7.1.12 Practical Recommendations

Retaining structures are among the most consequential geotechnical elements in railroad capital programs.
Authors: Daniel P. Colwell and Mario Ruel
7.1.12 Practical Recommendations
  1. Check seismic loading where it is required. Owner railroads and codes commonly require it in SDC C and D; confirm the requirement when the work is scoped.
  2. Do not use computed K_P for sliding resistance without a reduction factor. Full Rankine passive resistance is only mobilized at displacements of about 2–6% of wall height (dense to loose sand), far beyond railroad serviceability tolerances. Use 50% of K_P passive resistance in sliding checks, or mobilize passive through a properly designed shear key.
  3. Specify drainage as a contract requirement, not a recommendation. Owner railroads' engineering standards treat wall drainage as mandatory. Include perforated pipe, granular blanket, and weep holes in the Geotechnical Special Provisions (Appendix C). Make failing to install drainage a deficiency that triggers contractor correction at no cost to the railroad.
  4. Verify backfill compaction limits near walls. Heavy compaction equipment within 3 ft of a wall can generate earth pressures well above active pressure. Specify compaction equipment exclusion zones and hand-compaction zones in GSP. Confirm these exclusion zones with the owner railroad.
  5. Perform global stability analysis for all walls > 10 ft. Bearing capacity and sliding checks alone are not sufficient. A wall that passes sliding and bearing checks can still fail through a weak layer beneath the footing.
  6. For MSE walls supporting live track, confirm the owner's minimum cover requirement. Owner railroads may require a minimum thickness of unreinforced fill between the top reinforcement layer and the ballast. Confirm this geometry is met before finalizing wall face location and top of reinforcement elevation.
  7. Document wall deflection tolerance in the GDR. Railroad track geometry tolerances (FRA 49 CFR Part 213) define the acceptable deformation limits, not structural failure limits. A cantilever wall that deflects 1.5 in. at the top may be structurally fine but will cause gage or surface defects. State deflection limits explicitly in the geotechnical design report and coordinate with the track engineer.

Case study: 7.1.16.2 Design detailing and analysis input: short case notes (Look 2023), in §16.16 Case Studies.

Project management · Jacob and Müller (2017)

Estimating a Tied-Back Soldier Pile and Lagging Wall per Square Foot of Face

Jacob and Müller price a temporary anchored soldier pile wall by costing one complete bay, meaning one soldier pile and the lagging to the next pile. That bay cost is then spread over the exposed (visible) face area, which is the pay unit in their bill of quantities.

Section through the example anchored soldier pile wall, showing excavation depth, embedment, inclined tieback and soil layering used for the bay cost build-up (SI units in the original).
Figure 16-PM2. Section through the example anchored soldier pile wall, showing excavation depth, embedment, inclined tieback and soil layering used for the bay cost build-up (SI units in the original). Source: Jacob and Müller (2017), Figure 2.34.

Example geometry, converted to US units:

  • 17.4 ft clear excavation height and about 6.6 ft of embedment, for 24 ft of drilled hole per pile;
  • soldier piles at 9.8 ft centers, made of paired channels weighing about 47 lb/ft;
  • one row of tiebacks 34 ft long at 30°;
  • 4-in timber lagging;
  • a uniform surcharge of about 210 psf.

The bay cost is built from:

  • drilling, at a fraction of the drill rig’s day rate (24 ft of hole at about 197 ft/day);
  • pile extraction afterward, using a crane crew day rate at about 328 ft/day;
  • lean concrete at the toe and a sand-concrete fill above;
  • soldier steel per ton, including attrition, three months’ rent, cutting and round-trip trucking;
  • tiebacks per foot;
  • lagging per square foot, bought from a subcontractor.

Of the bay cost, lagging was about 28%, anchors about 25%, drilling about 25% and extraction about 8%. The bay cost divided by (17.4 ft × 9.8 ft) gives the cost per square foot of face. A 25% markup was applied.

The authors contrast this with sheet piling. Sheet piling is paid on the actual driven wall area rather than the exposed face. When it stays in place permanently, the full material cost is included.

For railroad work: Temporary soldier pile walls for culvert replacements, track-adjacent excavations and shoofly construction are often the largest cost of temporary works. A bay-based build-up shows the railroad how the price depends on several things:

  • the Cooper E-80 surcharge and the distance to track centerline, which drive pile section, embedment and the need for tiebacks;
  • whether tiebacks can be installed at all under the track or within the right-of-way;
  • rental duration, which is tied to the construction schedule and window availability;
  • whether piles are pulled or left in place.

The pay unit (exposed face, total wall area or lump sum) must be stated clearly in the special provision, together with who designs the system and the movement-monitoring limits.

Source: Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn, pp. 192–195. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Supplemental reference · Goswami (2015), Ch. 208

Typical Retaining Wall Damage, Inspection, and Rating Backfill

Damage patterns to look for during inspection:

  • Tilting. A tilt of about 10° can raise the lateral force on the wall by roughly 20%, so tilt tends to worsen once it starts.
  • Shifting, often from repeated freeze–thaw of wet backfill.
  • Bowing from excess lateral pressure, usually water building up behind the wall.
  • Water signs: green growth, efflorescence, mineral deposits and rust staining from ties.

Inspection. Typical codes require special inspection of walls with more than 8 ft of retained height, and of 4- to 8-ft walls that carry a surcharge or a slope steeper than 3H:1V. Periodic inspection should look for loss of backfill, open joints and movement; voids from lost backfill fill with water and raise the pressure, so fill them promptly. Walls built against freshly cut slopes may lose strength as the cut material softens with time, so design for long-term strength.

Rating granular backfill. Brown’s suitability number, developed to rate backfill for vibroflotation, compares how readily granular materials densify:

SN = 1.7 √( 3/D502 + 1/D202 + 1/D102 ) with D in mm, or SN = 0.067 √( 3/D502 + 1/D202 + 1/D102 ) with D in in.

Ratings: 0–10 excellent, 10–20 good, 20–30 fair, 30–50 poor, over 50 unsuitable.

For railroad work: Add tilt, bowing, water staining and backfill loss to the wall entries of the earthworks inventory (Chapter 7.4) and record them as defects in the risk rating (Chapter 3.8). Railroad walls carry train surcharge, so the 4- to 8-ft walls next to track normally fall in the special-inspection group. The suitability number is a quick way to compare candidate free-draining backfills and stone column or vibro backfill (Chapter 7.2, Section 7.2.4).

Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 208, Retaining Walls. Full reference under Supplemental References.