7.1.15 Practice Questions

Retaining structures are among the most consequential geotechnical elements in railroad capital programs.
Authors: Daniel P. Colwell and Mario Ruel
7.1.15 Practice Questions
Each question is worked in the same five parts as the examples.
Question 7.1-1: Rankine Thrust on a Cantilever Wall

Problem Statement

An 18-ft cantilever retaining wall will support the fill for a new main track next to an existing one, with granular backfill and the train surcharge shown. The engineer must compute the active earth pressure coefficient, the thrust from the soil and the added thrust from the train surcharge.

H = 18 ftGranular backfill φ′ = 32°, γ = 118 pcfTrain surcharge q = 520 psfKA, PA, ΔP = ?GivenH = 18 ftφ′ = 32°; γ = 118 pcfq = 520 psfRequired(a) KA (b) PA from soil(c) ΔP from surchargeBlack = given; red = required
Given and required for Question 7.1-1.

Given

VariableValueDescription
H18 ft
Backfillφ′ = 32°, γ = 118 pcf
q520 psf

Required

  • (a) KA
  • (b) PA from soil
  • (c) ΔP from surcharge

Equations

  1. Eq. 1: KA = tan²(45° − φ′/2); PA = ½KAγH²; ΔP = KAqH

Steps

Step 1 · (a)
tan²29°
0.307
↓
Step 2 · (b)
½ × 0.307 × 118 × 324
5,874 lb/ft
↓
Step 3 · (c)
0.307 × 520 × 18
2,877 lb/ft
↓
Solution
KA 0.307; 5,874 and 2,877 lb/ft.

Solution

(a) 0.307. (b) 5,874 lb/ft. (c) 2,877 lb/ft.

The surcharge adds about half as much again as the soil and acts higher on the wall (H/2), so it contributes more than half as much again to the overturning moment.

Question 7.1-2: Sliding, Toe Pressure and the Middle Third

Problem Statement

A gravity retaining wall supports a railroad embankment above a road. The wall carries the vertical load and horizontal thrust shown on an 8-ft base with no shear key. The engineer must check the wall for sliding, compute the toe pressure, and check the middle-third rule.

Gravity wallΣV = 18,000 lb/ftP = 7,200 lb/ftB = 8 fte = 1.2 ft; φ′base = 30°qtoe = ?FSsliding = ? Middle third?Railroad embankmentRoadGivenΣV = 18,000 lb/ftB = 8 ftP = 7,200 lb/fte = 1.2 ftφ′ base = 30°; no key, no adhesionRequired(a) FS sliding(b) Toe pressure(c) Middle-third checkBlack = given; red = required
Given and required for Question 7.1-2.

Given

VariableValueDescription
ΣV18,000 lb/ft
B8 ft
P7,200 lb/ft
e1.2 ft
φ′base30°No key, no adhesion

Required

  • (a) FSsliding
  • (b) Toe pressure
  • (c) Middle-third check

Equations

  1. Eq. 1: FS = ΣV tanφ′ / P
  2. Eq. 2: qtoe = (ΣV/B)(1 + 6e/B)

Steps

Step 1 · (a)
18,000 × 0.577 / 7,200
1.44 < 1.5: marginal
↓
Step 2 · (b)
2,250 × 1.9
4,275 psf
↓
Step 3 · (c)
B/6 = 1.33 ft; e = 1.2 ft
Within the middle third
↓
Solution
Sliding 1.44 (key needed); toe 4,275 psf; middle third OK.

Solution

(a) FS = 1.44, short of 1.5: add a shear key. (b) 4,275 psf. (c) e = 1.2 ft ≤ 1.33 ft: no tension at the heel.

A shear key under the base mobilizes passive resistance; it is usually cheaper than widening the base for sliding alone.

Question 7.1-3: Seismic Increment by Seed and Whitman

Problem Statement

A 16-ft railroad retaining wall in a seismic area carries the static active thrust shown, and the design horizontal seismic coefficient is 0.28. The engineer must compute the seismic increment by the Seed and Whitman method and the moment it adds to the overturning check.

The method of Example 7.1-3.

H = 16 ftBackfill γ = 120 pcf (assumed)ΔKAE, ΔPAE = ?Static PA = 5,500 lb/ftAdded MOT = ?kh = 0.28Givenkh = 0.28H = 16 ftPA = 5,500 lb/ft (static)γ = 120 pcf (assumed)Required(a) ΔKAE (b) ΔPAE (c) Added overturning momentBlack = given; red = required
Given and required for Question 7.1-3.

Given

VariableValueDescription
kh0.28
H16 ft
PA5,500 lb/ftStatic
γ120 pcf (assumed)

Required

  • (a) ΔKAE
  • (b) ΔPAE
  • (c) Added overturning moment

Equations

  1. Eq. 1: ΔKAE ≈ ¾kh; ΔPAE = ½ΔKAEγH²; ΔM = ΔPAE(0.6H)

Steps

Step 1 · (a)
0.75 × 0.28
0.210
↓
Step 2 · (b)
½ × 0.210 × 120 × 256
3,226 lb/ft
↓
Step 3 · (c)
3,226 × 9.6
30,970 ft-lb/ft
↓
Solution
ΔKAE 0.21; ΔP 3,226 lb/ft; ΔM 30,970 ft-lb/ft.

Solution

(a) 0.210. (b) 3,226 lb/ft. (c) 30,970 ft-lb/ft added to the static moment.

Compare: the static moment is 5,500 × 16/3 = 29,330 ft-lb/ft, so the seismic case slightly more than doubles it.

Question 7.1-4: Reinforcement Load and Pullout in an MSE Wall

Problem Statement

A Class I railroad needs an access road wall below its main line, and a reinforced soil wall with geogrid reinforcement has been proposed (the track itself is not carried on the wall). At 22 ft depth the fill properties, spacing, embedment and surcharge are as shown. The engineer must find the horizontal stress, the reinforcement load and the pullout factor of safety.

The method of Example 7.1-2.

z = 22 ftFill γ = 122 pcf, φ′ = 35°Surcharge q = 400 psfσh, Tmax, FSpo = ?Le = 5.0 ftAccess road wall (track not on wall)Givenγ = 122 pcf; φ′ = 35°z = 22 ftSv = 2.0 ft; Rc = 1.0Le = 5.0 ftF* = 0.80 tanφ′; α = 0.8; C = 2q = 400 psfRequired(a) σh (b) Tmax (c) Pullout capacity and FSBlack = given; red = required
Given and required for Question 7.1-4.

Given

VariableValueDescription
Fillγ = 122 pcf, φ′ = 35°
z22 ft
Sv, Rc2.0 ft; 1.0
Le5.0 ft
F*, α, C0.80 tanφ′; 0.8; 2
q400 psfSurcharge

Required

  • (a) σh
  • (b) Tmax
  • (c) Pullout capacity and FS

Equations

  1. Eq. 1: KA = tan²(45° − φ′/2); σh = KA(γz + q)
  2. Eq. 3 (FHWA GEC 11): Pr = F* α σ′v Le C Rc — pullout resistance per unit width; C = 2 for geogrid (both faces); α = 0.8 for geogrid

Steps

Step 1 · (a)
KA = 0.271; 0.271(122 × 22 + 400) = 727 + 108
835 psf
↓
Step 2 · (b)
835 × 2.0
1,670 lb/ft
↓
Step 3 · (c)
0.560 × 0.8 × 2,684 × 5.0 × 2
Pr = 12,030 lb/ft; FS = 7.2
↓
Solution
Tmax 1,670 lb/ft; pullout FS 7.2.

Solution

(a) 835 psf. (b) 1,670 lb/ft. (c) Pr ≈ 12,000 lb/ft, FS ≈ 7.2.

With both faces of the grid counted (C = 2), pullout is rarely critical at depth; it governs near the top of the wall, where σ′v is small. Check the top layers too.

Question 7.1-5: Required Resisting Moment, Static and Seismic

Problem Statement

A soldier pile wall supporting a railroad embankment has the static and seismic overturning moments shown, with required factors of safety of 2.0 and 1.15. The engineer must find the minimum resisting moment the wall must provide and say which case governs.

Railroad embankmentTrackMOT,static = 95,000 ft-lb/ft, FS 2.0MOT,seismic = 155,000 ft-lb/ft, FS 1.15Minimum ΣMR = ? Which governs?GivenMOT,static = 95,000 ft-lb/ftFS static 2.0MOT,seismic = 155,000 ft-lb/ftFS seismic 1.15RequiredMinimum resisting moment ΣMR Governing caseBlack = given; red = required
Given and required for Question 7.1-5.

Given

VariableValueDescription
MOT,static95,000 ft-lb/ftTarget FS 2.0
MOT,seismic155,000 ft-lb/ftTarget FS 1.15

Required

  • Minimum ΣMR

Equations

  1. Eq. 1: ΣMR ≥ FS × MOT

Steps

Step 1 · Static
2.0 × 95,000
190,000
↓
Step 2 · Seismic
1.15 × 155,000
178,250
↓
Step 3 · Governing
Static: 190,000 ft-lb/ft
↓
Solution
ΣMR ≥ 190,000 ft-lb/ft (static governs).

Solution

ΣMR ≥ 190,000 ft-lb/ft; the static case governs here.

The seismic moment is larger, but the lower factor of safety allowed for the rare event means static still governs. Lengthening the base, typically from about 11 to 14 ft for a 22-ft cantilever wall, provides the extra lever arm.