3.9.4 Boring Location Planning — Criteria by Project Type

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project.
Authors: Daniel P. Colwell and Mario Ruel
3.9.4 Boring Location Planning — Criteria by Project Type

The following boring spacing criteria are taken from published sources in the library; Section 3.9.5.3 sets out the sources, the depth criteria and the planner.

Table 3.9-1: Recommended Boring Spacing by Railroad Project Type
Project TypeSpacing or numberNotesSource
New main, siding or track extensionOne per 500 ft (high-strength soil), 200 ft (medium), 100 ft (low)Add borings at drainage crossings and cut-fill transitionsLi and others (2016), Table 8.1
Existing line, cut and fillSeries of 3 (shoulder, midslope, ditch at toe) about every 1,320 ftA railroad minimum; tighten for the groundA Class I railroad's public projects requirements
Embankment80 to 165 ft at critical areas; 330 ft or more elsewhereShoulder and toe borings at each stationLook, Table 1.8
Cut slope80 to 165 ft (H over 16 ft); 165 to 330 ft (lower cuts)Boring atop the cut and at the toeLook; A Class I railroad's public projects requirements
BridgeEach pier and abutment; one may do for a short bridge in uniform geologyToe of embankment, away from the track, where practicalA Class I railroad's bridge requirements; Look
Retaining wallAt each wall; 50 to 100 ft along the lineDenser in variable groundA Class I railroad's public projects requirements; spacing is practice
CulvertUnder 66 ft: 1; 66 to 130 ft: each end; longer: each end and every 66 ftEach end of a culvert to be extendedLook; A Class I railroad's public projects requirements
Pipeline crossingOne each side of the track on the pipe centerlineContinuous samplingA Class I railroad's pipeline occupancy specification
Yard or intermodal pavementGrid over the paved areaGrid spacing is practice; denser under crane railsEM 1110-1-1804, Table 2-4 (roads)
Slope failureAt least 3 borings or test pits on the critical sectionHead scarp, middle and toeLook, Table 1.8
Subgrade failure or mud boil2 to 4 borings straddling the failureAdd test pits or trenches across the trackPractice

Section 3.9.5.3 gives the full criteria, depths and the planner calculator.

Milepost referencing: All boring locations must be described in terms of railroad mileposts and offset from track centerline (in feet, left or right, looking in the direction of increasing milepost). GPS coordinates (NAD 83, decimal degrees or State Plane in feet) are required in addition to milepost references. Railroad mileposts are the primary location reference for all railroad engineering documents.

Supplemental reference

New alignments and crossing structures that carry wildlife

New alignments and major culvert or bridge replacements increasingly include wildlife passage as a permit condition. The FHWA Wildlife Crossing Structure Handbook gives recommended dimensions for eleven crossing types (overpasses, open-span bridges, large culverts, etc.); most overpasses are under 230–260 ft long, but landscape bridges spanning roads and a railway can be much longer. When a crossing structure is in the scope, add borings at both abutments/footings of the wildlife structure and at the approach fills, and confirm the clear-opening dimensions with the environmental permit before setting foundation boring depths.

Geotechnical Investigation for Bridges
Geotechnical Investigation for Bridges
Landscape bridge near Hilversum, The Netherlands, about 2,600 ft long, spanning two roads and a railroad (photo credit in source: Goois Natuurreservaat / W. Metz).
Supplemental Figure 5-S1. Landscape bridge near Hilversum, The Netherlands, about 2,600 ft long, spanning two roads and a railroad (photo credit in source: Goois Natuurreservaat / W. Metz). Source: Clevenger, A. P. and Huijser, M. P. (2011). Wildlife Crossing Structure Handbook: Design and Evaluation in North America. FHWA-CFL/TD-11-003, p. 60.

Source: Clevenger, A. P. and Huijser, M. P. (2011). Wildlife Crossing Structure Handbook: Design and Evaluation in North America. FHWA-CFL/TD-11-003

What the investigation must answer, and in what stages

No new line can be designed correctly or built economically unless the soils and hydrogeology along the route are known in detail. Profillidis lists what the investigation must establish:

  • whether fill material is available on site or must be imported;
  • appropriate slopes for embankments and cuts;
  • whether loosening or densification of soil may occur;
  • where weak ground needs treatment before filling;
  • where groundwater will cause problems;
  • measures for long-term stability of earthwork slopes;
  • where cuts need special drainage or protection;
  • what planting suits the cut and fill slopes.

Because investigation is costly, run it in stages: assemble existing information; reconnaissance (geologic and topographic maps, aerial photos, water and oil well logs, hydrologic data, state soil manuals); a preliminary site investigation with a few borings or test pits to establish stratification, soil types and groundwater; then the detailed investigation. The program should yield strength, deformation and hydraulic properties at the least cost. Techniques fall into geophysical (seismic, magnetic, gravimetric, resistivity), physical (borings, test pits), mechanical (pressuremeter, penetrometer, laboratory) and hydrogeological (piezometers) methods.

Foundation Soil Investigation
Foundation Soil Investigation
Soil Investigation Before Construction
Soil Investigation Before Construction

After Profillidis (2014), §9.2.1–9.2.4. Full reference under Supplemental References.

What the subgrade investigation must deliver for track design

Before the track structure is designed, the investigation along the alignment should establish, at a minimum:

  • Soil type and classification
  • Strength and bearing capacity
  • Groundwater levels
  • Natural water content (the UFC bearing check in Chapter 1.4, Table 2-S9 uses qu at natural water content)
  • Compaction characteristics of soils that will form or be reused in the subgrade

Add borings, laboratory testing and analysis at bridges and other special structures. AREMA Chapter 1, Part 1 gives the base recommendations, and the spacing in Table 3.9-1 applies. Where chemical stabilization is under consideration in a frost area, include frost-susceptibility and freeze–thaw durability testing in the laboratory program.

After UFC 4-860-01FA (2004), ch. 6, §8b and §8e. Full reference under Supplemental References.

Investigating the trackbed itself

Do not judge the trackbed from the surface. Clean ballast at the surface may be only one particle thick. Selig and Waters recommend the following, in order of effort:

  • Shoulder pits to about 3 ft below the subgrade surface, with the shoulder ballast removed to expose the ballast and subballast.
  • Cross trenches (full or half track width) to at least 4 ft below top of tie. Use them to find ballast pockets and depressions in the subgrade surface.
  • BALCON-type pits. Describe the site and delineate layers by color and gradation. Describe samples to ASTM D2488, with pits 1–2 ft or more below the tie. Many sites can be logged per day. Because layers are usually horizontal, one pit often represents a section. From the gradations, plot the percentage of reclaimable stone against undercut depth. The breaks in slope mark the layer boundaries and set the cutting depth.
  • Rail-mounted boring machine (British Rail). It has a center unit plus two side units that swing out to 10.8 ft from centerline. It drills 6.2 ft below the rail head as standard and up to 16.4 ft, and the core is viewed through a slot in the tube. An intact blanket with no subgrade fouling marks a good candidate for cleaning.
  • Deeper work. Use hollow-stem auger borings with SPT, rock coring and CPT.

Depth. Traffic stress is significant to about 16 ft below the tie, and rail deflection 80 in. down is still about half the surface value. CPT for track-modulus back-analysis should reach at least 16 ft below the tie.

After Selig & Waters (1994), chs. 2, 5, 10, 14 and 16. Full reference under Supplemental References.