Trenches for pipes and culverts across or along the track, and excavations for pits, vaults and foundations, are often supported by sheeting or soldier piles with internal struts or rakers. Because the bracing is installed from the top down as the excavation deepens, the wall cannot yield enough to develop the active state near the top, and the earth pressure is not triangular. Terzaghi and Peck measured strut loads in braced cuts and drew envelopes (“apparent pressure diagrams”) that bound them. The envelopes are not true pressure distributions: they are a design device for strut loads, wales and the spans between struts.
Equation 7.1-11. Apparent earth pressure envelopes (Peck, 1969)
H = excavation depth; m = 1.0 except where soft clay continues below the base (m = 0.4). Add surcharge pressure (uniform and the E80 strip of Section 7.1.17) and water pressure below the water table.
Strut loads are found by treating the wall as hinged at each strut below the top one, so that each span is a simple beam between struts. The cantilever above the top strut is carried by the top strut, and the span below the lowest strut is supported by the soil at the base. The strut load is the reaction per foot of wall times the horizontal strut spacing, and the wale moment is about P·s/10 for a wale continuous over several struts.
A 20-ft trench for a culvert extension next to a Class I railroad located in Texas is supported by sheeting with three levels of struts at 4, 11 and 17 ft, spaced 12 ft apart horizontally. The soil is medium dense sand above the water table, and the contractor’s equipment surcharge is 250 psf.
| Variable | Value | Description |
|---|---|---|
| H | 20 ft | Excavation depth |
| Struts | 4, 11 and 17 ft; s = 12 ft | Depth; horizontal spacing |
| Soil | γ = 120 pcf, φ′ = 32° | Sand |
| q | 250 psf, Kq = 0.33 | Uniform surcharge |
Design the top struts for about 51 kips, the middle for 44 kips and the bottom for 30 kips, and the top wale for about 61 kip-ft.
If the trench is within the track influence zone, add the E80 strip pressure (enter the track distance in the calculator); it adds most load to the upper struts. Preload the struts to about half their design load to limit movement under the track, and monitor the track surface while the trench is open.
Open the braced excavation calculator →
Apparent pressure envelopes for sand, soft clay and stiff clay with uniform and E80 surcharges, strut loads at each level by the hinge method, the base reaction and the wale moment.
The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.
Bottom heave. In soft to medium clay, the weight of the soil beside a braced cut can push the clay up into the bottom of the excavation. Bjerrum and Eide give:
FS = cu Nc / (γ H + q) ≥ 1.5
cu = undrained strength of the clay below the base (psf); Nc = bearing capacity factor that depends on the cut depth to width and length to width (about 5.1 for a long shallow cut, rising toward 9 for deep, square cuts); γ = unit weight (pcf); H = cut depth (ft); q = surcharge beside the cut (psf). If FS is too low, drive the sheeting deeper into firmer soil or reduce the surcharge.
Secant and tangent pile walls are rows of drilled shafts that touch (tangent) or overlap (secant). Secant walls cut off groundwater; tangent walls do not.
OSHA sloping (29 CFR 1926 Subpart P). For excavations less than 20 ft deep without a designed protective system, the maximum allowable slope depends on soil type:
| Type | Unconfined compressive strength | Maximum slope (H:V) |
|---|---|---|
| Stable rock | — | Vertical |
| A | 1.5 tsf or more | ¾:1 |
| B | 0.5 to 1.5 tsf | 1:1 |
| C | 0.5 tsf or less; granular, submerged or seeping soil | 1½:1 |
Deeper excavations, and any protective system outside the standard tables, must be designed by a registered professional engineer.
For railroad work: Soil that is fissured or subject to vibration from heavy traffic or similar sources cannot be classed as Type A, so excavations beside operating track are normally Type B or C and need flatter slopes or shoring designed for the train surcharge (Section 7.1.17). Check bottom heave for any braced cut in soft clay beside track, where the surcharge q includes the track and train load.
Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 209 (Support of Excavation) and Chapter 507 (Excavations). Full reference under Supplemental References.