Retaining structures are among the most consequential geotechnical elements in railroad capital programs.
Authors: Daniel P. Colwell and Mario Ruel
7.1.8 Client-Specific Requirements Summary
Table 7.1-2. Retaining Wall Design Requirements
RailroadMin. FS SlideMin. FS OTWall FrictionSurchargeSeismic Req.Drain Req.PE Seal StateGoverning Std.
AREMA1.52.0δ = ⅔φ' (common)E-80 strip load (Section 7.1.3.1)SDC per codeMandatoryPer stateAREMA MRE Ch. 8

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.