Record the basis of the depth in the boring plan, so the reviewer sees it was chosen, not guessed.

Example 3.9-2: Boring Depth for a Pile-Supported Bridge Abutment

A bridge replacement on a Class I railroad main line needs a new pile-supported abutment. Old borings show where the existing piles stopped, which is the best first guess at where the new ones will.

Soil Exploration and Foundation Basics
Soil Exploration and Foundation Basics

Given

VariableValueDescription
Refusal (1962 borings)45 ftExisting HP piles assumed to stop near here
New pile tip40 to 55 ftRange for the new load
Rule20 ft below the estimated pile tipSection 3.9.5.2
Owner rule (assumed)At least 20 ft into competent bearing material, or refusal, whichever is deeperConfirm with the railroad’s engineer

Required

  • Minimum boring depth

Equations

  1. Eq. 1: D = deepest estimated tip + 20 ft — Section 3.9.5.2

Steps

Step 1 · Deepest estimated tip
Upper end of 40 to 55 ft
55 ft
↓
Step 2 · Depth (Eq. 1)
55 + 20
75 ft
↓
Step 3 · Owner rule
Also 5 ft below the first refusal horizon, if that is deeper
↓
Solution
75 ft, or 5 ft below first refusal, whichever is deeper.

Solution

Drill to at least 75 ft, or 5 ft below the first refusal horizon, whichever is deeper.

Using the deep end of the tip range protects against a second mobilization if the design load pushes the piles deeper than the old ones. Refusal in 1962 may have been on a boulder or a hard layer over softer soil, so the new borings should core or sample through it rather than stop.

Example 3.9-3: Preliminary Boring Scope for an Intermodal Yard

A first-pass boring count and footage for a new intermodal yard expansion, built up zone by zone. The total drives the drilling budget in Chapter 3.7.

Yard plan: 2,200 ft × 800 ft3 crane rails, 2,100 ft: borings at 200 ft, 65 ft deepPavement 20 ac: 1 per 2 ac, 20 ftBuildingAcres = ? Boring count and total footage = ?GivenFootprint 2,200 × 800 ftCranes: 3 rails × 2,100 ft; 200-ft spacing, 65 ftPavement 20 ac: 1 per 2 ac, 20 ftBuilding 100 × 200 ft: 5 borings, 60 ftOther: 6 borings, 15 ftRequiredFootprint in acresBoring count and total footageBlack = given; red = required
Given and required for Example 3.9-3.

Given

VariableValueDescription
Footprint2,200 ft × 800 ftYard area
Cranes3 parallel crane rails, each 2,100 ftBorings at 200-ft spacing, 65 ft deep (20 ft below a 45-ft pile tip)
Pavement20 acres1 boring per 2 acres, 20 ft deep
Building100 ft × 200 ft4 corners + center, 60 ft deep (piles assumed)
OtherDrainage, gate, utilities6 borings, 15 ft deep

Required

  • Footprint in acres
  • Boring count and total footage

Equations

  1. Eq. 1: A = L W / 43,560 — acres
  2. Eq. 2: N = L / s + 1 — borings along a line
  3. Eq. 3: Footage = Σ Ni Di

Steps

Step 1 · Area (Eq. 1)
2,200 × 800 / 43,560
40.4 acres
↓
Step 2 · Crane borings (Eq. 2)
3 × (2,100/200 + 1) = 3 × 11.5, rounded to 11 per line
33
↓
Step 3 · Count
33 + 10 + 5 + 6
54 borings
↓
Step 4 · Footage (Eq. 3)
33(65) + 10(20) + 5(60) + 6(15) = 2,145 + 200 + 300 + 90
2,735 ft
↓
Solution
54 borings, 2,735 ft.

Solution

About 54 borings totaling 2,735 linear feet.

The crane rails take over three-quarters of the footage, because their pile foundations need deep borings at close spacing. That is where scope negotiation should focus: if the crane design allows 300-ft spacing, the count drops by about 10 borings and 650 ft.