Survey points, settlement plates and inclinometers measure movement precisely at a few points. Satellite radar interferometry (InSAR) and laser scanning (LiDAR) measure it over whole areas, which makes them useful for screening long corridors and for finding movement nobody knew to instrument. They complement, but do not replace, ground instruments (Gupta 2018; Jaboyedoff et al. 2018).
| Method | What it measures | Typical accuracy | Limits |
|---|---|---|---|
| Leveling, total station | Points | About 0.004 in. (0.1 mm) height change | Point based, labor intensive, needs access |
| GPS (GNSS) | Points | About 0.2 in. static; about 1 in. RTK | Point based; sky view needed |
| Differential InSAR | Area: change in distance along the satellite line of sight between two radar images | About 0.4 in. per interferogram | Loses coherence over vegetation, snow, water and fast movement; atmospheric delay |
| Persistent scatterer InSAR (PSInSAR) | Movement history of stable reflectors (roofs, bridges, towers, rock) from many images | Millimeters per year | Only where stable reflectors exist; slow movement only |
| Airborne LiDAR (ALS) | Bare-earth elevation model over large areas | About 2 to 12 in. position; historically 1 to 2 points per m², now about ten times more | Poor on steep and overhanging faces; dense forest limits ground returns |
| Terrestrial LiDAR (TLS) | Point cloud from a tripod | About 0.4 in.; up to thousands of points per ft² at short range | Shadowed areas need several setups; range limits |
A radar satellite records both the strength and the phase of the reflected signal. Differencing the phase of two images taken from nearly the same orbit at different times gives an interferogram, whose color fringes each represent one wavelength of change in distance to the ground. The processing steps are image registration, interferogram generation, a coherence check (0 to 1; low coherence means the result is unreliable), phase unwrapping to remove the 2π ambiguity, and conversion to displacement or height. Results are along the line of sight, so movement perpendicular to it (largely north–south for most orbits) is poorly seen; combining ascending and descending passes separates vertical and east–west movement. Atmospheric delay can mimic deformation and is corrected with GPS or by using many images. PSInSAR uses dozens of images and only the pixels that stay stable, overcoming the loss of coherence over vegetation, and gives millimeter-per-year movement histories.
LiDAR measures distance by timing laser pulses and builds a point cloud. Airborne LiDAR records several returns per pulse, so gaps in vegetation let some pulses reach the ground and a bare-earth model can be built from them; the shaded relief of that model shows old landslide scarps, hummocky ground and debris-flow fans under forest. Airborne surveys see the ground from above and represent steep rock faces poorly. Terrestrial scanners set up on a tripod are far denser and more accurate and see steep and overhanging faces, which makes them the tool for rock cuts. Repeat surveys are differenced to detect change, such as rockfall sources, bulging and erosion. Small registration errors between surveys produce apparent change, so only differences clearly larger than the combined survey error should be read as movement.
For railroad work: Use PSInSAR as a screen along long lengths of line for slow settlement over old mines, karst, groundwater withdrawal and soft ground; rails, structures and rock are good reflectors. Treat any anomaly as a reason to survey, not as a measurement, and remember that track maintenance lifts and resurfacing reset the track but not the ground. Use airborne LiDAR in the desktop study to map landslide terrain on forested slopes above and below the line (Chapter 3.2), and repeat terrestrial or mobile scanning of rock cuts to find developing rockfall sources (Chapter 3.8). Agree the survey accuracy and the change threshold before the second survey, not after.
Practice: Question 5.3-7 (Section 5.3.17) converts ascending and descending line-of-sight rates into vertical and horizontal movement.
Source: Gupta (2018); Jaboyedoff et al. (2018). Full references under Supplemental References.
Static GNSS measures the three-dimensional position of a monitoring antenna relative to a reference antenna on stable ground. Repeated sessions give displacement automatically and continuously, day and night, without a line of sight between points (Shimizu and Nakashima, in Feng 2017). The ISRM suggested method sets out the procedure and the error corrections:
For railroad work: GNSS suits slow-moving landslides above or below track, cut slopes, embankments on soft ground and long structures. The points can be kilometers apart and the work can be read without track time. Mount antennas on stable concrete pillars or deep-founded posts, not on fence posts or ballast. Keep the reference antenna outside the moving ground and within about 1 km, at a similar elevation where possible. Combine GNSS with InSAR (area-wide screening) and with inclinometers (depth of movement). GNSS shows how fast the surface is moving, InSAR shows where, and the inclinometer shows how deep.
Source: Shimizu and Nakashima, “Review of GPS displacement monitoring in rock engineering,” in Feng (ed.) (2017), Ch. 19. Summarized and paraphrased; units converted. Full reference under S27.