The following boring spacing criteria are taken from published sources in the library; Section 3.9.5.3 sets out the sources, the depth criteria and the planner.
| Project Type | Spacing or number | Notes | Source |
|---|---|---|---|
| New main, siding or track extension | One per 500 ft (high-strength soil), 200 ft (medium), 100 ft (low) | Add borings at drainage crossings and cut-fill transitions | Li and others (2016), Table 8.1 |
| Existing line, cut and fill | Series of 3 (shoulder, midslope, ditch at toe) about every 1,320 ft | A railroad minimum; tighten for the ground | A Class I railroad's public projects requirements |
| Embankment | 80 to 165 ft at critical areas; 330 ft or more elsewhere | Shoulder and toe borings at each station | Look, Table 1.8 |
| Cut slope | 80 to 165 ft (H over 16 ft); 165 to 330 ft (lower cuts) | Boring atop the cut and at the toe | Look; A Class I railroad's public projects requirements |
| Bridge | Each pier and abutment; one may do for a short bridge in uniform geology | Toe of embankment, away from the track, where practical | A Class I railroad's bridge requirements; Look |
| Retaining wall | At each wall; 50 to 100 ft along the line | Denser in variable ground | A Class I railroad's public projects requirements; spacing is practice |
| Culvert | Under 66 ft: 1; 66 to 130 ft: each end; longer: each end and every 66 ft | Each end of a culvert to be extended | Look; A Class I railroad's public projects requirements |
| Pipeline crossing | One each side of the track on the pipe centerline | Continuous sampling | A Class I railroad's pipeline occupancy specification |
| Yard or intermodal pavement | Grid over the paved area | Grid spacing is practice; denser under crane rails | EM 1110-1-1804, Table 2-4 (roads) |
| Slope failure | At least 3 borings or test pits on the critical section | Head scarp, middle and toe | Look, Table 1.8 |
| Subgrade failure or mud boil | 2 to 4 borings straddling the failure | Add test pits or trenches across the track | Practice |
Section 3.9.5.3 gives the full criteria, depths and the planner calculator.
Milepost referencing: All boring locations must be described in terms of railroad mileposts and offset from track centerline (in feet, left or right, looking in the direction of increasing milepost). GPS coordinates (NAD 83, decimal degrees or State Plane in feet) are required in addition to milepost references. Railroad mileposts are the primary location reference for all railroad engineering documents.
New alignments and major culvert or bridge replacements increasingly include wildlife passage as a permit condition. The FHWA Wildlife Crossing Structure Handbook gives recommended dimensions for eleven crossing types (overpasses, open-span bridges, large culverts, etc.); most overpasses are under 230–260 ft long, but landscape bridges spanning roads and a railway can be much longer. When a crossing structure is in the scope, add borings at both abutments/footings of the wildlife structure and at the approach fills, and confirm the clear-opening dimensions with the environmental permit before setting foundation boring depths.

Source: Clevenger, A. P. and Huijser, M. P. (2011). Wildlife Crossing Structure Handbook: Design and Evaluation in North America. FHWA-CFL/TD-11-003
No new line can be designed correctly or built economically unless the soils and hydrogeology along the route are known in detail. Profillidis lists what the investigation must establish:
Because investigation is costly, run it in stages: assemble existing information; reconnaissance (geologic and topographic maps, aerial photos, water and oil well logs, hydrologic data, state soil manuals); a preliminary site investigation with a few borings or test pits to establish stratification, soil types and groundwater; then the detailed investigation. The program should yield strength, deformation and hydraulic properties at the least cost. Techniques fall into geophysical (seismic, magnetic, gravimetric, resistivity), physical (borings, test pits), mechanical (pressuremeter, penetrometer, laboratory) and hydrogeological (piezometers) methods.


After Profillidis (2014), §9.2.1–9.2.4. Full reference under Supplemental References.
Before the track structure is designed, the investigation along the alignment should establish, at a minimum:
Add borings, laboratory testing and analysis at bridges and other special structures. AREMA Chapter 1, Part 1 gives the base recommendations, and the spacing in Table 3.9-1 applies. Where chemical stabilization is under consideration in a frost area, include frost-susceptibility and freeze–thaw durability testing in the laboratory program.
After UFC 4-860-01FA (2004), ch. 6, §8b and §8e. Full reference under Supplemental References.
Do not judge the trackbed from the surface. Clean ballast at the surface may be only one particle thick. Selig and Waters recommend the following, in order of effort:
Depth. Traffic stress is significant to about 16 ft below the tie, and rail deflection 80 in. down is still about half the surface value. CPT for track-modulus back-analysis should reach at least 16 ft below the tie.
After Selig & Waters (1994), chs. 2, 5, 10, 14 and 16. Full reference under Supplemental References.