This chapter covers existing railroad tunnels and their portals: tunnel types and their typical problems, inventory and inspection, lining defects, rock support checks in unlined sections, squeezing and swelling ground, portals, water and ice, clearance improvement for tall equipment, repair methods, monitoring and risk rating. Design of new tunnels is outside its scope.
Most railroad tunnels in North America were driven between the 1850s and the 1930s. They were built for smaller equipment, often by hand or with early drilling and black powder, and lined (if at all) with timber, brick, stone masonry or unreinforced concrete. Many are now more than a century old and carry heavier, taller and more frequent trains than they were designed for. This chapter is about keeping those tunnels safe and in service:
Design of new tunnels (excavation methods, NATM and TBM tunneling, support design for new openings) is outside the scope of this chapter. Settlement of track above a new tunnel driven beneath the railroad is covered in Chapter 6.2, Section 6.2.7. Blasting near track is covered in Chapter 5.3, Section 5.3.27.
For railroad work: A tunnel failure closes the line, often for weeks, and there may be no practical detour. Treat each tunnel as an asset with its own inspection record, risk rating and repair plan, and inspect it with the same care as a bridge. Keep the original construction records, later repair records and every inspection report together, because the history of a tunnel explains most of its defects.
The lining type, or lack of one, controls what can go wrong and how a tunnel should be inspected and repaired.
| Type | Where found | Typical problems | Notes |
|---|---|---|---|
| Unlined rock | Strong, massive rock (granite, gneiss, quartzite, massive sandstone and limestone) | Loose blocks and rockfall from the crown and walls; slaking of shale and mudstone layers; water and ice | Scaling and spot bolting are the usual maintenance. Weak beds within strong rock are the most common source of falls. |
| Timber-lined (sets and lagging) | Weaker or blocky rock in early tunnels | Decay, insect damage, fire, crushed or displaced sets, voids behind lagging | Many were later replaced or encased in concrete or shotcrete. Remaining timber is a fire and collapse hazard. |
| Brick or stone masonry arch | Soil, weak rock and portals of 19th-century tunnels | Lost mortar, ring separation, bulging, dropped stones, water through joints, freeze-thaw damage | Masonry arches carry load by compression; loss of shape or of mortar in joints reduces capacity. |
| Plain (unreinforced) concrete | Linings placed from about 1900 onward, often over timber or masonry | Cracking, spalling, cold-joint leakage, voids behind the lining, alkali-silica reaction, freeze-thaw near portals | Voids behind old linings are common where concrete was placed against timber or loose rock. |
| Reinforced concrete or shotcrete | Rehabilitation work and later tunnels | Corrosion of reinforcement where water and deicing salts reach it, delamination, drummy shotcrete | Check cover and chloride where leakage is heavy. |
| Steel liner plate or ribs | Repairs, short tunnels, portal extensions | Corrosion at the invert and where water drips | Section loss at the base of ribs is the usual weak point. |
Problems that apply to all types are water inflow and ice, clearance that is too small for modern equipment, drainage that has silted or frozen, and portals where the slopes above are unstable.
For railroad work: The type of lining often changes along a tunnel: rock in the middle, masonry or concrete near the portals and through weak zones. Record the lining type and its limits by station (or distance from a portal) in the inventory, because the inspection method, the defects to look for and the repair options change at each boundary.
The FHWA Highway and Rail Transit Tunnel Inspection Manual [S1] and the later Tunnel Operations, Maintenance, Inspection, and Evaluation (TOMIE) Manual [S2] set out the inventory, inspection and condition-rating practice now used for tunnels. The 2005 manual has since been superseded by the TOMIE Manual, which the National Tunnel Inspection Standards (23 CFR 650 Subpart E, 2015) incorporate by reference for highway tunnels on public roads. The standards do not apply to freight railroad tunnels, but their inspection intervals, element-by-element condition states and reporting of critical findings are a sound model for a railroad program. For railroad tunnels, the AREMA Manual for Railway Engineering covers design, maintenance and construction, and ventilation in Chapter 1, Part 8 [S8]. Railroads follow their own programs, but the same approach applies.
Laser scanning records the whole surface in 3D with images, so the data can be measured later and compared with the next scan. In rock tunnels it has been used for fracture mapping, locating water leakage, overbreak and underbreak, checking shotcrete thickness and monitoring deformation ([S4], Ch. 18). For railroad tunnels, a mobile scan from a track vehicle gives the clearance profile at close spacing along the whole tunnel in one track window.
Record each defect with its location (station, clock position or offset from centerline, height), type, size, and a photograph, and give it a condition rating. The FHWA manuals rate tunnel elements from 9 (new) to 0 (failed). GHRM uses the 1-to-5 risk scale of Chapter 3.8, and Table 6.6-6 in Section 6.6.11 maps tunnel defects to that scale.
For railroad work: Inspect from a work train or hi-rail vehicle with lights and a lift, under track protection, and allow enough window time to sound the lining and not only look at it. Mark each defect on the lining with a paint number and station so it can be found again. Re-scan after any reported change, and compare the scans to find movement that a visual inspection would miss.
The pattern of a defect usually shows its cause. Interpreting the pattern correctly decides whether a repair is cosmetic or structural.
| Defect | Likely cause | Significance |
|---|---|---|
| Longitudinal crack along the crown | Vertical ground load greater than the lining was built for; loss of support at the springlines; voids above the crown letting the arch deform | Structural. Check for flattening of the crown and for voids above it. Monitor crack width. |
| Longitudinal cracks at the springlines or walls, with bulging | Lateral ground pressure, often from swelling or squeezing ground or from water pressure behind the lining | Structural. Measure the profile and monitor convergence. |
| Transverse cracks at regular spacing | Shrinkage and temperature change in plain concrete placed in long pours | Usually not structural, but a path for water and ice. |
| Diagonal cracks near portals | Movement of the slope or portal structure; differential settlement | Structural. Check portal slope stability (Section 6.6.6). |
| Spalling and delamination | Freeze-thaw near portals; corrosion of reinforcement; locomotive exhaust and moisture; impact | Falling concrete is a hazard to trains and workers. Sound and remove loose material. |
| Lost mortar, open joints, dropped bricks or stones | Water flowing through joints; freeze-thaw; age | Loss of arch action if extensive. Repoint, and fix the water source. |
| Ring separation in brick arches | Weathering of the mortar between rings; cyclic loading | Reduces arch capacity. Investigate by coring or GPR. |
| Leakage and mineral deposits | Water passing through cracks, joints and cold joints | Ice at the portals, corrosion, fouled ballast, and washing of fines from behind the lining. |
| Floor heave and track profile changes | Swelling or squeezing rock in the invert; frost; poor drainage | Track geometry defects. See Section 6.6.5. |
Voids behind old linings deserve particular attention. Where concrete was placed against timber lagging or against overbreak without backfill, the timber rots and the voids remain. A rock block can then fall onto the lining from above as a point load, which a plain concrete arch cannot carry. GPR along the crown, followed by drilling, finds these voids; contact grouting fills them.
For railroad work: A new or widening longitudinal crack in the crown, a flattening of the arch, or fresh spalling over the track calls for a prompt in-depth inspection and, until it is done, a slow order or a protective measure (temporary support or netting). Photograph and measure cracks each time so that change, not just presence, is recorded.
The Q-system of Barton, Lien and Lunde [S5], updated by Grimstad and Barton [S6], rates rock mass quality for underground openings and links it to support needs:
Eq. 6.6-1: Q = (RQD / Jn) · (Jr / Ja) · (Jw / SRF), where RQD = rock quality designation (%), Jn = joint set number, Jr = joint roughness number, Ja = joint alteration number, Jw = joint water reduction factor and SRF = stress reduction factor. The three ratios represent block size, inter-block shear strength and active stress.
The opening size is expressed as an equivalent dimension, the span divided by the excavation support ratio ESR. ESR reflects how much safety the use of the opening demands; for major road and railway tunnels ESR is about 1.0 [S6].
Eq. 6.6-2: Maximum unsupported span = 2 · ESR · Q0.4 (m).
Eq. 6.6-3: Rock bolt length L = 2 + 0.15 B / ESR (m), where B = span (m). Empirical equations reference: RK-02, TN-02.
The support category (spot bolting, systematic bolting, bolts with shotcrete, fibre-reinforced shotcrete with bolts, ribs) is read from the Q-support chart using Q and B/ESR [S6]. Rock mass classification and the Hoek-Brown criterion are covered in Chapter 2.7, Section 2.7.17, and geologic structures in rock (faults, shear zones) in Section 2.7.19.
A Class I railroad located in Virginia has a 1,200-ft unlined single-track tunnel in jointed sandstone. Recent rockfall onto the track came from a section where a clay-filled fault crosses the tunnel. The engineer mapped the rock in the typical section and in the fault zone and must decide whether either needs rock support and how long the bolts should be.
| Variable | Value | Description |
|---|---|---|
| B | 18 ft (5.49 m) | Tunnel span |
| Typical rock | RQD 60; Jn 9; Jr 1.5; Ja 2.0; Jw 1.0; SRF 1.0 | Three joint sets, rough planar joints, slightly altered walls, dry |
| Fault zone | RQD 30; Jn 12; Jr 1.0; Ja 6.0; Jw 0.66; SRF 2.5 | Crushed rock with clay gouge, medium inflow, a single weakness zone |
| ESR | 1.0 | Excavation support ratio for a railway tunnel |
Q = 5.0 and 0.11; unsupported spans of 12.5 ft and 2.7 ft are less than the 18-ft span, so both sections need support. Bolts about 10 ft long; heavier support through the fault zone.
Neither zone can stand unsupported across 18 ft in the long term, which is consistent with the falls reported. In the typical rock, systematic rock bolting with spacing read from the Q-support chart, plus scaling, is the normal answer; spot bolting may suffice where mapping shows blocks are few. Through the fault zone and for about one tunnel width either side of it, the chart calls for much heavier support: fibre-reinforced shotcrete with systematic bolting, or steel ribs where the gouge is wide and squeezing. Drain the fault before shotcreting, because Jw = 0.66 shows water is entering through it. Q values depend strongly on the Ja and SRF chosen for the gouge, so map the fault zone carefully and check the result against the rockfall history.
Method: Barton, Lien and Lunde (1974); Grimstad and Barton (1993). See [S5], [S6].
Open the Q-system rock support calculator →
For railroad work: In operating tunnels, scaling and bolting are done in short track windows from a work platform, so design the support pattern to be installed in stages. Keep a log of falls with their locations; repeated falls from the same place show where the Q-system check and support are most needed.
Some rocks keep moving into a tunnel long after it was built:
In old railroad tunnels both usually show as floor heave, with the track rising and needing repeated surfacing, and as inward movement and cracking of the walls. Wetting by leakage or a blocked drain often starts or speeds up swelling.
Aksoy and Gulsev Uyar describe a design approach for such rocks in which the support is sized so that deformation does not exceed an amount set by analysis, using time-dependent rock mass parameters and three-dimensional models, rather than trying to stop deformation altogether ([S4], Ch. 6). For an existing tunnel, the practical steps are to keep water away from the swelling rock, measure the movement and its rate, and design any invert slab or wall strengthening for the measured behavior.
For railroad work: Where a tunnel needs frequent surfacing for floor heave, survey the track profile and the tunnel profile at the same stations on each visit, and take cores of the invert rock for swelling tests. Restore the invert drainage first. A structural invert slab may be needed, but placing it without dealing with the water usually only moves the problem.
Portals are where most tunnel incidents start. The rock and soil above a portal are usually weathered and loosened, the cut slopes were steepened to shorten the tunnel, and freeze-thaw and runoff are concentrated there. Typical problems are:
Common measures are scaling and bolting of the portal face, draped mesh or rockfall barriers, catchment ditches, drainage of the slope above, and portal extensions (canopies or rock sheds) that carry falling rock and snow over the track. Rock cut design and stabilization are covered in Chapter 6.3, Section 6.3.7, and the rockfall hazard rating for cuts in Section 3.8.29.
For railroad work: Rate each portal and its approach cuts with the rockfall hazard rating of Section 3.8.29 and include the slope above the portal in the slope inventory. After heavy rain, snowmelt or an earthquake, inspect the portals before the first train. Treat new diagonal cracks in a portal or movement of the portal face as a slope problem until shown otherwise.
Water is behind most tunnel deterioration. It washes fines from behind linings, corrodes steel and reinforcement, softens shale and clay, fouls the ballast, and near the portals freezes into icicles and ice columns that foul the clearance envelope or fall onto trains.
For railroad work: Ice in the clearance envelope is a train-safety issue. In cold regions, set an ice inspection and removal routine for the winter months, and record where ice forms each year so the water sources can be treated in summer. Do not grout off leaks without providing another drainage path, or water pressure will build behind the lining.
Double-stack container trains, tri-level auto racks and high-cube cars need more vertical clearance than most old tunnels provide. Clearance diagrams and the equipment outlines they must accommodate are covered in AREMA Chapter 28, Clearances [S8], and in each railroad’s own clearance standards; the route criterion governs. The usual ways to gain clearance are:
| Method | How it works | Main issues |
|---|---|---|
| Track lowering (undercutting) | Excavate the floor and lower the track | Undermining of sidewall footings; drainage outfalls; grade change at the ends; rock excavation in the invert, sometimes by blasting |
| Crown notching | Cut notches in the crown or upper walls where the car corners need room | Only in sound rock or thick linings; weakens a masonry or plain concrete arch |
| Liner replacement | Remove the old lining and install a thinner modern lining (shotcrete, precast) | Temporary support of the ground while the lining is out; long track outages |
| Enlargement | Excavate the rock to a larger profile and reline | Blasting or mechanical excavation beside live track; staged work |
| Daylighting | Remove the tunnel and replace it with an open cut | Large excavation and slopes; feasible for short, shallow tunnels |
| New parallel bore | Build a new tunnel and retire or reuse the old one | Cost; usually only where the old tunnel is in very poor condition |
Laser-scanned profiles at close spacing are the basis of any clearance study: they show the tight spots, which are often local (a sagging section of lining, a misaligned ring, a low spot in an arch) rather than the whole tunnel. Excavation by blasting must meet the vibration limits of Section 5.3.27, with the lining itself treated as the structure to protect.
A Class I railroad located in Pennsylvania wants to run double-stack trains through a 19th-century brick-lined tunnel. The laser-scan profile shows a semicircular arch. The railroad’s clearance criterion for the route requires 21.0 ft above top of rail over a width of 5.0 ft either side of centerline. The engineer must find how much the track must be lowered and whether lowering will undermine the sidewall footings.
| Variable | Value | Description |
|---|---|---|
| R | 10 ft | Radius of the semicircular arch |
| hs | 9.6 ft | Height of springline above existing top of rail at centerline |
| Hreq | 21.0 ft over ±5.0 ft | Required clearance envelope (route criterion) |
| t | 2.0 ft | Track section, top of rail to top of subgrade |
| zf | 3.5 ft | Depth of sidewall footing base below existing top of rail |
Clearance is 19.6 ft at centerline and 18.26 ft at the envelope corners; the track must come down about 2.75 ft, which puts the new subgrade 1.25 ft below the footing base.
The arch corners govern, not the crown: lowering by only the 1.4-ft crown deficit would leave the container corners 1.34 ft short. Lowering the track 2.75 ft with the same 2.0-ft track section exposes the sidewall footings by 1.25 ft, which is not acceptable for a masonry arch that relies on its footings to resist thrust. Options are to underpin the footings (for example with micropiles or a concrete toe wall, Chapter 6.1), to build a structural invert slab that ties the walls together and lets the track section be thinner, or to choose a different method such as liner replacement. Check the grade and drainage at both ends: a 2.75-ft drop must be run out over a long approach on each side, and the invert drains must still reach an outfall. Confirm the profile at many stations, because the arch shape varies along an old tunnel.
Open the arch tunnel clearance calculator →
For railroad work: Ask for a laser-scan clearance survey before choosing a method, and check every tight spot, not only a typical section. Design track lowering together with the footing and drainage details, and plan staged work within track windows with the lining monitored throughout.
| Problem | Methods | Notes |
|---|---|---|
| Loose rock in unlined sections | Scaling; spot or systematic rock bolts; wire mesh; shotcrete | Design from mapping and the Q-system check (Section 6.6.4). Test bolts in place (Chapter 6.3, Section 6.3.7). |
| Spalling and delamination of concrete | Remove loose material; patch with repair mortar or shotcrete; mesh or netting as interim protection | Find and fix the water source first. |
| Lost mortar and loose masonry | Repointing; replacing units; stitching or anchoring rings | Use mortar compatible with the original (often lime-based). |
| Voids behind the lining | Contact grouting through drilled holes, starting low and working up | Control grout pressure to avoid damaging the lining; provide drainage. |
| Water inflow | Chemical or cementitious grouting of leaks; drainage behind the lining; channels and drain pipes on the lining surface | Never seal without a drainage path. |
| Deteriorated or under-strength lining | Shotcrete overlay (plain, mesh or fibre-reinforced); steel ribs or arches; new cast or precast lining | Check clearance first; an overlay reduces it. |
| Floor heave | Restore drainage; structural invert slab; rock bolts in the invert | See Section 6.6.5. |
| Portal instability | Slope stabilization; portal extension or canopy; rockfall protection | See Section 6.6.6. |
Repairs in an operating tunnel are done in short windows, often at night, and must leave the track safe for traffic at the end of each shift. Materials and methods that can be installed in stages, and that cure quickly, are preferred. Ventilation and dust control are needed for shotcrete and grouting.
For railroad work: Repairs that reduce clearance (shotcrete overlays, ribs, new linings) must be checked against the clearance envelope before design is finished, using the laser-scan profile. Record each repair by station in the tunnel file so later inspections can tell repair from original lining.
Monitoring tells whether a defect is stable or getting worse, and how fast. The common tools for existing tunnels are:
Set alert and action levels for each instrument from the expected behavior and the consequences, tie each level to an action (more frequent readings, a slow order, closure and inspection), and give the plan to the dispatcher and track supervisor. Observation-based methods, in which measured deformation is back-analyzed to update the rock parameters and the support, are described by Sharifzadeh et al. ([S4], Ch. 15).
For railroad work: Readings are only useful if someone looks at them. Assign a responsible engineer for each monitored tunnel, plot each instrument against time with its alert and action levels, and review the plots on a set schedule and after any event. Use the trend, not a single reading, to decide what to do; see Question 6.6-1.
Tunnels fit the GHRM risk framework of Chapter 3.8: a likelihood (frequency) rating from 1 to 5 for each element, a consequence (severity) rating, and a current risk from their combination. Table 6.6-5 gives the likelihood levels for the main tunnel elements, with the reasoning for each level.
| Rating | Lining (concrete, masonry) | Unlined rock | Water and ice | Portal | Rationale |
|---|---|---|---|---|---|
| 1 Very low | Sound; hairline cracks only; no voids found | Massive rock, Q > 10; no falls on record | Dry or damp; no ice | Stable slopes; no rockfall | No defect that could develop into a failure within the inspection cycle. |
| 2 Low | Minor cracks and spalls; stable over several inspections | Q 4–10; occasional small falls removed by scaling | Minor drips; small ice removed routinely | Minor raveling caught by the ditch | Defects present but stable; routine maintenance controls them. |
| 3 Moderate | Cracks or spalls over the track; small voids; loose masonry units | Q 1–4, or a weak bed or fault in otherwise good rock; repeated falls from one location | Steady leaks; ice in the clearance envelope some winters | Rockfall reaching the track occasionally; old instability | A defect that could reach the track or the train between inspections; needs a repair plan and closer inspection. |
| 4 High | Widening crown cracks; delamination over the track; voids above the crown; lost mortar over large areas | Q 0.1–1 without adequate support; recent falls onto track | Heavy inflow; ice in the envelope every winter; washing of fines | Active slope movement above the portal; recent rockfall onto track | Deterioration is active and a failure affecting traffic is plausible within the next year; monitor and repair soon, with interim protection. |
| 5 Severe | Arch deformation; new large cracks or spalling; falling material | Q < 0.1 unsupported, squeezing ground, or a fall that left an overhang | Inflow carrying sediment; ice blocking the envelope | Movement of the portal structure; large blocks perched above the portal | Failure is likely or under way; restrict or stop traffic until made safe. |
Consequence depends on train speed, traffic, whether passengers or hazardous materials are carried, the length of an outage (often much longer for a tunnel than for an open line), and whether a detour exists. Combine the ratings with the 5×5 matrix of Chapter 3.8. Risk reduction ratings for the chosen repair follow the same chapter.
For railroad work: Rate each tunnel by segment (portal zones, lining types, fault zones) rather than as a whole, because one bad segment controls the risk. Re-rate after every in-depth inspection and after any event, and feed monitored changes into the live rating described in Chapter 3.8.
Practice questions use the five-part format: Given, Required, Equations, Steps and Solution.
A crown crack in the plain concrete lining of a single-track tunnel on a Class I railroad located in West Virginia is being monitored with a crack gauge. The railroad has set an action level of 0.050 in. of opening, at which a slow order is imposed and an in-depth inspection is made. Six readings have been taken two months apart over one year. The engineer must estimate the opening rate and how long remains before the action level is reached, and say what should be done now.
| Variable | Value | Description |
|---|---|---|
| t | 0, 2, 4, 6, 8, 10 months | Reading times |
| w | 0.018, 0.021, 0.023, 0.026, 0.030, 0.033 in. | Crack opening readings |
| wA | 0.050 in. | Action level |
The crack is opening about 0.0015 in. per month and will reach the 0.050-in. action level in roughly a year if the trend continues.
A steady opening over a full year, through all seasons, is not a seasonal (thermal) cycle: it shows continuing movement of the lining, so the crack should be treated as structural. Do not wait for the action level. Arrange an in-depth inspection now: map all cracks in that section, measure the crown profile by laser scan to check for flattening, run GPR along the crown to look for voids above the lining, and check the drainage. Increase the reading frequency to monthly, add a second gauge and convergence pins, and record temperature with each reading. If the rate increases, or the inspection finds a void or flattening, plan contact grouting or a lining repair and consider interim protection over the track.
Supplemental references for this chapter. Links open the publisher or agency page, or a search for the reference.
Related GHRM chapters: rock and rock mass classification (Chapter 2.7); mining and man-made hazards (Chapter 3.10); risk ratings (Chapter 3.8); construction monitoring (Chapter 5.3); rock cut design (Chapter 6.3); earthworks asset management (Chapter 7.4).