3.9.5 Boring Depth Planning — Criteria and Equations (English Units)

A well-planned geotechnical investigation is the foundation of every successful railroad engineering project.
Authors: Daniel P. Colwell and Mario Ruel
3.9.5 Boring Depth Planning — Criteria and Equations (English Units)

Boring depth must be sufficient to characterize all soil and rock materials that will influence the performance of the planned structure or earthwork. Minimum boring depths for each project type are set by the applicable stress influence criterion, the structure geometry, and the owner railroad's requirements.

3.9.5.1 Stress Influence Criterion — 2:1 Method

For footings and other structures, Das gives the ASCE (1972) rule: the minimum boring depth is the smaller of D1, where the stress increase falls to 10% of the applied pressure, and D2, where it falls to 5% of the effective overburden stress. The rule is for structures, not embankments (Section 3.9.5.3.3). Using the 2:1 stress distribution approximation:

Equation 3.9-1: Stress Increase at Depth z Below a Loaded Area B × L (English units)
Δσz = Q(B + z)(L + z)

Where:

  • Δσ_z = stress increase at depth z (psf)
  • Q = total applied load (lb)
  • B = footing width or embankment base width (ft)
  • L = footing length or embankment base length (ft)
  • z = depth below the base of the loaded area (ft)

Minimum boring depth condition (ASCE 1972, in Das):

D1: Δσz = 0.10 q;   D2: Δσz = 0.05 σ'v0;   minimum depth = smaller of D1 and D2

Where σ'_v₀ is the effective overburden stress at depth z (psf), computed as:

σ'v0 = γ' × z

with γ' = effective unit weight (pcf), typically 55–65 pcf (buoyant) below the water table, or 100–125 pcf (total) above it.

Inputs: where each value comes from (6)
SymbolWhat it isComes fromHow to get itTypical range
Qtotal applied load (lb)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Bfooting width or embankment base width (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Lfooting length or embankment base length (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
zdepth below the base of the loaded area (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
σ'v0vertical stress / pore pressure = γ' × zAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
γ'buoyant unit weightAnother equationγ' = γsat − γw (γw = 62.4 pcf). Use below the water table.50–75 pcf for most mineral soils · by USCS group
Important Foundation Levels
Important Foundation Levels
Equation 3.9-2: Minimum Boring Depth for a Square Footing (B × B)

For a square footing with total applied stress q (psf) over area B²:

D1 = (√10 − 1) B ≈ 2.16 B;   D2: q B² / (B + z)² = 0.05 σ'v0(z), solved by trial

D1 has a closed form for a square footing; D2 does not, because σ'v0 grows with z. The investigation planner (Section 3.9.5.3) solves both.

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
γ'buoyant unit weightAnother equationγ' = γsat − γw (γw = 62.4 pcf). Use below the water table.50–75 pcf for most mineral soils · by USCS group
3.9.5.2 Minimum Boring Depths by Project Type (English Units)
Minimum boring depths by project type
Project TypeMinimum Boring Depth (ft)Source
Track subgrade, new or existing10 to 15 ft below proposed grade; stop at rock or 5 ft into dense or very stiff soilLi and others (2016)
Embankment fill0.5 to 2 times the fill height below original ground, and through compressible soilDas (2010); Look, Table 1.8
Cut slopeTop of cut: to 5 ft below the proposed ditch flowline; toe: 16 ft or 10 ft into rock, whichever is shallowerA Class I railroad's public projects requirements; Look
Bridge, spread footingAbout 2 B below the base, and the ASCE stress depth; Look gives 4 B to 5 BA Class I railroad's bridge requirements; Das; Look
Bridge, piles or shafts10 ft below the estimated tip, or 10 pile diameters in competent strataA Class I railroad's bridge requirements; Look
Bridge pier in a waterwayBelow the estimated scour depth as well as the foundation criterionScour estimate (FHWA HEC-18 methods)
Retaining wallAbout 2 to 2.5 times the retained height for a cantilever soldier pile wall; into rock or a firm layerPractice
Culvert2 B to 4 B below the invert, and below compressible soilLook, Table 1.8
Slope failure investigationBelow the slide zone: as a guide 2 times the slope height or the width of the moving zoneLook, Table 1.8
Rock coringAbout 10 ft into rock to prove it is not a boulderLook, Table 1.8

Values not supported by the sources in the library were removed in the November 2026 fact check (Table 3.9-8).

Supplemental reference

Railroad-bridge boring depth rules of thumb

The railroad's bridge investigation requirements (Ruel, 2003) follow AREMA and add practical limits: borings extend below the depth significantly affected by the loads, river scour or deep shear — about twice the anticipated spread-footing width, or 10 ft below the estimated pile tip from a preliminary static analysis. One boring can be sufficient for a short bridge replacement in uniform, well-mapped geology; where practical, drill at the toe of the embankment rather than on the track. A railroad Bridges & Structures representative accompanies the crew.

The railroad also asks the geotechnical engineer for: allowable pile load vs. depth for each pile type (typical working load about 160 kips for a 14-in. H-pile), DRIVEN static capacity (compression and uplift), GRLWEAP driving criteria and maximum blows/in., p–y curves, and a linear lateral spring constant K per stratum for pile deflection up to about ½ in. at the bridge seat — so SPT, strength and unit-weight data must be sufficient for LPILE input in every stratum.

Table 5-S2. Guideline to extent of investigation (Look, 2007, Table 1.8, abridged)

DevelopmentTest spacingApproximate depth
BridgesEach pier4B–5B for shallow footings; 10 pile diameters in competent strata; in bedrock, ≥ 10 ft of coring and 3 pile diameters below founding level (RQD > 50%, moderately weathered or better)
Buildings65–165 ft2B–4B for pads/strips; 10 ft or 3 diameters below pile toe
Embankments80–165 ft at critical areas; 330–1,650 ft elsewhereBeyond base of compressible alluvium at critical or suspect areas

Source: Ruel, M. and KRK (2003). General Requirements for Geotechnical Investigations for the railroad's Bridge Construction Projects and “A Practical Approach to Lateral Loading on Piles for Railroad Bridge Design on Class I railroad Projects.” a Class I railroad · Look, B. G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis

Geotechnical Investigation
Geotechnical Investigation
3.9.5.3 Required Boring Spacing and Depth

No single code fixes how many borings a railroad project needs or how deep they go. The criteria in the library come from four kinds of source, and they do not all agree: a Class I railroad's own requirements (public projects, bridge foundations and pipeline occupancy), a railway geotechnics text that ties boring spacing along the track to soil strength (Li and others), general investigation guides (Look's Table 1.8, USACE EM 1110-1-1804 Table 2-4 and a short course on site investigation), and the stress rule for structures given by Das. This section sets them side by side, fact-checks the spacing and depth values used elsewhere in this manual against them, and gives the planner that applies them. Use the railroad's requirement as the minimum, then tighten spacing and extend depth for the ground: weak, variable or suspect soil governs over any table.

3.9.5.3.1 Spacing

Table 3.9-5. Boring spacing and number by feature, with sources
FeatureSpacing or numberSource
Track corridor (new siding, second main, extension)One boring every 500 ft in high-strength soil, 200 ft in medium, 100 ft in low-strength soilLi and others (2016), Table 8.1
Existing line, cut and fill (public projects)A series of three borings (on the track grade at the shoulder, at midslope, and in the ditch at the toe) about every quarter mile (1,320 ft), sited to represent the prevailing cut or fillA Class I railroad's public projects requirements
Embankments80 to 165 ft at critical or suspect areas; 330 ft or more elsewhere, as for roadsLook, Table 1.8
Cut slopes80 to 165 ft where H exceeds 16 ft; 165 to 330 ft where H is under 16 ftLook, Table 1.8
Landslide or slope failureAt least three borings or test pits along the critical sectionLook, Table 1.8
BridgesAt each pier and abutment; one boring can be enough for a short bridge in uniform, mapped geologyLook, Table 1.8; EM 1110-1-1804, Table 2-4; a Class I railroad's bridge requirements
CulvertsUnder 66 ft long: one; 66 to 130 ft: one at each end; longer: each end and between, at most 66 ft apart. A boring at each end of a culvert to be extendedLook, Table 1.8; a Class I railroad's public projects requirements
Pipeline crossing under trackOne on each side of the track on the pipe centerline, as close to the track as practicableA Class I railroad's pipeline occupancy specification
Retaining wallsAt each wall; 50 to 100 ft along the wall lineA Class I railroad's public projects requirements (at each wall); spacing is practice
Light towers, signal masts, catenary polesAt each foundationLook, Table 1.8 (monopoles and towers)
Roads and yard pavementOne per 490 ft of centerline for a two-lane road (245 ft multilane); a grid over yards (practice)EM 1110-1-1804, Table 2-4

Look's metric values are converted (25 m = 82 ft, rounded to 80; 50 m = 165 ft). Spacing tightens wherever the ground changes between borings, and test pits, probes or geophysics can fill the gaps.

3.9.5.3.2 Depth

Table 3.9-6. Minimum boring depth by feature, with sources
FeatureMinimum depthExtend whenSource
Track subgrade10 to 15 ft below proposed gradePoor soil is known or suspected; stop at rock or 5 ft into dense or very stiff soilLi and others (2016)
Embankment0.5 to 2 times the embankment height below original ground; beyond the base of compressible soil at critical areasSoft, organic or compressible soil continuesDas (2010); Look, Table 1.8
Cut slopeCut height to 5 ft below the proposed ditch flowline (top-of-cut boring); 16 ft below the toe or 10 ft into rock, whichever is shallowerWater-bearing or weak layers below the cutA Class I railroad's public projects requirements; Look, Table 1.8
LandslideBelow the slide zone: as a guide 2 times the slope height or the width of the moving zone, and 16 ft below the toe or 10 ft into rockThe slip surface is not foundLook, Table 1.8
Bridge, spread footingsAbout 2 B below the base (1.5 B to 2 B); Look gives 4 B to 5 B for bridge footingsCompressible layers within the stress zone; scour depthA Class I railroad's bridge requirements; short course; Look, Table 1.8
Bridge, piles or shafts10 ft below the estimated tip; 10 pile diameters in competent strataWeak layer below the tipA Class I railroad's bridge requirements; Look, Table 1.8
RockAbout 10 ft of core, to show that rock is not a boulder; for bridge piles, 3 diameters below founding levelVoids, clay seams or weathered zonesLook, Table 1.8
Culvert2 B to 4 B below the invert (B = span), and below compressible soilHigh fill over soft groundLook, Table 1.8
Pipeline crossingContinuous sampling to 5 ft below the proposed invert; rock cored–A Class I railroad's pipeline occupancy specification
Light tower or pole15 ft for poles up to 66 ft high, rising to about 49 ft for 230 to 260 ft towers; less in hard ground, 30% more in softLoose sand or soft clayLook, Table 1.8
Road or yard pavement10 ft below finished grade (6.5 ft below formation in Look)Organic or soft fill continuesEM 1110-1-1804, Table 2-4; Look, Table 1.8

Every boring that ends in soft, organic or loose soil, uncontrolled fill, or rock that could be a boulder is extended, whatever the table says.

3.9.5.3.3 The stress rule for structures

For footings and other structures, Das gives the rule recommended by the American Society of Civil Engineers (1972). Find the depth D1 at which the stress increase from the structure falls to 10% of the applied pressure, and the depth D2 at which it falls to 5% of the effective overburden stress. The approximate minimum boring depth is the smaller of the two. The short course gives the same picture from elastic theory: under a square footing the stress increase is about 15% of the applied pressure at 1.5 B and 10% at 2 B, but under a long strip it is still 40% and 30% at those depths, so strips need deeper borings.

Equation 3.9-3. ASCE (1972) boring depth rule, with the 2:1 stress distribution

Δσ(z) = q B L / [(B + z)(L + z)];   D1: Δσ = 0.10 q;   D2: Δσ = 0.05 σ'v0;   minimum depth below the base = smaller of D1 and D2

z is measured below the footing base; σ'v0 is the effective overburden stress at that depth, with the buoyant unit weight below the water table.

The rule was written for buildings and does not work for embankments. Under a strip as wide as a railroad fill, D1 is about 9 times the base width, which is why Das gives a separate range for embankments (one-half to two times the height) and why this manual no longer applies the stress check to fills.

Table 3.9-7. Checks of the planner against the sources
CheckSourcePlanner
Square footing, depth where Δσ = 10% of qAbout 2 B (short course, elastic); 2.16 B (2:1 closed form)2.17 B (B = 10 ft, D1 = 21.7 ft)
Long strip, depth where Δσ = 10% of qWell beyond 2 B (short course: 30% at 2 B); 9 B (2:1 closed form)8.9 B
Track corridor in medium soil, 6,500 ftOne boring every 200 ft (Li and others)34 borings, 510 ft
Culvert 150 ft longEach end and between, at most 66 ft apart (Look)4 borings
Pipeline crossing, invert 9 ft below the trackEach side, to 5 ft below the invert (a Class I railroad's specification)2 borings to 14 ft, rounded to 15 ft

3.9.5.3.4 What the fact check changed

Table 3.9-8. Earlier values in this manual and the published criteria
Earlier valueWherePublished criterionNow
Track subgrade borings every 500 to 1,000 ftTable 3.3-2100 to 500 ft by soil strength (Li and others); quarter-mile series as a railroad minimum100 to 500 ft; quarter-mile series as the floor
New sidings: 3 borings up to 5,000 ft; 1 per 2,500 ft beyondTable 3.9-1As aboveSpacing by soil strength
Embankment over 10 ft: 1.5 times the base width deepSection 3.9.5.20.5 to 2 times the height (Das)0.5 to 2 H, through compressible soil
Depth where Δσ = 10% of σ'v0Section 3.9.5.1Smaller of D1 (10% of q) and D2 (5% of σ'v0), for structures only (ASCE, in Das)Equation 3.9-3
Culvert: one diameter below the invertTable 3.3-32 B to 4 B below the invert (Look)2 B to 4 B
Rock core 5 to 10 ftTable 3.3-3About 10 ft (Look)10 ft
Pile-supported abutment: 20 ft below the tipSection 3.9.5.210 ft below the tip (a Class I railroad's bridge requirements); 10 pile diameters (Look)10 ft or 10 diameters

3.9.5.3.5 Worked examples

Slope repair. A 600-ft embankment repair with 20-ft slopes in medium-strength soil, with the railroad's three-boring series (shoulder, midslope and toe) at each station. At the 165-ft spacing Look gives for critical areas the planner places 5 stations and 15 borings: the shoulder borings go through the fill and one fill height below original ground (40 ft), the midslope and toe borings to 30 ft. That is 500 ft of drilling, about 6.1 days at 90 ft/day including half a day to set up, and a standby allowance of 24.5 hr at 3.5 hr/day.

New siding. A 6,500-ft siding on medium-strength soil needs about 34 borings at 200-ft spacing, each 15 ft deep (510 ft). The railroad's quarter-mile series would give 6 stations and 18 borings; the soil-strength spacing governs here, and the railroad minimum governs only in strong, uniform ground.

Bridge footing. A 10-ft-square pier footing with its base 6 ft deep, bearing 4,000 psf, groundwater at 10 ft: D1 = 21.7 ft and D2 = 38.8 ft below the base, so the stress rule gives 21.7 ft. The railroad's 2 B gives 20 ft. The planner takes the deeper, 21.7 ft, and adds the 6-ft embedment: borings about 30 ft deep at each support.

Write the basis of every boring depth into the boring plan (the rule, its source and the dimension used), and give the driller the instruction to extend any boring that ends in soft or organic soil, fill or possible boulders. A boring stopped at a table depth in the wrong material is the most common reason a second mobilization is needed.

Open the investigation planner calculator →
Boring number, spacing and depth for eleven railroad features from the published criteria above, the ASCE stress check for footings, soil and core footage, drilling days and train standby.

3.9.5.3.6 Sources in the library

These documents are in the reference library. Summaries are paraphrased and metric values converted to English units. Individual railroads are not named.

  • A Class I railroad's public projects geotechnical requirements, 16 Railroad, Carriers folder: quarter-mile boring series, cut and culvert borings.Find source ↗
  • A Class I railroad's general requirements for geotechnical investigations for bridge construction projects (2003), Site Investigation folder: one boring for short bridges, 2 B or 10 ft below the pile tip.Find source ↗
  • A Class I railroad's pipeline occupancy specification (2018), Carriers folder: borings each side of the track to 5 ft below the invert.Find source ↗
  • D. Li, J. Hyslip, T. Sussmann and S. Chrismer, Railway Geotechnics (2016), Section 8.1.2 and Table 8.1: spacing by soil strength, depth 10 to 15 ft below grade.Find source ↗
  • B. G. Look, Handbook of Geotechnical Investigation and Design Tables (2007), Table 1.8: guideline to extent of investigation.Find source ↗
  • USACE, EM 1110-1-1804 Geotechnical Investigations (2001), Table 2-4: suggested boring programs (after Dunlap 1980).Find source ↗
  • B. M. Das, Principles of Geotechnical Engineering, 7th edition, Section 18.1: boring spacing, building depth rules and the ASCE (1972) stress rule; embankments 0.5 to 2 H.Find source ↗
  • A Short Course in Geotechnical Site Investigation, Chapter 1: borehole depth of 1.5 B to 2 B and the stress increase under square and strip footings.Find source ↗