7.1.17 Temporary Shoring Next to an Operating Track

Retaining structures are among the most consequential geotechnical elements in railroad capital programs.
Authors: Daniel P. Colwell and Mario Ruel
7.1.17 Temporary Shoring Next to an Operating Track

Excavations for bridge footings, culverts, utilities and grade separations often sit within the zone where train loads push on the excavation support. Two Class I railroads publish joint guidelines for temporary shoring that supplement AREMA. They cover clearances, the Cooper E80 lateral load, deflection limits, embedment and allowable stresses, and what must be submitted. Consistent with Chapter 7.1, soldier piles with lagging and sheet piles are the usual systems; trench boxes are not accepted where railroad surcharge is present, and tiebacks under the track are discouraged because they obstruct future utilities and must be removed.

7.1.17.1 Loads and criteria

Equation 7.1-3. E80 lateral pressure, resultant and point of action (Boussinesq strip)

Ps = (2q/π)(β − sinβ cos2α)   R = 2qHβ/π   z = [H²β − bH + X2²(π/2 − θ2) − X1²(π/2 − θ1)]/(2Hβ)

q = 80,000/(5 × b) psf; X1,2 = S ∓ b/2; θ = arctan(X/H); β = θ2 − θ1; α = (θ1 + θ2)/2; moment at depth H = R(H − z).

Table 7.1-6. Shoring criteria in the joint guidelines
ItemRequirement
ClearanceNo excavation closer than 12 ft to track centerline; otherwise shift or remove the track
Deflection, shoring 12 to 18 ft from centerline3/8 in. shoring; 1/4 in. rail (horizontal or vertical)
Deflection, shoring 18 to 24 ft from centerline1/2 in. shoring; 1/4 in. rail
EmbedmentEquilibrium depth × about 1.3 for temporary shoring; anchored systems at least 1.5 times calculated embedment
Cantilever sheet pilesAt least 12 ft from centerline; granular soils or stiff clays only
Other loads2 ft spoil surcharge; track 200 lb/ft; ballast 120 pcf; centrifugal force where curvature exceeds 3°
Allowable stressesSteel 0.55Fy bending, 0.35Fy shear; sheet piles 2/3 Fy; concrete f'c/3; anchor rods Fy/2; no temporary-load increase
OperationsFlagman for work within 25 ft of centerline; monitor top of rail and alignment throughout
SOIL SCREW installation equipment
Photo 7.1.17-1. SOIL SCREW® installation equipment. (From abchance.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
SOIL SCREW being installed
Photo 7.1.17-2. SOIL SCREW® being installed. (From abchance.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Screw-in soil nail wall face before shotcrete
Photo 7.1.17-3. Screw-in soil nail wall face before shotcrete. (From abchance.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Shotcrete application
Photo 7.1.17-4. Shotcrete application. (From abchance.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Table 7.1-7. AREMA backfill types and properties used when tests are not justified (Tables 8-5-1 and 8-5-2)
TypeDescriptionUnit weight (pcf)φ
1Clean sand, gravel or broken stone10533 to 42° (38° broken stone)
2Coarse-grained with silt11030°
3Fine silty sand; clayey granular; residual soil with stones12528°
4Soft clay, organic silt, soft silty clay (engineer's approval)1000 (c = 0)
5Medium or stiff clay kept dry (engineer's approval)1200 (c = 240 psf)

7.1.17.2 Worked example: the guideline sample problem

Table 7.1-8. S = 12 ft, H = 6 ft, q = 1,778 psf (b = 9 ft); type 2 soil and 2 ft spoil (calculator output)
ResultValue
E80 pressure at 6 ft558 psf
E80 resultant / moment at 6 ft2,214 lb/ft / 4,944 ft-lb/ft
Total force with earth and spoil3,314 lb/ft
Total moment at excavation base7,584 ft-lb/ft
Check against the guideline chart: S = 16 ft, H = 10 ft411 psf; 2,964 lb/ft; 11,385 ft-lb/ft

The E80 values reproduce the guideline sample (558 psf, 2,214 lb/ft, z = 3.77 ft, 4,940 ft-lb/ft) and Chart A (411 psf, 2,964 lb/ft, 11,385 ft-lb/ft at S = 16 ft, H = 10 ft).

Note that the train load contributes most of the force at this shallow depth and that the pressure peaks a few feet down rather than at the top. The deflection limit of 3/8 in. at 12 ft from the track usually governs the soldier pile size more than stress does.

Open the temporary shoring calculator →
E80 Boussinesq lateral pressure, resultant and moment, active earth and spoil pressure, and the clearance, deflection and embedment criteria for shoring next to track.

7.1.17.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • Joint guidelines for temporary shoring of two Class I railroads (2004), Carriers folder: criteria, sample problem and Chart A.Find source ↗
  • A Class I railroad's pipeline occupancy specification (2018), Carriers folder: E80 strip surcharge (q = 1,882 psf with 8.5 ft ties).Find source ↗
  • AREMA conference papers: retaining wall design for railroad infrastructure (2014); emergency and non-emergency earth retaining with pressed-in sheet piles (2019).Find source ↗
  • AREMA Committee 1 files on micropile retaining walls and tieback shoulder repairs, AREMA folder.Find source ↗