5.3.6 Settlement Monitoring

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.6 Settlement Monitoring
5.3.6.1 Settlement Plates

Settlement plates are installed at the base of embankment construction to measure total settlement of the underlying foundation soils during and after filling. They consist of a steel plate (24 in. × 24 in. × ¼ in.) with a vertical measurement rod extending through the embankment fill.

Settlement measurement:

S = E_initial − E_reading (in. or ft)

where E_initial = initial elevation of plate top (ft); E_reading = current survey elevation (ft).

Settlement plates are read by differential leveling survey with ±0.01 ft precision. Reading frequency:

Table 5.3-2. Settlement Plate Reading Frequency by Construction Stage
StageReading FrequencyPurpose
Embankment filling (active)Daily or each fill liftTrack rate of settlement vs. fill height
End of fillingDaily for first 2 weeksConfirm no sudden increase
Consolidation monitoringWeekly for first 3 monthsConfirm consolidation progressing per design
Long-term monitoringMonthly until ΔS < 0.01 ft/monthConfirm primary consolidation complete

Deliver settlement plate data to the project engineer within 24 hours of each reading during active filling.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
Ereadingcurrent survey elevation (ft).Field or lab measurementRecorded during the test or monitoring (readings, times, dimensions of the test setup).project-specific
5.3.6.2 Embankment Fill Rate Control

During staged construction over soft ground (Chapter 7.2), the fill rate must be controlled to prevent undrained shear failure. The maximum safe fill rate:

ΔH_max ≈ 5.14 × Δs_u / (γ_fill × FS) (ft per stage; Chapter 2.5, Eq. 21-10 applied to the strength gain)

where:

  • Δs_u = strength gain since the previous stage ≈ (s_u/σ'_v) × U × Δσ (Chapter 2.5, Section 2.5.7)
  • γ_fill = unit weight of fill = 120–130 pcf
  • FS = required end-of-construction factor of safety, commonly 1.3 (USACE EM 1110-2-1902); check every stage with a stability analysis

Field monitoring trigger: if settlement rate increases disproportionately to fill rate (creep rupture indicator), suspend filling immediately and notify the geotechnical engineer. A common trigger is ΔS > 1 in./day without new fill added.

Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
ΔSustrength gain of subgrade per inch of consolidation (SHANSEP, Chapter 7.2)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
γfillunit weight of fill = 120–130 pcfLab testWeigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w).sands 105–135, clays 95–130 pcf · by USCS group
FSsloperequired slope stability FS ≥ 1.25 (short-term per AREMA/USACE)Design criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.project-specific
Supplemental reference

Monitoring track support after construction: wayside instrumentation and GPR

Wayside monitoring of fouled ballast (FRA and Class I railroad waiver research). Under an FRA waiver from 49 CFR §213.103 (2017–2019, 340 route miles of Class I track), six solar-powered wayside sites near Lincoln, NE and Kansas City, MO recorded rail and tie strain, accelerations, video displacement and ballast moisture from 2017 to 2020. Support was measured by the distribution efficiency DE = PDist/PC × 100%, where PC is the wheel load from crib strain gauges and PDist is the load still carried by the rail over the tie. DE = 100% is a hanging tie, and a well-supported tie carries about 40% (DE ≈ 40%). Findings:

  • Fouling at every site was CL–CH clay at or near its liquid limit — derived from the subgrade, not ballast breakdown or spillage.
  • At Parkville, MO, DE was 29% while frozen and 47% after thaw, and rose to 71% with repeated freeze–thaw. Surfacing brought it back to 36% (about a 50% stiffness gain). Fouled ballast took up to 7 days to freeze but only 1–3 days to thaw, so stiffness is lost faster than it is gained.
  • Higher-plasticity fouling produced larger freeze–thaw swings than more visible but lower-PI fouling: the type of fouling may matter more than the amount. Concrete-tie sites were more sensitive to rain and freeze–thaw than timber-tie sites.

Network GPR. The railroad has used ground-penetrating radar since 2009 and in 2018 added it to its train-based geometry car (Figure 15-S1). It reports a Ballast Fouling Index (BFI, the GPR estimate of Selig’s FI = P4 + P200 in the top 16 in.) for the center and shoulders, and since 2018 a Free Draining Layer depth (FDL, 0–16 in. of clean ballast above the fouled zone; Figure 15-S2). Calibration used an automated “Vibro Sampler” for physical gradations. The goal is to group track reliably into clean, moderate and fouled rather than to match FI exactly. BFI and FDL, with geometry, tonnage and maintenance history, feed a model that chooses among surfacing, shoulder ballast cleaning (fast, but does not fix high center fouling), track lifting and undercutting (productivity drops with high fines and moisture), and ditching. For geotechnical work, low FDL with clay-type fines points to a subgrade source, which ballast cleaning alone will not cure.

GPR antennas on a Class I railroad&rsquo;s train-based track geometry inspection platform.
Supplemental Figure 15-S1. GPR antennas on the railroad's train-based track geometry inspection platform. Source: Bankston, A. and Wilk, S. (TTCI) (2021). “Use of Track Based Inspection Technologies to Improve the railroad's Ballast Maintenance Planning.” AREMA 2021 Annual Conference.
Ballast Fouling Index (BFI) and Free Draining Layer (FDL) as measured by GPR.
Supplemental Figure 15-S2. Ballast Fouling Index (BFI) and Free Draining Layer (FDL) as measured by GPR. Source: Bankston, A. and Wilk, S. (TTCI) (2021). “Use of Track Based Inspection Technologies to Improve the railroad's Ballast Maintenance Planning.” AREMA 2021 Annual Conference.

Source: Stark, T. D., Thompson, H. B., Sussmann, T. R., Bruzek, R. and Banister, R. (2021). “Long-Term Field Monitoring of Fouled Ballast.” AREMA 2021 Annual Conference · Bankston, A. and Wilk, S. (TTCI) (2021). “Use of Track Based Inspection Technologies to Improve the railroad's Ballast Maintenance Planning.” AREMA 2021 Annual Conference

Figure 5.3-13. Flow chart of planning and implementation stages for track renewal and maintenance (years N−3 to N+1). Profillidis Fig. 16.12.
Figure 5.3-13. Flow chart of planning and implementation stages for track renewal and maintenance (years N−3 to N+1). Profillidis Fig. 16.12.

Geometry acceptance after construction or maintenance

After tamping, a survey crew sets the lift and line corrections, the tamper corrects and compacts under the ties, and a recording car checks the remaining defects against acceptance values. Stabilizing machines that follow the tamper raise lateral resistance. If heavy machinery does the leveling, no further lifts should be made until traffic has stabilized the track. Defects left after that period are corrected with light equipment without re-lifting.

Figure 5.3-12. Tamping machine during track maintenance. Profillidis Fig. 16.9.
Figure 5.3-12. Tamping machine during track maintenance. Profillidis Fig. 16.9.
Table 5.3-7. Acceptance values of track defects after maintenance (European practice)
Track speed (mph)> 155124–15575–124> 50< 50
Longitudinal defect (in.)0.0790.120.120.160.2
Horizontal defect (in.)0.0790.120.120.160.2
Track twist (in./ft)0.0120.0120.0120.0180.018
Track gauge (in.)±0.079±0.079±0.079±0.12±0.12

The period up to about 2 million tons after the work (about 1–4 months on a UIC group 4 line, 15–40 days on busier lines) is when defects grow fastest. Profillidis calls continuous monitoring and prompt local correction during this period the key to track longevity. The same window applies after subgrade repairs, undercutting and new embankment tie-ins.

After Profillidis (2014), §16.6.3, §16.8–16.10, Table 16.3, Figs. 16.9, 16.12. Full reference under Supplemental References.