↑ Parent Menu⌂ Main Menu
← Railway Ground Hazard Risk Management
GHRM
Railway Ground Hazard Risk Management · 6.0 · Analysis
Sections · open a dropdown to go to a section or subsection

Chapter 6.6 — Tunnels and Portals

Inspection, assessment, repair and clearance improvement of existing railroad tunnels and their portals.
Author: Daniel P. Colwell

This chapter covers existing railroad tunnels and their portals: tunnel types and their typical problems, inventory and inspection, lining defects, rock support checks in unlined sections, squeezing and swelling ground, portals, water and ice, clearance improvement for tall equipment, repair methods, monitoring and risk rating. Design of new tunnels is outside its scope.

6.6.0 Purpose and Overview

Most railroad tunnels in North America were driven between the 1850s and the 1930s. They were built for smaller equipment, often by hand or with early drilling and black powder, and lined (if at all) with timber, brick, stone masonry or unreinforced concrete. Many are now more than a century old and carry heavier, taller and more frequent trains than they were designed for. This chapter is about keeping those tunnels safe and in service:

Design of new tunnels (excavation methods, NATM and TBM tunneling, support design for new openings) is outside the scope of this chapter. Settlement of track above a new tunnel driven beneath the railroad is covered in Chapter 6.2, Section 6.2.7. Blasting near track is covered in Chapter 5.3, Section 5.3.27.

For railroad work: A tunnel failure closes the line, often for weeks, and there may be no practical detour. Treat each tunnel as an asset with its own inspection record, risk rating and repair plan, and inspect it with the same care as a bridge. Keep the original construction records, later repair records and every inspection report together, because the history of a tunnel explains most of its defects.

6.6.1 Railroad Tunnel Types and Typical Problems

The lining type, or lack of one, controls what can go wrong and how a tunnel should be inspected and repaired.

Table 6.6-1. Railroad tunnel types and their typical problems
TypeWhere foundTypical problemsNotes
Unlined rockStrong, massive rock (granite, gneiss, quartzite, massive sandstone and limestone)Loose blocks and rockfall from the crown and walls; slaking of shale and mudstone layers; water and iceScaling and spot bolting are the usual maintenance. Weak beds within strong rock are the most common source of falls.
Timber-lined (sets and lagging)Weaker or blocky rock in early tunnelsDecay, insect damage, fire, crushed or displaced sets, voids behind laggingMany were later replaced or encased in concrete or shotcrete. Remaining timber is a fire and collapse hazard.
Brick or stone masonry archSoil, weak rock and portals of 19th-century tunnelsLost mortar, ring separation, bulging, dropped stones, water through joints, freeze-thaw damageMasonry arches carry load by compression; loss of shape or of mortar in joints reduces capacity.
Plain (unreinforced) concreteLinings placed from about 1900 onward, often over timber or masonryCracking, spalling, cold-joint leakage, voids behind the lining, alkali-silica reaction, freeze-thaw near portalsVoids behind old linings are common where concrete was placed against timber or loose rock.
Reinforced concrete or shotcreteRehabilitation work and later tunnelsCorrosion of reinforcement where water and deicing salts reach it, delamination, drummy shotcreteCheck cover and chloride where leakage is heavy.
Steel liner plate or ribsRepairs, short tunnels, portal extensionsCorrosion at the invert and where water dripsSection loss at the base of ribs is the usual weak point.

Problems that apply to all types are water inflow and ice, clearance that is too small for modern equipment, drainage that has silted or frozen, and portals where the slopes above are unstable.

For railroad work: The type of lining often changes along a tunnel: rock in the middle, masonry or concrete near the portals and through weak zones. Record the lining type and its limits by station (or distance from a portal) in the inventory, because the inspection method, the defects to look for and the repair options change at each boundary.

6.6.2 Inventory and Inspection

The FHWA Highway and Rail Transit Tunnel Inspection Manual [S1] and the later Tunnel Operations, Maintenance, Inspection, and Evaluation (TOMIE) Manual [S2] set out the inventory, inspection and condition-rating practice now used for tunnels. The 2005 manual has since been superseded by the TOMIE Manual, which the National Tunnel Inspection Standards (23 CFR 650 Subpart E, 2015) incorporate by reference for highway tunnels on public roads. The standards do not apply to freight railroad tunnels, but their inspection intervals, element-by-element condition states and reporting of critical findings are a sound model for a railroad program. For railroad tunnels, the AREMA Manual for Railway Engineering covers design, maintenance and construction, and ventilation in Chapter 1, Part 8 [S8]. Railroads follow their own programs, but the same approach applies.

Inventory

  • Location, length, number of tracks, grade and curvature, portal coordinates.
  • Lining type and limits by station; cross-section dimensions; clearance diagram.
  • Geology along the tunnel, from construction records, geologic maps and later mapping.
  • Drainage layout (sidewall ditches, invert drains, outfalls), ventilation and utilities.
  • History: construction date and method, relining, fires, falls, floods and repairs.

Inspection

  • Routine inspection on a fixed cycle, commonly yearly, from a hi-rail vehicle or on foot during a track window. Look at the crown, walls, portals, drainage, track and any previously recorded defects.
  • In-depth inspection at longer intervals, or after a fall, flood, earthquake or fire, with close-up access from a lift or work platform. Sound concrete and masonry with a hammer (a dull or hollow sound indicates delamination or voids), measure cracks, map leaks and ice, and take cores where needed.
  • Special methods: ground penetrating radar run along the lining to find voids and thin sections behind it (Section 5.1.15); terrestrial or mobile laser scanning for the full profile, clearance and changes between surveys; infrared thermography for wet areas and delamination; impact-echo or cores for lining thickness and strength.

Laser scanning records the whole surface in 3D with images, so the data can be measured later and compared with the next scan. In rock tunnels it has been used for fracture mapping, locating water leakage, overbreak and underbreak, checking shotcrete thickness and monitoring deformation ([S4], Ch. 18). For railroad tunnels, a mobile scan from a track vehicle gives the clearance profile at close spacing along the whole tunnel in one track window.

Recording defects

Record each defect with its location (station, clock position or offset from centerline, height), type, size, and a photograph, and give it a condition rating. The FHWA manuals rate tunnel elements from 9 (new) to 0 (failed). GHRM uses the 1-to-5 risk scale of Chapter 3.8, and Table 6.6-6 in Section 6.6.11 maps tunnel defects to that scale.

For railroad work: Inspect from a work train or hi-rail vehicle with lights and a lift, under track protection, and allow enough window time to sound the lining and not only look at it. Mark each defect on the lining with a paint number and station so it can be found again. Re-scan after any reported change, and compare the scans to find movement that a visual inspection would miss.

6.6.3 Lining Defects and Their Causes

The pattern of a defect usually shows its cause. Interpreting the pattern correctly decides whether a repair is cosmetic or structural.

Table 6.6-2. Lining defects, likely causes and significance
DefectLikely causeSignificance
Longitudinal crack along the crownVertical ground load greater than the lining was built for; loss of support at the springlines; voids above the crown letting the arch deformStructural. Check for flattening of the crown and for voids above it. Monitor crack width.
Longitudinal cracks at the springlines or walls, with bulgingLateral ground pressure, often from swelling or squeezing ground or from water pressure behind the liningStructural. Measure the profile and monitor convergence.
Transverse cracks at regular spacingShrinkage and temperature change in plain concrete placed in long poursUsually not structural, but a path for water and ice.
Diagonal cracks near portalsMovement of the slope or portal structure; differential settlementStructural. Check portal slope stability (Section 6.6.6).
Spalling and delaminationFreeze-thaw near portals; corrosion of reinforcement; locomotive exhaust and moisture; impactFalling concrete is a hazard to trains and workers. Sound and remove loose material.
Lost mortar, open joints, dropped bricks or stonesWater flowing through joints; freeze-thaw; ageLoss of arch action if extensive. Repoint, and fix the water source.
Ring separation in brick archesWeathering of the mortar between rings; cyclic loadingReduces arch capacity. Investigate by coring or GPR.
Leakage and mineral depositsWater passing through cracks, joints and cold jointsIce at the portals, corrosion, fouled ballast, and washing of fines from behind the lining.
Floor heave and track profile changesSwelling or squeezing rock in the invert; frost; poor drainageTrack geometry defects. See Section 6.6.5.

Voids behind old linings deserve particular attention. Where concrete was placed against timber lagging or against overbreak without backfill, the timber rots and the voids remain. A rock block can then fall onto the lining from above as a point load, which a plain concrete arch cannot carry. GPR along the crown, followed by drilling, finds these voids; contact grouting fills them.

For railroad work: A new or widening longitudinal crack in the crown, a flattening of the arch, or fresh spalling over the track calls for a prompt in-depth inspection and, until it is done, a slow order or a protective measure (temporary support or netting). Photograph and measure cracks each time so that change, not just presence, is recorded.

6.6.4 Rock in Unlined Tunnels: Q-System Checks and Rock Support

The Q-system of Barton, Lien and Lunde [S5], updated by Grimstad and Barton [S6], rates rock mass quality for underground openings and links it to support needs:

Eq. 6.6-1: Q = (RQD / Jn) · (Jr / Ja) · (Jw / SRF), where RQD = rock quality designation (%), Jn = joint set number, Jr = joint roughness number, Ja = joint alteration number, Jw = joint water reduction factor and SRF = stress reduction factor. The three ratios represent block size, inter-block shear strength and active stress.

The opening size is expressed as an equivalent dimension, the span divided by the excavation support ratio ESR. ESR reflects how much safety the use of the opening demands; for major road and railway tunnels ESR is about 1.0 [S6].

Eq. 6.6-2: Maximum unsupported span = 2 · ESR · Q0.4 (m).

Eq. 6.6-3: Rock bolt length L = 2 + 0.15 B / ESR (m), where B = span (m). Empirical equations reference: RK-02, TN-02.

The support category (spot bolting, systematic bolting, bolts with shotcrete, fibre-reinforced shotcrete with bolts, ribs) is read from the Q-support chart using Q and B/ESR [S6]. Rock mass classification and the Hoek-Brown criterion are covered in Chapter 2.7, Section 2.7.17, and geologic structures in rock (faults, shear zones) in Section 2.7.19.

Example 6.6-1: Does an Unlined Rock Tunnel Section Need Support?

Problem Statement

A Class I railroad located in Virginia has a 1,200-ft unlined single-track tunnel in jointed sandstone. Recent rockfall onto the track came from a section where a clay-filled fault crosses the tunnel. The engineer mapped the rock in the typical section and in the fault zone and must decide whether either needs rock support and how long the bolts should be.

ballast B = 18 ft Fault zone(clay gouge) Typical rock Given Typical rock: RQD 60,Jn 9, Jr 1.5, Ja 2.0,Jw 1.0, SRF 1.0 Fault zone: RQD 30,Jn 12, Jr 1.0, Ja 6.0,Jw 0.66, SRF 2.5 ESR = 1.0 (railway tunnel) Required(a) Q for each zone(b) Max. unsupported span(c) Rock bolt length
Figure 6.6-1. Example 6.6-1: unlined single-track rock tunnel with a fault zone crossing it.

Given

VariableValueDescription
B18 ft (5.49 m)Tunnel span
Typical rockRQD 60; Jn 9; Jr 1.5; Ja 2.0; Jw 1.0; SRF 1.0Three joint sets, rough planar joints, slightly altered walls, dry
Fault zoneRQD 30; Jn 12; Jr 1.0; Ja 6.0; Jw 0.66; SRF 2.5Crushed rock with clay gouge, medium inflow, a single weakness zone
ESR1.0Excavation support ratio for a railway tunnel

Required

  • (a) Q for the typical rock and for the fault zone
  • (b) Maximum unsupported span for each
  • (c) Rock bolt length, and the support approach

Equations

  1. Eq. 6.6-1: Q = (RQD/Jn)(Jr/Ja)(Jw/SRF)
  2. Eq. 6.6-2: spanmax = 2 · ESR · Q0.4 (m)
  3. Eq. 6.6-3: L = 2 + 0.15 B / ESR (m)

Steps

Step 1 · (a) Q, typical rock
(60/9)(1.5/2.0)(1.0/1.0) = 6.67 × 0.75 × 1.0
Q = 5.0 (fair rock)
↓
Step 2 · (a) Q, fault zone
(30/12)(1.0/6.0)(0.66/2.5) = 2.5 × 0.167 × 0.264
Q = 0.11 (very poor rock)
↓
Step 3 · (b) Unsupported span
Typical: 5.00.4 = e0.4 × 1.609 = 1.904; 2 × 1.0 × 1.904 = 3.81 m. Fault: 0.110.4 = e0.4 × (−2.207) = 0.414; 2 × 0.414 = 0.83 m
12.5 ft (typical); 2.7 ft (fault zone), both less than the 18-ft span
Spot check: 3.81 m × 3.281 = 12.5 ft; 0.83 m × 3.281 = 2.7 ft.
↓
Step 4 · (c) Bolt length
2 + 0.15 × 5.49 / 1.0 = 2.82 m
L ≈ 9.3 ft (use 10-ft bolts)
↓
Solution
Q = 5.0 and 0.11; unsupported spans of 12.5 ft and 2.7 ft are less than the 18-ft span, so both sections need support. Bolts about 10 ft long; heavier support through the fault zone.

Solution

Q = 5.0 and 0.11; unsupported spans of 12.5 ft and 2.7 ft are less than the 18-ft span, so both sections need support. Bolts about 10 ft long; heavier support through the fault zone.

Neither zone can stand unsupported across 18 ft in the long term, which is consistent with the falls reported. In the typical rock, systematic rock bolting with spacing read from the Q-support chart, plus scaling, is the normal answer; spot bolting may suffice where mapping shows blocks are few. Through the fault zone and for about one tunnel width either side of it, the chart calls for much heavier support: fibre-reinforced shotcrete with systematic bolting, or steel ribs where the gouge is wide and squeezing. Drain the fault before shotcreting, because Jw = 0.66 shows water is entering through it. Q values depend strongly on the Ja and SRF chosen for the gouge, so map the fault zone carefully and check the result against the rockfall history.

Method: Barton, Lien and Lunde (1974); Grimstad and Barton (1993). See [S5], [S6].

Open the Q-system rock support calculator →

For railroad work: In operating tunnels, scaling and bolting are done in short track windows from a work platform, so design the support pattern to be installed in stages. Keep a log of falls with their locations; repeated falls from the same place show where the Q-system check and support are most needed.

6.6.5 Squeezing and Swelling Ground

Some rocks keep moving into a tunnel long after it was built:

  • Squeezing is time-dependent shear deformation of weak rock (clay shale, fault gouge, weathered schist) around the opening when stresses exceed the rock mass strength.
  • Swelling is volume increase when certain rocks take up water: clay shales and mudstones with swelling clay minerals, and anhydrite that hydrates to gypsum.

In old railroad tunnels both usually show as floor heave, with the track rising and needing repeated surfacing, and as inward movement and cracking of the walls. Wetting by leakage or a blocked drain often starts or speeds up swelling.

Aksoy and Gulsev Uyar describe a design approach for such rocks in which the support is sized so that deformation does not exceed an amount set by analysis, using time-dependent rock mass parameters and three-dimensional models, rather than trying to stop deformation altogether ([S4], Ch. 6). For an existing tunnel, the practical steps are to keep water away from the swelling rock, measure the movement and its rate, and design any invert slab or wall strengthening for the measured behavior.

For railroad work: Where a tunnel needs frequent surfacing for floor heave, survey the track profile and the tunnel profile at the same stations on each visit, and take cores of the invert rock for swelling tests. Restore the invert drainage first. A structural invert slab may be needed, but placing it without dealing with the water usually only moves the problem.

6.6.6 Portals

Portals are where most tunnel incidents start. The rock and soil above a portal are usually weathered and loosened, the cut slopes were steepened to shorten the tunnel, and freeze-thaw and runoff are concentrated there. Typical problems are:

  • rockfall and raveling from the portal face and the cut slopes either side;
  • slope instability above the portal, which can load or move the portal structure (diagonal cracking in the portal lining is a sign);
  • debris flows, snow avalanches and icefalls in mountain terrain;
  • deterioration of masonry and concrete portal faces and wing walls from freeze-thaw and water.

Common measures are scaling and bolting of the portal face, draped mesh or rockfall barriers, catchment ditches, drainage of the slope above, and portal extensions (canopies or rock sheds) that carry falling rock and snow over the track. Rock cut design and stabilization are covered in Chapter 6.3, Section 6.3.7, and the rockfall hazard rating for cuts in Section 3.8.29.

For railroad work: Rate each portal and its approach cuts with the rockfall hazard rating of Section 3.8.29 and include the slope above the portal in the slope inventory. After heavy rain, snowmelt or an earthquake, inspect the portals before the first train. Treat new diagonal cracks in a portal or movement of the portal face as a slope problem until shown otherwise.

6.6.7 Water, Drainage and Ice

Water is behind most tunnel deterioration. It washes fines from behind linings, corrodes steel and reinforcement, softens shale and clay, fouls the ballast, and near the portals freezes into icicles and ice columns that foul the clearance envelope or fall onto trains.

  • Map leaks by station and flow on each inspection, separately for wet and dry seasons. A change in flow or in the color or sediment of the water is significant.
  • Keep sidewall ditches and invert drains clear and graded to an outfall. Many old tunnels have drains that have silted up or been covered by ballast.
  • Near portals, where freezing reaches into the tunnel, ice forms where water enters. Ice can be removed by crews, intercepted at the source (drains behind the lining, grouting of leaks) or prevented by insulated or heated drainage and portal doors in extreme climates.

For railroad work: Ice in the clearance envelope is a train-safety issue. In cold regions, set an ice inspection and removal routine for the winter months, and record where ice forms each year so the water sources can be treated in summer. Do not grout off leaks without providing another drainage path, or water pressure will build behind the lining.

6.6.8 Clearance Improvement Projects

Double-stack container trains, tri-level auto racks and high-cube cars need more vertical clearance than most old tunnels provide. Clearance diagrams and the equipment outlines they must accommodate are covered in AREMA Chapter 28, Clearances [S8], and in each railroad’s own clearance standards; the route criterion governs. The usual ways to gain clearance are:

Table 6.6-3. Ways to increase tunnel clearance
MethodHow it worksMain issues
Track lowering (undercutting)Excavate the floor and lower the trackUndermining of sidewall footings; drainage outfalls; grade change at the ends; rock excavation in the invert, sometimes by blasting
Crown notchingCut notches in the crown or upper walls where the car corners need roomOnly in sound rock or thick linings; weakens a masonry or plain concrete arch
Liner replacementRemove the old lining and install a thinner modern lining (shotcrete, precast)Temporary support of the ground while the lining is out; long track outages
EnlargementExcavate the rock to a larger profile and relineBlasting or mechanical excavation beside live track; staged work
DaylightingRemove the tunnel and replace it with an open cutLarge excavation and slopes; feasible for short, shallow tunnels
New parallel boreBuild a new tunnel and retire or reuse the old oneCost; usually only where the old tunnel is in very poor condition

Laser-scanned profiles at close spacing are the basis of any clearance study: they show the tight spots, which are often local (a sagging section of lining, a misaligned ring, a low spot in an arch) rather than the whole tunnel. Excavation by blasting must meet the vibration limits of Section 5.3.27, with the lining itself treated as the structure to protect.

Example 6.6-2: Track Lowering for Double-Stack Clearance in a Masonry Arch Tunnel

Problem Statement

A Class I railroad located in Pennsylvania wants to run double-stack trains through a 19th-century brick-lined tunnel. The laser-scan profile shows a semicircular arch. The railroad’s clearance criterion for the route requires 21.0 ft above top of rail over a width of 5.0 ft either side of centerline. The engineer must find how much the track must be lowered and whether lowering will undermine the sidewall footings.

sidewallfooting Existing top of rail (TOR) Top of subgrade (2.0 ft below TOR) Footing base (3.5 ft below TOR) Springline (9.6 ft above TOR) Required envelope: 21.0 ft corner ±5.0 ft R = 10 ft GivenSemicircular arch, R = 10 ftSpringline 9.6 ft above TOREnvelope: 21.0 ft aboveTOR over ±5.0 ftTrack section 2.0 ftFooting base 3.5 ftbelow TOR Required(a) Clearance at center and at ±5.0 ft(b) Track lowering(c) New subgrade vs footing base
Figure 6.6-2. Example 6.6-2: masonry arch tunnel and the clearance envelope for double-stack service (not to scale vertically).

Given

VariableValueDescription
R10 ftRadius of the semicircular arch
hs9.6 ftHeight of springline above existing top of rail at centerline
Hreq21.0 ft over ±5.0 ftRequired clearance envelope (route criterion)
t2.0 ftTrack section, top of rail to top of subgrade
zf3.5 ftDepth of sidewall footing base below existing top of rail

Required

  • (a) Existing clearance at centerline and at ±5.0 ft
  • (b) Required track lowering
  • (c) New top of subgrade compared with the footing base

Equations

  1. y(x) = hs + √(R2 − x2) — arch height above TOR at offset x
  2. Δ = Hreq − min y(x) over the envelope width
  3. zsg,new = Δ + t — new top of subgrade below existing TOR

Steps

Step 1 · (a) Clearance at centerline
9.6 + √(100 − 0) = 9.6 + 10.0
19.6 ft
↓
Step 2 · (a) Clearance at ±5.0 ft
9.6 + √(100 − 25) = 9.6 + 8.66
18.26 ft (governs)
Spot check: 8.662 + 5.02 = 75.0 + 25.0 = 100 = R2 ✓.
↓
Step 3 · (b) Lowering
21.0 − 18.26
Δ = 2.74 ft; use 2.75 ft (33 in.)
↓
Step 4 · (c) New top of subgrade
2.75 + 2.0 = 4.75 ft below existing TOR, against footing base at 3.5 ft
New subgrade is 1.25 ft below the footing base
↓
Solution
Clearance is 19.6 ft at centerline and 18.26 ft at the envelope corners; the track must come down about 2.75 ft, which puts the new subgrade 1.25 ft below the footing base.

Solution

Clearance is 19.6 ft at centerline and 18.26 ft at the envelope corners; the track must come down about 2.75 ft, which puts the new subgrade 1.25 ft below the footing base.

The arch corners govern, not the crown: lowering by only the 1.4-ft crown deficit would leave the container corners 1.34 ft short. Lowering the track 2.75 ft with the same 2.0-ft track section exposes the sidewall footings by 1.25 ft, which is not acceptable for a masonry arch that relies on its footings to resist thrust. Options are to underpin the footings (for example with micropiles or a concrete toe wall, Chapter 6.1), to build a structural invert slab that ties the walls together and lets the track section be thinner, or to choose a different method such as liner replacement. Check the grade and drainage at both ends: a 2.75-ft drop must be run out over a long approach on each side, and the invert drains must still reach an outfall. Confirm the profile at many stations, because the arch shape varies along an old tunnel.

Open the arch tunnel clearance calculator →

For railroad work: Ask for a laser-scan clearance survey before choosing a method, and check every tight spot, not only a typical section. Design track lowering together with the footing and drainage details, and plan staged work within track windows with the lining monitored throughout.

6.6.9 Repair and Rehabilitation Methods
Table 6.6-4. Repair and rehabilitation methods for railroad tunnels
ProblemMethodsNotes
Loose rock in unlined sectionsScaling; spot or systematic rock bolts; wire mesh; shotcreteDesign from mapping and the Q-system check (Section 6.6.4). Test bolts in place (Chapter 6.3, Section 6.3.7).
Spalling and delamination of concreteRemove loose material; patch with repair mortar or shotcrete; mesh or netting as interim protectionFind and fix the water source first.
Lost mortar and loose masonryRepointing; replacing units; stitching or anchoring ringsUse mortar compatible with the original (often lime-based).
Voids behind the liningContact grouting through drilled holes, starting low and working upControl grout pressure to avoid damaging the lining; provide drainage.
Water inflowChemical or cementitious grouting of leaks; drainage behind the lining; channels and drain pipes on the lining surfaceNever seal without a drainage path.
Deteriorated or under-strength liningShotcrete overlay (plain, mesh or fibre-reinforced); steel ribs or arches; new cast or precast liningCheck clearance first; an overlay reduces it.
Floor heaveRestore drainage; structural invert slab; rock bolts in the invertSee Section 6.6.5.
Portal instabilitySlope stabilization; portal extension or canopy; rockfall protectionSee Section 6.6.6.

Repairs in an operating tunnel are done in short windows, often at night, and must leave the track safe for traffic at the end of each shift. Materials and methods that can be installed in stages, and that cure quickly, are preferred. Ventilation and dust control are needed for shotcrete and grouting.

For railroad work: Repairs that reduce clearance (shotcrete overlays, ribs, new linings) must be checked against the clearance envelope before design is finished, using the laser-scan profile. Record each repair by station in the tunnel file so later inspections can tell repair from original lining.

6.6.10 Monitoring Existing Tunnels

Monitoring tells whether a defect is stable or getting worse, and how fast. The common tools for existing tunnels are:

  • Crack gauges and pins across cracks, read by hand or with a data logger. Record temperature with each reading, because cracks in linings open and close with the seasons.
  • Convergence measurements between pins on opposite walls and the crown, by tape extensometer or total station.
  • Repeat laser scanning, comparing scans to find deformation and changes in clearance over the whole surface ([S4], Ch. 18).
  • Fiber-optic strain sensing along the lining or in boreholes (Section 5.3.8), and tiltmeters on portals and walls.
  • Piezometers behind the lining where water pressure is suspected.
  • On-site visualization, with sensors that show their state by color at the instrument, so track crews see a change at once (Section 5.3.21).

Set alert and action levels for each instrument from the expected behavior and the consequences, tie each level to an action (more frequent readings, a slow order, closure and inspection), and give the plan to the dispatcher and track supervisor. Observation-based methods, in which measured deformation is back-analyzed to update the rock parameters and the support, are described by Sharifzadeh et al. ([S4], Ch. 15).

For railroad work: Readings are only useful if someone looks at them. Assign a responsible engineer for each monitored tunnel, plot each instrument against time with its alert and action levels, and review the plots on a set schedule and after any event. Use the trend, not a single reading, to decide what to do; see Question 6.6-1.

6.6.11 Risk Rating for Tunnels

Tunnels fit the GHRM risk framework of Chapter 3.8: a likelihood (frequency) rating from 1 to 5 for each element, a consequence (severity) rating, and a current risk from their combination. Table 6.6-5 gives the likelihood levels for the main tunnel elements, with the reasoning for each level.

Table 6.6-5. Likelihood ratings for tunnel elements (1 = very low, 5 = severe)
RatingLining (concrete, masonry)Unlined rockWater and icePortalRationale
1 Very lowSound; hairline cracks only; no voids foundMassive rock, Q > 10; no falls on recordDry or damp; no iceStable slopes; no rockfallNo defect that could develop into a failure within the inspection cycle.
2 LowMinor cracks and spalls; stable over several inspectionsQ 4–10; occasional small falls removed by scalingMinor drips; small ice removed routinelyMinor raveling caught by the ditchDefects present but stable; routine maintenance controls them.
3 ModerateCracks or spalls over the track; small voids; loose masonry unitsQ 1–4, or a weak bed or fault in otherwise good rock; repeated falls from one locationSteady leaks; ice in the clearance envelope some wintersRockfall reaching the track occasionally; old instabilityA defect that could reach the track or the train between inspections; needs a repair plan and closer inspection.
4 HighWidening crown cracks; delamination over the track; voids above the crown; lost mortar over large areasQ 0.1–1 without adequate support; recent falls onto trackHeavy inflow; ice in the envelope every winter; washing of finesActive slope movement above the portal; recent rockfall onto trackDeterioration is active and a failure affecting traffic is plausible within the next year; monitor and repair soon, with interim protection.
5 SevereArch deformation; new large cracks or spalling; falling materialQ < 0.1 unsupported, squeezing ground, or a fall that left an overhangInflow carrying sediment; ice blocking the envelopeMovement of the portal structure; large blocks perched above the portalFailure is likely or under way; restrict or stop traffic until made safe.

Consequence depends on train speed, traffic, whether passengers or hazardous materials are carried, the length of an outage (often much longer for a tunnel than for an open line), and whether a detour exists. Combine the ratings with the 5×5 matrix of Chapter 3.8. Risk reduction ratings for the chosen repair follow the same chapter.

For railroad work: Rate each tunnel by segment (portal zones, lining types, fault zones) rather than as a whole, because one bad segment controls the risk. Re-rate after every in-depth inspection and after any event, and feed monitored changes into the live rating described in Chapter 3.8.

6.6.12 Practice Questions

Practice questions use the five-part format: Given, Required, Equations, Steps and Solution.

Question 6.6-1: When Will a Crown Crack Reach the Action Level?

Problem Statement

A crown crack in the plain concrete lining of a single-track tunnel on a Class I railroad located in West Virginia is being monitored with a crack gauge. The railroad has set an action level of 0.050 in. of opening, at which a slow order is imposed and an in-depth inspection is made. Six readings have been taken two months apart over one year. The engineer must estimate the opening rate and how long remains before the action level is reached, and say what should be done now.

0.0100.0300.050 0102030 Months since first reading Action level 0.050 in. GivenReadings every 2 months:0.018, 0.021, 0.023,0.026, 0.030, 0.033 in.Action level 0.050 in. Required(a) Opening rate(b) Months to action level(c) What to do now
Figure 6.6-3. Question 6.6-1: crack gauge readings across a crown crack, with the fitted trend extended to the action level.

Given

VariableValueDescription
t0, 2, 4, 6, 8, 10 monthsReading times
w0.018, 0.021, 0.023, 0.026, 0.030, 0.033 in.Crack opening readings
wA0.050 in.Action level

Required

  • (a) Opening rate by least-squares fit
  • (b) Months from the last reading to the action level
  • (c) What should be done now

Equations

  1. b = Σ(t − t̄)(w − w̄) / Σ(t − t̄)2 — slope of the fitted line
  2. ŵ(t) = w̄ + b (t − t̄) — fitted value
  3. tA = (wA − ŵ(10)) / b — time to the action level

Steps

Step 1 · Means
t̄ = 30/6; w̄ = 0.151/6
t̄ = 5.0 months; w̄ = 0.02517 in.
↓
Step 2 · (a) Slope
Σ(t − t̄)2 = 25 + 9 + 1 + 1 + 9 + 25 = 70; Σ(t − t̄)(w − w̄) = 0.0358 + 0.0125 + 0.0022 + 0.0008 + 0.0145 + 0.0392 = 0.1050; b = 0.1050 / 70
b = 0.0015 in./month (0.018 in./yr)
Spot check: the first and last readings give (0.033 − 0.018)/10 = 0.0015 in./month as well.
↓
Step 3 · Fitted value at 10 months
0.02517 + 0.0015 × 5
ŵ(10) = 0.0327 in.
↓
Step 4 · (b) Time to action level
(0.050 − 0.0327) / 0.0015
tA ≈ 11.6 months, about one year
↓
Solution
The crack is opening about 0.0015 in. per month and will reach the 0.050-in. action level in roughly a year if the trend continues.

Solution

The crack is opening about 0.0015 in. per month and will reach the 0.050-in. action level in roughly a year if the trend continues.

A steady opening over a full year, through all seasons, is not a seasonal (thermal) cycle: it shows continuing movement of the lining, so the crack should be treated as structural. Do not wait for the action level. Arrange an in-depth inspection now: map all cracks in that section, measure the crown profile by laser scan to check for flattening, run GPR along the crown to look for voids above the lining, and check the drainage. Increase the reading frequency to monthly, add a second gauge and convergence pins, and record temperature with each reading. If the rate increases, or the inspection finds a void or flattening, plan contact grouting or a lining repair and consider interim protection over the track.

6.6.13 References

Supplemental references for this chapter. Links open the publisher or agency page, or a search for the reference.

  1. Federal Highway Administration and Federal Transit Administration (2005). Highway and Rail Transit Tunnel Inspection Manual. Publication No. FHWA-IF-05-002. Washington, DC: FHWA. Superseded by the TOMIE Manual [S2]; still useful for its rail transit tunnel elements and defect descriptions. FHWA copy (marked superseded) ↗
  2. Federal Highway Administration (2015). Tunnel Operations, Maintenance, Inspection, and Evaluation (TOMIE) Manual. Publication No. FHWA-HIF-15-005. Washington, DC: FHWA. Incorporated by reference in the National Tunnel Inspection Standards, 23 CFR 650 Subpart E. Official page ↗
  3. Federal Highway Administration and Federal Transit Administration (2005). Highway and Rail Transit Tunnel Maintenance and Rehabilitation Manual. Publication No. FHWA-IF-05-017. Washington, DC: FHWA. Archived FHWA page ↗
  4. Feng, X.-T. (ed.) (2017). Rock Mechanics and Engineering, Volume 4: Excavation, Support and Monitoring. Leiden: CRC Press/Balkema. Chapters used: Aksoy and Gulsev Uyar (Ch. 6), Akutagawa (Ch. 7), Sharifzadeh, Ghorbani and Yasrobi (Ch. 15), Wang and Gage (Ch. 17), Feng, Wang and Röshoff (Ch. 18). Find source ↗
  5. Barton, N., Lien, R. and Lunde, J. (1974). “Engineering classification of rock masses for the design of tunnel support.” Rock Mechanics, 6(4), 189–236. Find source ↗
  6. Grimstad, E. and Barton, N. (1993). “Updating the Q-system for NMT.” Proc. Int. Symp. on Sprayed Concrete, Fagernes, Norway. Oslo: Norwegian Concrete Association. Find source ↗
  7. Hoek, E. (2007). Practical Rock Engineering. RocScience course notes. Official page ↗
  8. American Railway Engineering and Maintenance-of-Way Association (2026). Manual for Railway Engineering. Chapter 1, Roadway and Ballast, Part 8, Tunnels (Sections 8.4 Design, 8.5 Maintenance and Construction, 8.7 Ventilation); Chapter 28, Clearances. Lanham, MD: AREMA. Official page ↗

Related GHRM chapters: rock and rock mass classification (Chapter 2.7); mining and man-made hazards (Chapter 3.10); risk ratings (Chapter 3.8); construction monitoring (Chapter 5.3); rock cut design (Chapter 6.3); earthworks asset management (Chapter 7.4).

← Previous · 6.0 Analysis Chapter 6.5 — Seismic Hazard and Liquefaction
Next · 7.0 Design → Chapter 7.1 — Retaining Structures