7.1.4 Wall Types and Selection

Retaining structures are among the most consequential geotechnical elements in railroad capital programs.
Authors: Daniel P. Colwell and Mario Ruel
7.1.4 Wall Types and Selection
7.1.4.1 Gravity Walls

Gravity walls resist sliding and overturning through their own mass. Common materials include mass concrete and dry-laid or mortared stone masonry. Practical retained height limit is approximately 12–15 ft for mass concrete.

Retaining Walls
Retaining Walls
Gravity Retaining Wall
Gravity Retaining Wall

Factor of Safety Against Sliding:

FS_sliding = (W × tan δ_base + c_base × B) / P_A_total ≥ 1.5 (AREMA Ch. 8)

where:

  • W = total vertical weight of wall + retained soil on heel (lb/ft)
  • δ_base = friction angle at base (degrees); typically φ' of foundation soil or 0.9φ' for concrete-on-soil
  • c_base = base adhesion (psf)
  • B = base width (ft)
  • P_A_total = total active force including surcharge (lb/ft)
Crib Retaining Wall
Crib Retaining Wall
MSE Wall — SeaTac Airport Runway Extension
MSE Wall — SeaTac Airport Runway Extension

Factor of Safety Against Overturning:

FS_OT = ΣM_resisting / ΣM_overturning ≥ 2.0 (AREMA Ch. 8)

Resultant Eccentricity:

e = B/2 − (ΣM_resisting − ΣM_overturning) / ΣV (ft)

For no tension at the base, the middle-third rule requires:

e ≤ B/6

This is the usual requirement for gravity and cantilever walls on soil supporting track; confirm the owner railroad's criterion (rock foundations may allow more eccentricity).

Bearing Pressure at Toe:

q_toe = (ΣV/B) × (1 + 6e/B) (psf)

Bearing Pressure at Heel:

q_heel = (ΣV/B) × (1 − 6e/B) (psf)

Inputs for the equations in this section (6)
SymbolWhat it isComes fromHow to get itTypical range
Wtotal vertical weight of wall + retained soil on heel (lb/ft)Another equationArea of the slice, wedge or wall section from the cross-section geometry × unit weight γ (from lab tests).project-specific
δbasefriction angle at base (degrees)Lab test (or fraction of φ')Interface direct shear (ASTM D5321); otherwise δ = 0.6–1.0 φ' depending on the surface (steel, concrete, geosynthetic).0.6–1.0 φ' · by USCS group
cbasebase adhesion (psf)Lab testEffective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more.0–300 psf · by USCS group
Bbase width (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
PAtotaltotal active force including surcharge (lb/ft)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
evoid ratio = B/2 − ( ΣM_resisting − ΣM_overturning ) / ΣV (ft)Another equatione = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435).sands 0.35–0.85, clays 0.5–2.0 · by USCS group
Shored MSE Wall System — Generic Cross-Section
Shored MSE Wall System — Generic Cross-Section
Soil nail load test
Soil nail load test
7.1.4.2 Cantilever Walls

Cantilever walls use a reinforced concrete stem and footing to resist overturning. The critical design section is at the base of the stem. Retained heights of 10–25 ft are typical.

Stem base moment (per foot of wall):

M_stem = (K_A × γ × H³/6) + (K_A × q_design × H²/2) (ft·lb/ft)

Minimum embedment depth for adequate passive resistance:

d_min is determined by setting FS_sliding ≥ 1.5 with the contribution of passive resistance over the embedded depth of the footing toe.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
7.1.4.3 Mechanically Stabilized Earth (MSE) Walls

MSE walls use reinforced fill to develop internal stability. They are commonly preferred for retained heights of 10–40 ft where ROW permits adequate fill width. MSE walls are commonly designed to AASHTO LRFD Bridge Design Specifications in addition to AREMA Chapter 8.

Soil-nailed shoring wall of a shored MSE wall project under construction in Colorado
Photo 7.1.4-1. Soil-nailed shoring wall of a shored MSE wall project in Colorado, under construction. (Photo courtesy of Colorado DOT.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Completed shored MSE wall with facing, Colorado
Photo 7.1.4-2. The same shored MSE wall project, complete with facing. (Photo courtesy of Colorado DOT.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Generic cross section of an SMSE wall system
Photo 7.1.4-3. Generic cross section of an SMSE wall system, showing the shoring wall and MSE wall components. (Figure from Morrison et al., 2006.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Installation of ground anchors to stabilize the Mississippi loess at Natchez Bluff
Photo 7.1.4-4. Installation of ground anchors to stabilize the Mississippi loess, Natchez Bluff. (Photograph by Kenneth Bergeron; from Fairweather, 1997.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Typical cross section of the soil nail and MSE wall used at US Highway 26-89
Photo 7.1.4-5. Typical cross section of the soil nail and MSE wall system used at US Highway 26-89. (Turner and Jensen, 2005; with permission from ASCE.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

Internal stability checks include:

  • Tensile stress in reinforcement: T_max = σ_h × S_v × S_h (lb) where S_v and S_h are vertical and horizontal reinforcement spacing (ft)
  • Reinforcement pullout: F_pullout = f × α × σ_v' × L_e × R_c × b* (lb) where L_e is the embedment length beyond the failure plane

External stability checks (sliding, overturning, bearing) use the MSE mass as an equivalent gravity wall.

Owner railroads may require a minimum cover of unreinforced structural fill between the top reinforcement layer and the ballast for MSE walls next to live track; confirm it.

7.1.4.4 Soldier Pile and Lagging Walls

Soldier pile walls use steel H-piles driven or drilled at 6–8 ft spacing with timber lagging. They are commonly used for temporary shoring during cut construction and for permanent retained cuts in urban railroad corridors where MSE fill width is unavailable.

Retaining Wall Construction
Retaining Wall Construction

Required embedment depth below excavation for cantilever soldier piles (simplified method):

Struts in Deep Excavation
Struts in Deep Excavation

(1/6) × K_p × γ × d³ = P_A × (ȳ + d),  per foot of wall, taking moments about the pile tip; ȳ = height of P_A above the excavation level. For discrete soldier piles, apply the passive resistance over an effective width of about 2–3 pile widths.

Solve iteratively for d; common practice increases d by 20–40% for design.

Size timber lagging for the span and soil type (FHWA GEC 4).

7.1.4.5 Sheet Pile Walls

Sheet pile walls (steel) are used for waterfront structures, scour protection, and temporary cofferdams. Free-earth support method for cantilever sheet piles:

Figure 7.1-17. Sheet piling protecting track along a riverbank.
Figure 7.1-17. Sheet piling protecting track along a riverbank.

d_theoretical is determined by moment equilibrium; common practice increases d_theoretical by 20–40% (USACE instead factors the passive strength; see the box below).

Anchored sheet pile walls use tie rods to reduce embedment depth and moment demand. The anchor force:

T_A = P_A − P_P (horizontal force equilibrium, free-earth support)

Owner railroads may require coated or encapsulated steel sheet piles for permanent waterfront applications where tidal or chemically aggressive conditions exist.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
γtotal (moist) unit weightLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
7.1.4.6 Soil Nail Walls

Soil nail walls are constructed top-down and are well suited to cuts in stiff clays, dense sands, and weathered rock. Nail design:

T_design = σ_h × S_v × S_h / FS_nail (lb)

Pullout resistance per unit length: Q_u = π × d_borehole × q_s (lb/ft) where q_s is the unit skin friction (psf)

FHWA GEC 7 (FHWA-NHI-14-007, 2015) recommends a global stability FS of 1.5 for permanent soil nail walls. AREMA Chapter 1 (Section 2.3.3) lists soil nail walls among slope repair methods and says they must be designed by an experienced engineer.

Supplemental reference

Micropile and soil-nail “A-walls” built from the track

Where a ballast shoulder or fill slope has slumped away from the ties and there is no room or time for a conventional wall, a micropile–tieback facing can be built from the embankment crest within track windows. Two projects in the AREMA Committee 1 files, both by GeoStabilization International (2018), show the arrangement:

Completed shored MSE wall with facing, Colorado
Completed shored MSE wall with facing, Colorado
  • A Class I railroad, Illinois (shoulder repair, 130 LF): Class I railroad cleared and excavated the failed shoulder and handled train protection. The contractor installed self-drilling hollow-bar micropiles (about 30 ft long, 2 ft spacing) at the outer edge of the shoulder and self-drilling soil nails (about 30 ft long, 4 ft spacing), drilled back beneath the track at 20–45° below horizontal depending on obstructions. A 12-in. reinforced shotcrete facing (two layers of 4×4–W2.9 welded wire fabric, No. 4 walers, 8×8×3/8-in. nail plates) tied the heads together, with one micropile per flank returning into the embankment. Weep holes (1½–2 in. PVC) were placed at 10 ft centers. New ballast was then placed behind the facing to restore the section (Figures 16-S1 and 16-S2). Nail grout was neat Type I/II/III cement at w/c 0.50–0.60.
  • Class I railroad Yard, Virginia (culvert headwall): a failing timber lagging wall over a culvert headwall beside the track was replaced by a micropile cap beam on micropiles up to 30 ft long battered about 40° from vertical, with soil nails up to 30 ft long at 30° ± 5°.
Soil Nailing with Shotcrete Facing
Soil Nailing with Shotcrete Facing
Drilling a soil nail hole
Drilling a soil nail hole
Soil Nail Retaining Wall
Soil Nail Retaining Wall
US 26/89 Typical Section — Soil Nail / MSE Wall
US 26/89 Typical Section — Soil Nail / MSE Wall
Failed ballast shoulder before repair, Class I railroad line in Illinois.
Supplemental Figure 16-S1. Failed ballast shoulder before repair, Class I railroad line in Illinois. Source: GeoStabilization International (2018). Micropile Tieback Railroad Shoulder Repair, Class I railroad located in Illinois — drawings and construction photographs. AREMA Committee 1 files.
Figure 7.1-21. Soil-nailed shotcrete face with bearing plates.
Figure 7.1-21. Soil-nailed shotcrete face with bearing plates.

Why micropiles fit railroad sites (SHRP2): they can be drilled through any ground, including boulders, rubble fill and old ballast, at any angle, with small rigs, low noise and little spoil (low-headroom rigs work under 10 ft clearance). Capacity comes from grout-to-ground bond (toe resistance neglected), so tension and compression capacities are about equal. At least about 40% of the load is carried by the steel. Capacities commonly exceed 200 tons in soil and 500 tons in rock, and most are under 100 ft long. Limitations: high slenderness (check buckling in very soft or liquefiable soil), and the method depends on contractor drilling and grouting skill, so load testing is essential.

Composite gabion walls (gabion facing combined with tiebacks, soil nails, reinforced concrete beams or drilled shafts) are marketed on the same principle — less excavation behind the face than a gravity gabion or cantilever wall — which matters when the excavation would otherwise undermine the track.

Retaining Wall vs Gabion Wall vs Toe Wall
Retaining Wall vs Gabion Wall vs Toe Wall
Gabion Retaining Wall
Gabion Retaining Wall
Shotcreting the wall face
Shotcreting the wall face

Source: GeoStabilization International (2018). Micropile Tieback Railroad Shoulder Repair, Class I railroad located in Illinois — drawings and construction photographs. AREMA Committee 1 files · GeoStabilization International (2018). Class I railroad Yard Culvert Wall — Micropile Cap (drawings). AREMA Committee 1 files · SHRP2 R02 / GeoTechTools (2012). Micro-piles — fact sheet

MSE Wall Construction — MnDOT Crosstown Project
MSE Wall Construction — MnDOT Crosstown Project
Completed reinforced-shotcrete micropile/soil-nail facing along the track shoulder, before ballast was restored behind it.
Supplemental Figure 16-S2. Completed reinforced-shotcrete micropile/soil-nail facing along the track shoulder, before ballast was restored behind it. Source: GeoStabilization International (2018). Micropile Tieback Railroad Shoulder Repair, Class I railroad located in Illinois — drawings and construction photographs. AREMA Committee 1 files.
Supplemental reference

How USACE applies safety factors to sheet pile embedment

Section 7.1.4.5 increases the theoretical embedment by 1.3. EM 1110-2-2504 takes a different approach: it applies a strength-reduction factor to the passive side only (tan φeff = tan φ/FSP; ceff = c/FSP), uses best estimates elsewhere, and usually takes FSA = 1 unless wall deformation must be limited. It then solves directly for the penetration. The two approaches do not give the same depth; do not apply both.

Table 16-S1. Minimum FS on passive pressure for penetration depth (EM 1110-2-2504, Table 5-1, retaining walls)

Loading caseFine-grained soilsFree-draining soils
Usual2.00 Q-case; 1.50 S-case1.50 S-case
Unusual1.75 Q-case; 1.25 S-case1.25 S-case
Extreme1.50 Q-case; 1.10 S-case1.10 S-case

Other USACE points relevant to track walls: in medium-dense or denser sand, the active state develops at about 0.1–0.2% of wall height (about ¼–½ in. for a 20-ft wall), while full passive needs about 2–4% (roughly 5–10 in.). This is why passive resistance should be discounted where track settlement is critical. For anchored walls, the Free Earth method gives stable walls with less penetration than Fixed Earth but overpredicts moment (use Rowe’s moment reduction). Initially place the anchor at ¼–⅓ of the exposed height below the top. Grouted anchors must lie entirely outside the active wedge and develop the tie-rod yield strength. Proof-test every anchor to 110% of required resistance and performance-test at least two to 150% of design capacity.

Source: U.S. Army Corps of Engineers (1994). Design of Sheet Pile Walls. EM 1110-2-2504

Supplemental reference

Walls and revetments protecting track along shorelines

Lines along coasts, lakes and large rivers often depend on revetments, seawalls or bulkheads. EM 1110-2-1614 sizes armor stone by Hudson’s equation:

W = γrH3 / [KD(γr/γw − 1)3 cot θ]

where W is the armor unit weight (W50 for graded riprap) and H is the design wave height. Suggested KD for breaking waves: rough angular quarrystone, two layers, random 2.0 (1.2 for smooth rounded); graded riprap 2.2 (slopes 2.0–6.0 cot θ). A single layer of randomly placed rough stone is “do not use”, and graded riprap is not recommended where waves exceed 5 ft. For irregular waves on dumped riprap, the zero-damage stability number is Nsz = 1.14 cot1/6 θ with Hs.

  • Riprap gradation (relative to W50 min): W100 max ≤ 4 W50 min (the largest economically quarried size); W100 min ≥ 2 W50 min; W50 max ≈ 1.5 W50 min; W15 min ≈ 0.4 W50 min; W15 max set by filter criteria (EM 1110-2-1901; see the filter table in Chapter 1.9) and slightly above W50 min. Graded riprap thickness is two diameters of the W50 min stone.
  • A revetment is armor + filter + toe protection. Toe scour and slope instability from poor drainage are the usual failure modes, and minimum expected water levels control toe scour. Bulkheads and seawalls retaining the track fill should be checked for low water with the fill saturated, as well as for wave overtopping and loss of fill through joints.

Source: U.S. Army Corps of Engineers (1995). Design of Coastal Revetments, Seawalls, and Bulkheads. EM 1110-2-1614

Reinforced soil vs. conventional walls on railway fills

For very tall embankment sides, Profillidis shows either a conventional retaining wall at the toe or reinforced soil: an assembly of good-quality granular backfill, metallic reinforcing bars or strips anchored in the fill, and a concrete facing. Reinforced soil is recommended particularly on poor and very poor subgrades (S1, S0) and allows very steep or vertical faces. A French cost comparison for railway projects found reinforced soil economically and technically advantageous over a retaining wall, especially at heights of 10–40 ft (Figure 7.1-13).

Soil nail load test
Photo 7.1.4-6. Soil nail load test. (From FHWA.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Drilling a nail hole
Photo 7.1.4-7. Drilling a nail hole. (From FHWA.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Grouting a nail hole
Photo 7.1.4-8. Grouting a nail hole. (From FHWA.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Shotcreting the face
Photo 7.1.4-9. Shotcreting the face. (From FHWA.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Schematic diagram of MSE wall principal elements
Photo 7.1.4-10. Mechanically stabilized earth mass — principal elements. (Figure from Berg et al. (2009).)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
MSE wall construction on MnDOT Crosstown Project, 2008
Photo 7.1.4-11. MSE wall construction on MnDOT Crosstown Project, 2008. Photograph courtesy of Ryan Berg.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
SeaTac Airport runway extension MSE wall, tiered face with workers for scale
Photo 7.1.4-12. SeaTac Airport runway extension MSE wall. Photograph courtesy of Tony Allen.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Anchored Retaining Wall
Anchored Retaining Wall
Figure 7.1-11. Retaining wall supporting a very tall embankment side. Profillidis Fig. 9.16.
Figure 7.1-11. Retaining wall supporting a very tall embankment side. Profillidis Fig. 9.16.
Figure 7.1-12. Reinforced-soil technique: concrete facing panels, metallic bars and good-quality backfill. Profillidis Fig. 9.17.
Figure 7.1-12. Reinforced-soil technique: concrete facing panels, metallic bars and good-quality backfill. Profillidis Fig. 9.17.
Figure 7.1-13. Relative construction cost of retaining wall and reinforced soil vs. height, French railway projects. Profillidis Fig. 9.18.
Figure 7.1-13. Relative construction cost of retaining wall and reinforced soil vs. height, French railway projects. Profillidis Fig. 9.18.

Caution for electrified lines. The book states that metallic-reinforced soil cannot be used on electrified railways, because return current corrodes the metal reinforcement and can lead to failure. Where a reinforced-soil wall is proposed near an electrified line or a DC transit system, address stray-current corrosion explicitly. Options include non-metallic (geosynthetic) reinforcement or a corrosion design that accounts for stray current.

After Profillidis (2014), §9.12.2, §9.13, Figs. 9.16–9.18. Full reference under Supplemental References.

Walls used to stabilize track: field practice

Use a wall when a berm cannot be placed. Driven walls isolate the track from shallow-to-medium movement below but are not efficient against deep-seated failures. H-pile walls along the shoulder use piles about 4 ft apart. If movement continues, add a whaler so the piles act together; if it still moves, add soil anchors or tie back to piles on the far side of the grade. Rule of thumb: to hold 4 ft of unstable ground, embed at least 8 ft below the slip plane. At one Atlantic Canada site, a tidal bank retrogressing toward the track was treated with a temporary riprap toe berm and then a design combining 55-ft H-piles with a 40-ft sheet-pile wall.

Ground Anchor Installation — Natchez Bluff
Ground Anchor Installation — Natchez Bluff
Figure 7.1-14. Piles must pass fully through the shear plane to hold.
Figure 7.1-14. Piles must pass fully through the shear plane to hold.
Figure 7.1-15. H-piles driven along the shoulder.
Figure 7.1-15. H-piles driven along the shoulder.
Figure 7.1-16. Driving an H-pile on a prairie main line.
Figure 7.1-16. Driving an H-pile on a prairie main line.
  • Sheet piles: interlocking steel sections, also cutting groundwater inflow; can be anchored.
  • Soldier pile and lagging / Berlin wall: H-piles with timber, steel or precast lagging; heavier anchored versions for active slides.
  • Gravity walls: precast K-blocks (typically three high, each 5 ft × 2.5 ft × 2.5 ft) on and behind geotextile, which can be raised over time; gabions and geosynthetic-reinforced walls where space or budget is tight.
  • Soil nailing: built top-down in 3–6 ft lifts with near-horizontal grouted bars at 3–6 ft centers (commonly about 20 ft long), drainage and shotcrete facing. Nails must extend beyond the slip surface.
Precast T-Wall installation
Precast T-Wall installation
Sheet Pile Retaining Wall
Sheet Pile Retaining Wall
Figure 7.1-18. Berlin wall with timber lagging approaching a trestle.
Figure 7.1-18. Berlin wall with timber lagging approaching a trestle.
Figure 7.1-19. K-block wall with geotextile beneath and behind.
Figure 7.1-19. K-block wall with geotextile beneath and behind.
Figure 7.1-20. Finished K-block wall along a river.
Figure 7.1-20. Finished K-block wall along a river.

After Geotechnology for Railroaders Program, Module 6.1; §05–07, §10. Full reference under Supplemental References.

Project management · Cretu et al. (2011)

Integrating Value Engineering with Risk Response: Function Statements

Cretu et al. argue that risk assessment and value engineering (VE) belong together, because risk analysis characterizes the problems and VE generates the solutions. VE, also called value methodology, is a facilitated multidiscipline study built on function analysis. It asks what an element must do rather than what it is, and that is what separates it from simple cost cutting. For each high or moderate risk they add a function-based step to response planning:

MSE Wall — Principal Elements
MSE Wall — Principal Elements
  1. Identify the risk object, which is the noun of the project function that the risk affects, stated in a word or two.
  2. Write response functions as verb–noun pairs. The verb comes from the response strategy: accept, avoid, mitigate or transfer for threats, and enhance, exploit or share for opportunities.
  3. Brainstorm ideas under each function statement, aiming for quantity before judgment.
  4. Screen each idea as a green check (develop it), a yellow exclamation (keep it as a fallback) or a red X (reject it).
  5. Develop action plans for the green-check ideas, each with an owner and specific steps.
Template for converting a risk description and its object into a threat or opportunity response function statement built from a response verb and an object noun.
Figure 16-PM1. Template for converting a risk description and its object into a threat or opportunity response function statement built from a response verb and an object noun. Source: Cretu et al. (2011), Figure 5.4.

Reducing a long risk narrative to a short function statement keeps the team focused on the thing that can actually be managed. It also tends to produce several candidate solutions instead of one.

For railroad work: Wall selection is a natural application. Suppose the risk is “soft clay below the planned cantilever wall may cause excessive rotation under E-80 surcharge.” The risk object is the foundation. The response functions might be “avoid foundation” (a lightweight-fill embankment or a pile-supported wall), “mitigate settlement” (ground improvement or preloading where a track window allows), “transfer design” (a performance-specified proprietary system) and “accept movement” (a flexible MSE or gabion wall with a resurfacing allowance). Screening these against track-outage limits, construction access from the right-of-way, and the railroad’s preferences for wall type gives a short list. The short list can then be ranked by weighted paired-comparison scoring and compared on a whole-life cost basis.

Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 157–162. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

7.1.4.7 Soldier Pile Passive Resistance, Passive Softening and Anchor Fixed Length

Soldier piles and lagging are this manual's standard wall next to track. Below the excavation the piles act as discrete elements, not a continuous wall, and the passive resistance per pile is more than the plane-strain value over the pile width. UK guidance (CIRIA C580, summarised in Pickles, 2012, pp. 995–996) gives the ultimate net resistance per pile when the spacing s is more than three pile widths b.

Equation 7.1-6. Ultimate passive resistance of a discrete pile, per unit depth

Drained:  P = Kp b p′v  (z ≤ 1.5b),  P = Kp² b p′v  (z ≥ 1.5b)
Undrained:  P = (2 + 7z/3b) su b  (z ≤ 3b),  P = 9 su b  (z ≥ 3b)

Pickles (2012), Eqs. 64.5–64.8, after Barton (1982) and Fleming et al. (1994). Divide by s for resistance per foot of wall. Kp = (1 + sinφ′)/(1 − sinφ′); valid for Kp = 3.0 to 5.3 (30° ≤ φ′ ≤ 43°). z is depth below the excavation and p′v the effective overburden there. Vol. II prints “≤” in both depth limits; the second limit of each pair is evidently ≥, where the deeper expression takes over.

Full active pressure is assumed on the retained side. The Kp² form is close to the 3Kp rule (Broms) used in many U.S. guidelines at Kp = 3 and higher at larger Kp; follow the governing railroad shoring guideline where it prescribes a method (Section 7.1.17).

Softening of the passive zone in clay

Excavation unloads the clay in front of the wall; as negative pore pressures dissipate, the clay near the excavation base softens. Take the undrained strength as zero at the excavation level, rising to the design value at a depth L (Pickles, 2012, Eq. 64.4, p. 994):

Equation 7.1-7. Depth of softened clay below an excavation

L = √(12 cv t)

cv = coefficient of consolidation; t = time the excavation is open. Use L of about 1.6 ft (0.5 m) where no groundwater recharge is possible.

For example, with cv = 0.1 ft²/day, L is about 4.1 ft after two weeks and about 10 ft after three months, which can remove much of the passive resistance a short embedment relies on. Also allow for unplanned over-excavation in front of the wall: 10% of the retained height, up to about 1.6 ft (0.5 m), in Eurocode practice (Pickles, 2012, p. 985).

Ground anchor fixed length

Equation 7.1-8. Fixed anchor length from bond (skin friction)

Tult = π d L τult;   Tdesign = Tult/F;   in clay Tult = π d L α cu

Turner (2012), Eqs. 66.1–66.6, pp. 1017–1021. d = borehole diameter; L = fixed (bond) length; τ = grout–ground bond from load tests or published values; F = global factor (Vol. II recommends retaining the BS 8081 global factors).

Example 7.1-7: Passive resistance of a soldier pile in sand

Soldier piles in 2-ft drilled holes at 8-ft spacing support an excavation beside track. Below the excavation the soil is dense sand. Find the ultimate passive resistance per pile at 5 ft below the excavation and compare it with the 3Kp rule.

Sand: φ′ 34°, γ 120 pcfRetained soilExcavationz = 5 ftPp per pile per ft = ?Plan: b = 2 ft at s = 8 fts = 8 ftResistance per ft of wall = ?Givenb = 2 ft (drilled hole)s = 8 ft (s > 3b = 6 ft)φ′ = 34°; γ = 120 pcf (dry)z = 5 ft below excavationRequiredUltimate passive resistance per pile per foot of depthResistance per foot of wallBlack = given; red = required
Given and required for Example 7.1-7.

Given

VariableValueDescription
b2 ftPile (drilled hole) width
s8 ftPile spacing (s > 3b = 6 ft)
φ′34°Sand below excavation
γ120 pcfUnit weight (above groundwater)
z5 ftDepth below excavation

Required

  • Ultimate passive resistance per pile per foot of depth
  • Resistance per foot of wall

Equations

  1. EP-02: Kp = (1 + sinφ′)/(1 − sinφ′)
  2. Eq. 7.1-6: P = Kp² b p′v for z ≥ 1.5b

Steps

Step 1 · Kp
(1 + 0.559)/(1 − 0.559)
3.54 (within 3.0 to 5.3)
↓
Step 2 · Which form
z = 5 ft ≥ 1.5b = 3 ft
Use Kp²
↓
Step 3 · p′v
120 × 5
600 psf
↓
Step 4 · P per pile
3.54² × 2 × 600 = 12.51 × 1,200
15,000 lb/ft of depth
Spot check: 3Kp rule: 3 × 3.54 × 2 × 600 = 12,700 lb/ft, about 15% lower.
↓
Step 5 · Per foot of wall
15,000 / 8
1,880 lb/ft per ft of depth
↓
Solution
Ultimate passive resistance about 15,000 lb per foot of depth per pile at 5 ft (1,880 lb/ft per foot of wall).

Solution

This is an ultimate value; apply the factor of safety or the reduced passive coefficient that the governing railroad shoring guideline requires before using it to find embedment.

In clay, replace this with the undrained form and reduce the strength near the excavation base by the softened depth L.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • Pickles, A. (2012). Geotechnical design of retaining walls. Chapter 64 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 981–1000Find source ↗Library entry
  • Turner, M. (2012). Geotechnical design of ground anchors. Chapter 66 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1011–1030Find source ↗Library entry