Culvert headwalls, wall caps, drainage structures and drilled shafts all bring concrete into a geotechnical project, and the geotechnical engineer is often the one in the field when the cylinder results come back. The PCA's Design and Control of Concrete Mixtures sets out the ACI 318 sequence. A mix is proportioned for a required average strength f'cr, which is higher than the specified f'c by a margin that depends on how variable the producer's results have been. Strength tests are then judged on running averages of three, not on single cylinders. Bungey's Testing of Concrete in Structures covers what to do when the cylinders fail: cores, rebound hammer and pulse velocity, and how much weight each deserves.
Equation 5.3-3. Required average strength (ACI 318), f'c ≤ 5000 psi
| Condition | Requirement |
|---|---|
| Standard deviation s from 15, 20 or 25 tests | Multiply s by 1.16, 1.08 or 1.03 (1.00 at 30 or more) |
| No test record, f'c under 3000 psi | f'cr = f'c + 1000 |
| No test record, f'c 3000 to 5000 psi | f'cr = f'c + 1200 |
| No test record, f'c over 5000 psi | f'cr = 1.1f'c + 700 |
| Acceptance of strength tests | Every average of 3 consecutive tests ≥ f'c, and no single test more than 500 psi below f'c (10% below when f'c exceeds 5000) |
| Cores in suspect concrete | Average of 3 cores ≥ 85% of f'c and no core below 75% |
| Sampling frequency (one railroad's general specification) | One set per day's pour, plus one set for each 50 cu yd beyond the first 50 cu yd of a class; one 7-day cylinder per set |
| 28-day strength (psi) | Non-air-entrained | Air-entrained |
|---|---|---|
| 2000 | 0.82 | 0.74 |
| 3000 | 0.68 | 0.59 |
| 4000 | 0.57 | 0.48 |
| 5000 | 0.48 | 0.40 |
| 6000 | 0.41 | 0.32 |
| 7000 | 0.33 | – |
The calculator interpolates for f'cr and takes the lower of this value and the durability limit. PCA's own worked example reads w/cm from a material-specific trial-batch curve, so it differs from the table; use trial batches where they exist.
For a 4000 psi air-entrained mix from a producer with s = 300 psi over 30 tests, f'cr = max(4000 + 1.34×300, 4000 + 2.33×300 − 500) = 4,402 psi, matching PCA's example. The table gives w/cm 0.45 for that strength, which controls over a 0.50 exposure limit. A 120 cu yd pour in one day needs 3 sets of cylinders. The eight sample results average 4,168 psi: every running average of three meets 4000 psi and no test falls below 3500 psi, so the concrete is accepted even though two single results are below f'c. With no test record the same mix would have to be proportioned for 5,200 psi.
Open the concrete acceptance calculator →
Required average strength, w/cm for strength and durability, the number of cylinder sets per pour, running-average and single-test acceptance, and core acceptance.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads, clients and projects are not named.