Seeley explains how the civil engineering method of measurement (CESMM3, Class B) breaks a ground investigation into separately priced items, and why. Every group of test pits or borings generates at least two items: the number of holes and the aggregate depth. Costs that follow the number of holes (moving and setting up the rig at each location) are therefore kept apart from costs that follow footage. Further items cover depth in rock versus other material, hole support or backfill, samples by type and class, removal of obstructions (paid by the hour), and pumping (paid by the hour at a stated minimum extraction rate). Hand-dug pits are itemized separately because they cost more. The rate covers preparing and submitting records and results, but not their analysis, which is paid separately.
His sample bill (converted to US units) shows the pattern: 34 trial pits 10–16 ft deep with a minimum base area of about 24 ft², 446 ft of pit depth, 446 ft of backfill, 15 hours of obstruction removal and 30 hours of pumping at a minimum 35 gpm; 14 rotary core holes (4-in. minimum core), 367 ft of cored depth in holes 16–33 ft deep, 367 ft of grout backfill and 28 core boxes 10 ft long; 102 disturbed bag samples of at least 11 lb; and 56 thin-wall tube samples 4 in. × 24 in.
For railroad work: build the cost estimate and the scope of services the same way, so that a change in the number of borings or their depth reprices on its own rather than becoming a negotiation. Typical line items are: mobilization to the subdivision (fixed); moves between holes, priced per hole and split between hi-rail or on-track access and off-track access on the right-of-way; drilling footage in soil and rock in depth bands; coring footage; SPT and thin-wall tube samples counted separately; grouted abandonment per foot; standby hours for flagging delays or train traffic; and per-day items for flagging protection and roadway worker protection briefings where the railroad bills them. Keep laboratory testing and engineering analysis out of the field unit rates, as Class B does, so that adding borings at a growing slide does not quietly use up the analysis budget. A table set up like this also gives the client a clear, auditable invoice against the work authorization.
Source: Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press, pp. 80–81. Summarized and paraphrased. Full reference under Supplemental References.