↑ Parent Menu⌂ Main Menu
← Chapter 7.1 Retaining Structures
GHRM
Railway Ground Hazard Risk Management · 7.0 · Design
Sections · click a car to open it

7.1.16 Case Studies

Retaining structures are among the most consequential geotechnical elements in railroad capital programs.
Authors: Daniel P. Colwell and Mario Ruel
7.1.16 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S11 under Supplemental References.

Case Study 16.16.1 — Back-analysis of a failed wall: condemn 330 ft, or not?
Case study · Look (2023) §13.12

Related section: 7.1.5 Global Stability of Retaining Structures

In an extreme 2008 rainfall, 79 ft of a ten-year-old retaining wall, about 6.6 ft high, failed. The client proposed to condemn the remaining 328 ft as well, a replacement of over AU$1 million, because a back-analysis of the failure using saturated soil mechanics, a single-stage failure and a high water table gave the intact wall a factor of safety below 1.2 (Look, 2016).

The failed and intact sections were not alike:

  • The failed section was lower (under 6.6 ft against about 13 ft) but had a back slope over 20°; the analysis had assumed under 10°, which held everywhere else. The change fell on a single cross section of those drawn every 33 ft and was missed in detailing.
  • It sat in a gully with a catchment six times larger.
  • A water pipe had burst above it.
  • It had deeper colluvium.

No groundwater had ever been seen at this elevated road, and residents reported the failure developed over two days. Coupling finite element seepage with limit equilibrium showed that rainfall reduced soil suction rather than raising a water table. The three back-analyses led to three conclusions for the intact wall:

  • FS < 1.2: high water table, single-stage failure, so demolish and replace.
  • FS = 1.3: high water table, progressive failure, so acceptable for an existing wall but not a new one.
  • FS = 1.6: unsaturated soil with loss of suction, progressive failure, so the intact wall is acceptable.

The intact wall had since come through several large storms with no distress. Look’s lessons: saturated and unsaturated analyses can disagree; back-analysis carries its assumptions into the result; a factor of safety is a decision tool, not an end in itself; and analysis is not design. A slope above a wall can raise active pressure by a factor of three, so the lowest wall is not necessarily the lowest load.

For railroad work: before parameters from a failed retaining wall or cut are applied to the rest of a structure, compare catchment, back slope, water sources and soil depth section by section. Antecedent rainfall, not daily rainfall alone, is the trigger to compare.

Assumed versus actual differences between the failed and stable sections: burst pipe, catchment six times larger, back slope over 20°.
Figure 16-LK1. Assumed versus actual differences between the failed and stable sections: burst pipe, catchment six times larger, back slope over 20°. Source: Look (2023), Figure 13.12-3, p. 487.
Wall cross sections every 33 ft: the back slope exceeded the analysis assumption at the one section that failed.
Figure 16-LK2. Wall cross sections every 33 ft: the back slope exceeded the analysis assumption at the one section that failed. Source: Look (2023), Figure 13.12-5, p. 488.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §13.12, pp. 484–490. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 16.16.2 — Design detailing and analysis input: short case notes
Case study · Look (2023) §13.13

Related section: 7.1.12 Practical Recommendations

Look closes the design chapter with several short cases where the analysis was right but the detail or the input was not:

  • Unloading broke a sewer. A surcharge for ground improvement extended past the site boundary over two pipes. After 15 months, with the ground improved, the fill was being removed to build a two-level sleeper wall. An excavator working at the crest cut too steep an edge, the edge failed, and the council’s sewer, 3.3 ft from the boundary, ruptured into adjacent wetlands. Design had looked at improvement and long-term stability but not at pipe strains from loading and unloading.
  • The lower wall governed. In the back-analysis case (§16.5), the shorter section with a back slope was the critical one, not the tallest.
  • 95% density does not give one modulus. At the same density ratio, compacted fills from sandstone, interbedded siltstone/sandstone and basalt gave plate load EV2 of about 10,000, 5,800 and 9,400 psi. Typical values: well-compacted, well-graded base 29 ksi or more, subbase 100 or more, working platform 60 or more, granular subgrade 50, cohesive subgrade 25. Resilient modulus is not the same as E; for one clay, Mr was about 2E.
  • Friction angle depends on fill and roller. In-situ friction of compacted weathered-rock fill rose from about 37° at 90% density to 43° at 100%, but varied with source rock and roller type.
  • Side-long fills crack. Old “goat tracks” widened by pushing fill down the hillside develop longitudinal cracks however good the compaction. Bench the cut-to-fill interface, or use another detail where steep hard rock prevents benching.

For railroad work: side-hill fills are among the most common chronic slide sites on mountain and river-grade lines. When one is rebuilt, the benching or keying detail matters as much as the stability analysis. Surcharge and unloading near buried utilities that cross the right-of-way need their own deflection check.

Longitudinal cracking and instability at a side-long fill over weathered rock and colluvium.
Figure 16-LK3. Longitudinal cracking and instability at a side-long fill over weathered rock and colluvium. Source: Look (2023), Figure 13.13-3, p. 493.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §13.13, pp. 490–494. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

← Previous · 6.0 Analysis Chapter 6.6 — Tunnels and Portals
Next · 7.0 Design → Chapter 7.2 — Ground Improvement Methods