7.1.9 Worked Calculation Examples

Retaining structures are among the most consequential geotechnical elements in railroad capital programs.
Authors: Daniel P. Colwell and Mario Ruel
7.1.9 Worked Calculation Examples
The three examples cover a cantilever wall, an MSE wall and the seismic case for a gravity wall. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution. Walls that retain track next to an operating line are usually soldier pile and lagging; Section 7.1.3.1 works that case.
Example 7.1-1: Cantilever Wall at a Rock Cut Transition

A second main track on a Class I railroad located in the Shenandoah Valley of western Virginia needs a 20-ft cantilever wall where the slope is cut back. The example computes the earth pressure with Coulomb wall friction, adds the train surcharge, and checks sliding and overturning on a trial footing.

Cantilever Retaining Wall
Cantilever Retaining Wall
RC Cantilever Retaining Wall
RC Cantilever Retaining Wall
RCC Cantilever Retaining Wall
RCC Cantilever Retaining Wall
Cantilevered Retaining Wall
Cantilevered Retaining Wall

Given

VariableValueDescription
H20 ftRetained height
Backfillφ′ = 34°, c′ = 0, γ = 120 pcfCompacted granular fill
δ22.7° (2/3 φ′)Wall friction
q520 psfTrain surcharge with DLF 1.3, simplified as uniform (Section 7.1.3.1 gives the strip load)
Baseφ′base = 30°; qallow = 4,000 psfDense sand
W≈ 24,000 lb/ftStem, footing and soil on the heel, B = 10 ft (from the wall geometry, not detailed here)
TargetsFSsliding ≥ 1.5; FSOT ≥ 2.0

Required

  • KA, forces and stem moment
  • Sliding and overturning on the trial footing

Equations

  1. Eq. 1: KA = cos²φ′ / {cosδ [1 + √(sin(φ′ + δ) sinφ′ / cosδ)]²} — Coulomb, vertical wall, level backfill
  2. Eq. 2: PA = ½KAγH² at H/3; ΔP = KAqH at H/2
  3. Eq. 3: FSsliding = W tanφ′base / P; FSOT = ΣMR/ΣMOT — about the toe

Steps

Step 1 · KA (Eq. 1)
0.687 / {0.922 × [1 + √(0.836 × 0.559/0.922)]²} = 0.687 / (0.922 × 2.930)
KA = 0.254
↓
Step 2 · Forces (Eq. 2)
½ × 0.254 × 120 × 400 = 6,096; 0.254 × 520 × 20 = 2,642
P = 8,738 lb/ft
↓
Step 3 · Stem moment
6,096 × 6.67 + 2,642 × 10.0
M ≈ 67,060 ft-lb/ft
↓
Step 4 · Sliding (Eq. 3)
24,000 × tan30° / 8,738 = 13,856 / 8,738
FS = 1.58 ≥ 1.5
↓
Step 5 · Overturning, B = 10 ft
24,000 × 4.0 / 67,060
FS = 1.43 < 2.0: revise
↓
Step 6 · Overturning, B = 14 ft
ΣMR ≈ 142,000 (from the revised geometry) / 67,060
FS = 2.12 ≥ 2.0
↓
Solution
KA = 0.254; sliding 1.58; overturning needs B = 14 ft.

Solution

KA = 0.254 and the total thrust is 8,738 lb/ft. Sliding passes at 1.58; overturning fails at B = 10 ft (1.43) and passes at B = 14 ft (2.12).

Cantilever walls usually take three to five geometry iterations; the heel is the most effective thing to lengthen because it adds both soil weight and lever arm. The uniform 520-psf surcharge understates the load where the track is close to the wall, so recheck sliding and overturning with the strip load (Section 7.1.3.1) once the track offset is fixed. Railroad walls next to track are usually soldier pile and lagging; a cantilever wall suits a cut transition like this one.

Example 7.1-2: MSE Wall at an Intermodal Yard Throat

A 30-ft MSE wall supports an approach embankment at an intermodal expansion on a Class I railroad located in Kansas City. Each geogrid layer must carry the horizontal earth pressure over its tributary spacing, and must be anchored far enough behind the failure surface not to pull out.

H = 30 ftReinforced fill φ′ = 36°, γ = 125 pcfTrain surcharge q = 520 psfTmax at z = 28 ft = ? FSpo = ?L = 22 ftBearing pressure = ?GivenH = 30 ft; L = 22 ftSv = 2.0 ft; Rc = 1.0; Le = 4.5 ft at 28 ftF* = 0.487; α = 0.8; C = 2q = 520 psf (train)qallow = 6,000 psfRequiredTmax at z = 28 ftPullout factor of safetyBearing pressureBlack = given; red = required
Given and required for Example 7.1-2.

Given

VariableValueDescription
H30 ft
Reinforced fillφ′ = 36°, γ = 125 pcf
GeogridSv = 2.0 ft; Rc = 1.0; Le = 4.5 ft at z = 28 ft
F*, α, C0.67 tanφ′ = 0.487; 0.8; 2FHWA GEC 11 defaults for geogrid
q520 psfTrain surcharge
L22 ftReinforcement length
qallow6,000 psfFoundation

Required

  • Maximum reinforcement load at z = 28 ft
  • Pullout factor of safety
  • Bearing pressure

Equations

  1. Eq. 1: KA = tan²(45° − φ′/2) — Rankine
  2. Eq. 2: σh = KA(γz + q); Tmax = σh Sv
  3. Eq. 3 (FHWA GEC 11): Pr = F* α σ′v Le C Rc — pullout resistance per unit width; C = 2 for geogrid (both faces); α = 0.8 for geogrid
  4. Eq. 4: qb = (γH + q)L / L — simple bearing check

Steps

Step 1 · KA
tan²27°
0.260
↓
Step 2 · Tmax (Eq. 2)
0.260(125 × 28 + 520) = 910 + 135 = 1,045 psf; × 2.0
Tmax = 2,090 lb/ft
↓
Step 3 · Pullout (Eq. 3)
0.487 × 0.8 × 3,500 × 4.5 × 2 × 1.0
Pr = 12,270 lb/ft; FS = 5.9 ≥ 1.5
Spot check: Without C = 2 (one face only), Pr = 6,136 lb/ft and FS = 2.9: still adequate, but understated by half.
↓
Step 4 · Bearing (Eq. 4)
(125 × 30 + 520) = 4,270 psf
4,270 < 6,000 psf
↓
Solution
Tmax = 2,090 lb/ft; pullout FS = 5.9; bearing 4,270 psf.

Solution

Tmax = 2,090 lb/ft at z = 28 ft; pullout FS = 5.9; bearing 4,270 psf against 6,000 psf allowable.

The geogrid must also have a long-term design strength Tal above 2,090 lb/ft after the reduction factors for creep, installation damage and durability (FHWA GEC 11); that comes from the product data. The final design must also check eccentricity of the base reaction, global stability and settlement.

Example 7.1-3: Seismic Earth Pressure on a Gravity Wall

A 15-ft gravity wall on a Class I railroad located near Salem, Oregon, in Seismic Design Category D. The Seed-Whitman simplification adds a seismic increment to the static thrust and applies it higher on the wall, which is why seismic overturning so often governs.

H = 15 ftBackfill φ′ = 32°, γ = 120 pcfPAE = ? ΔPAE = ?kh = 0.25, kv = 0Seismic MOT = ?GivenH = 15 ftφ′ = 32°; γ = 120 pcfkh = 0.25; kv = 0KA = 0.307 (Rankine)Coulomb, δ = 21.3°: 0.275Target FSOT ≥ 1.1RequiredSeismic thrust and incrementSeismic overturning momentBlack = given; red = required
Given and required for Example 7.1-3.

Given

VariableValueDescription
H15 ft
Backfillφ′ = 32°, γ = 120 pcf
kh, kv0.25 and 0
KA0.307 (Rankine)Coulomb with δ = 21.3° gives 0.275
TargetFSOT ≥ 1.1 seismic (assumed)

Required

  • Seismic thrust and increment
  • Seismic overturning moment

Equations

  1. Eq. 1: ΔKAE ≈ ¾ kh; KAE = KA + ΔKAE — Seed and Whitman (1970), φ′ 30° to 40°, kh < 0.3
  2. Eq. 2: P = ½KγH²
  3. Eq. 3: M = PA(H/3) + ΔPAE(0.6H)

Steps

Step 1 · KAE (Eq. 1)
0.307 + 0.75 × 0.25
0.495
Spot check: The full Mononobe-Okabe solution with δ = 21.3° gives 0.476, so the simplified value is slightly conservative.
↓
Step 2 · Forces (Eq. 2)
½ × 0.495 × 120 × 225; ½ × 0.307 × 120 × 225
PAE = 6,683; PA = 4,150; ΔPAE = 2,532 lb/ft
↓
Step 3 · Moment (Eq. 3)
4,150 × 5.0 + 2,532 × 9.0 = 20,750 + 22,790
M = 43,540 ft-lb/ft, 2.1 times the static moment
↓
Solution
Seismic overturning moment 2.1 times the static.

Solution

KAE ≈ 0.495; the seismic increment is 2,532 lb/ft, and the seismic overturning moment is about 43,500 ft-lb/ft, 2.1 times the static value.

The increment acts at 0.6H rather than H/3, so it nearly doubles the moment on its own. In Seismic Design Category D the seismic case usually governs the wall geometry; size the footing for FSOT ≥ 1.1 under this moment.