Soldier piles with lagging are this manual’s standard wall for stabilizing a slope or shoring an excavation next to track: the piles are driven or set in drilled holes from the shoulder, the lagging goes in as the face is excavated, and nothing has to be built behind the wall under the track. A cantilever wall relies only on the embedment of the piles below the excavation, so it suits retained heights up to about 10 to 15 ft; above that, or where deflection limits are tight, tiebacks or rakers are added (Section 7.1.4.7 for anchor bond). The analysis differs from a sheet pile wall (Section 7.1.18) in two ways. Above the excavation the lagging collects earth and surcharge pressure over the full pile spacing and delivers it to each pile. Below the excavation the pile is a discrete element and mobilizes passive resistance over more than its own width.
Driving load per pile per foot of depth is w = s(Kaγz + Kaq + σE80) above the excavation and b(Kaσv + Kaq + σE80) below it, where σE80 is the Cooper E80 strip pressure of Section 7.1.17 (Eq. 7.1-3). Passive resistance below the excavation follows Eq. 7.1-6 (discrete pile) or the arching factor below, divided by a factor of safety. The embedment D0 is found from moment equilibrium about the toe and increased by 20% (some guidelines 30%) for the reverse pressure near the toe, as for the sheet pile wall.
Equation 7.1-9. Passive resistance of a soldier pile by the arching factor
Caltrans Trenching and Shoring Manual; d = depth below the excavation; b = flange width or drilled-hole diameter; s = spacing. Railroad temporary shoring commonly applies FS = 1.5 to passive resistance.
Equation 7.1-10. Timber lagging thickness
p = design pressure behind the lagging (psf), reduced for soil arching where permitted; l = clear span between flanges (ft); M in lb-in. per ft of height; Fb = allowable bending stress of the timber (psi).
The maximum moment per pile occurs at the point of zero shear below the excavation; the required section modulus is M/fb. Deflection, not strength, usually governs next to track: the railroad shoring guidelines limit horizontal movement within the track influence zone, so check deflection with a beam-on-spring or p-y model, and add anchors where the cantilever is too flexible.
A 10-ft cut for a drainage structure on a Class I railroad located in Georgia is shored with a cantilever soldier pile wall whose face is 16 ft from the nearest track centerline. Piles are set in 24-in. drilled holes at 8-ft centers, with timber lagging.
| Variable | Value | Description |
|---|---|---|
| H | 10 ft | Retained height |
| s, b | 8 ft; 24 in. = 2.0 ft | Spacing; hole diameter |
| Retained soil | γ = 120 pcf, φ′ = 32° | Above the excavation |
| Embedment soil | γ = 125 pcf, φ′ = 34° | Dense sand below |
| q | 250 psf | Construction and spoil surcharge |
| E80 | 80,000/(5 × 9) = 1,778 psf strip, 9 ft wide | Track centerline 16 ft from the wall |
| FSp | 1.5 | On passive resistance |
| fb, Fb | 33 ksi; 1,000 psi | Pile; timber lagging |
A cantilever wall works in strength with 30-ft piles, a section of at least 165 in.³ (for example a W21×83 at 171 in.³ set in the drilled hole) and 5-in. lagging.
The train surcharge more than doubles the load on the wall, and the cantilever will be flexible: at 10 ft retained and 16 ft from track, expect deflection near the railroad’s limit. Run a deflection check before submitting; if it fails, a single row of tiebacks at about 3 ft below the top cuts both moment and deflection sharply. Where the railroad accepts a 0.6 arching factor on lagging pressure, the computed lagging falls to about 3.7 in., and 4-in. rough-cut boards would do.
Open the soldier pile wall calculator →
Active pressure over the spacing and the pile width, uniform and E80 strip surcharges, passive resistance by the arching factor or Eq. 7.1-6 (with softened clay), embedment by moment equilibrium, maximum moment, section modulus and lagging thickness.
The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.