Global stability analysis (deep-seated failure of the entire wall-soil system) should be performed for walls retaining more than about 10 ft of fill and wherever weak soil underlies the wall. Use Bishop Simplified (Chapter 6.3) or Spencer's method for complex geometries.
Minimum global FS values (Table 7.1-1):
| Railroad | Long-Term FS (static) | Seismic FS | Submerged/Seepage FS | Source |
|---|---|---|---|---|
| Typical | 1.5 | 1.1 | 1.3 | Common practice; confirm with owner |
Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.
Case study: 7.1.16.1 Back-analysis of a failed wall: condemn 330 ft, or not? (Look 2023), in §16.16 Case Studies.