↑ Parent Menu⌂ Main Menu
← Chapter 5.3 Construction Monitoring and Field Testing
GHRM
Railway Ground Hazard Risk Management · 5.0 · Testing
Sections · click a car to open it

5.3.17 Practice Questions

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.17 Practice Questions
Each question is worked in the same five parts as the examples.
Question 5.3-1: Field Dry Density and Acceptance

Problem Statement

A nuclear gauge test was taken on a lift of embankment fill for a new Class I railroad siding. The gauge gave the wet density and moisture shown, and the railroad’s specification requires at least 92% relative compaction. The inspector must compute the dry density and relative compaction and decide whether the lift passes.

Previous liftsEmbankment lift, new sidingNuclear gaugeprobeγd = ? RC = ? Pass or fail?WD = 135.8 pcf; w = 9.5%GivenWD = 135.8 pcfw = 9.5%γd,max = 130.2 pcfSpec: RC ≥ 92%Required(a) γd (b) RC(c) Pass or failBlack = given; red = required
Given and required for Question 5.3-1.

Given

VariableValueDescription
WD135.8 pcf
w9.5%
γd,max130.2 pcf
SpecRC ≥ 92%

Required

  • (a) γd
  • (b) RC
  • (c) Pass or fail

Equations

  1. Eq. 1: γd = WD / (1 + w) — dry density from the gauge wet density and moisture
  2. Eq. 2: RC = γd / γd,max × 100% — relative compaction

Steps

Step 1 · (a) γd
135.8 / 1.095
124.0 pcf
↓
Step 2 · (b) RC
124.0 / 130.2
95.2%
↓
Step 3 · (c) Compare
95.2% ≥ 92%: pass
↓
Solution
RC = 95.2%: pass.

Solution

(a) 124.0 pcf. (b) 95.2%. (c) Passes.

A moisture check against the specification window should accompany every density test.

Question 5.3-2: Davisson Offset Limit for a Load Test

Problem Statement

A static load test was run on a 12-in. concrete test pile for a new railroad bridge. At 300 kips the pile head had settled 0.68 in. The engineer must compute the Davisson offset limit for the pile and say whether failure has been reached at that load.

Settlement (in.)Load Q (kips)elastic QL/AEDavisson offset = ?300 kips at 0.68 in.Failure at 300 kips?GivenQ = 300 kips; δ = 0.68 in.L = 60 ft (720 in.); D = 12 in.A = 113.1 in.²E = 3,824,000 psiRequiredDavisson offset limitHas failure occurred?Black = given; red = required
Given and required for Question 5.3-2.

Given

VariableValueDescription
Q300 kips
L60 ft = 720 in.
D12 in.
A113.1 in.²
E57,000√4,500 = 3,824,000 psi
δ0.68 in.Measured settlement

Required

  • Davisson offset limit and whether failure has occurred

Equations

  1. Eq. 1: Δf = QL/(AE) + D/120 + 0.15 — inches

Steps

Step 1 · Elastic shortening
300,000 × 720 / (113.1 × 3,824,000) = 216.0×106 / 432.5×106
0.499 in.
↓
Step 2 · Δf
0.499 + 0.10 + 0.15
0.749 in.
↓
Step 3 · Compare
0.68 < 0.749
Not failed
↓
Solution
Limit 0.75 in.; 0.68 in. measured: not failed.

Solution

Davisson limit 0.75 in.; measured 0.68 in., so failure has not occurred at 300 kips.

Continue loading; the Davisson capacity is the load at which the load-settlement curve crosses the offset line.

Question 5.3-3: Vibrating Wire Piezometer Reading and ru

Problem Statement

A railroad embankment over soft clay is being built in stages, with a vibrating-wire piezometer in the clay. Six feet of fill was placed in the last 24 hours, bringing the total to 14 ft, and the readings changed as shown. The engineer must compute the excess pore pressure and pore pressure ratio and decide whether filling can continue against the trigger of 0.50.

Fill 14 ft at 120 pcf (6 ft in 24 h)Soft clayVW piezometerR0 = 8,250 → R1 = 8,180 digitsΔu = ? ru = ? Continue filling?GivenR0 = 8,250; R1 = 8,180 digitsG = 0.075 psi/digitFill 14 ft at 120 pcf6 ft placed in last 24 hTrigger ru = 0.50Required(a) Δu(b) Stresses(c) ru (d) Can filling continue?Black = given; red = required
Given and required for Question 5.3-3.

Given

VariableValueDescription
R0, R18,250 and 8,180 digitsReading falls as pressure rises
G0.075 psi/digit
Fill14 ft at 120 pcf, 6 ft placed in the last 24 hours
Triggerru = 0.50

Required

  • (a) Δu
  • (b) Stresses
  • (c) ru
  • (d) Can filling continue?

Equations

  1. Eq. 1: Δu = G(R0 − R1)
  2. Eq. 2: ru = Δu / σv,all fill

Steps

Step 1 · (a) Δu
0.075 × 70 = 5.25 psi
756 psf
↓
Step 2 · (b) Stresses
Last lift 720 psf; all fill 1,680 psf
↓
Step 3 · (c) ru
756 / 1,680
0.45 (756/720 = 1.05 is meaningless)
↓
Step 4 · (d) Decision
Below 0.50: continue, but closely
↓
Solution
ru = 0.45: continue with closer monitoring.

Solution

(a) 756 psf. (b) 720 psf from the lift, 1,680 psf from all fill. (c) ru = 0.45. (d) Filling may continue, with more frequent readings.

Always compute ru against all the fill above the instrument: excess pore pressure from earlier lifts is still present, so dividing by the last lift alone overstates it.

Question 5.3-4: Inclinometer Movement Rates

Problem Statement

An inclinometer at the toe of a new railroad embankment over soft ground recorded the weekly cumulative deflections shown. The monitoring plan sets alert and action rates for movement toward the fill. The engineer must compute the weekly movement rates, identify any trigger levels reached and state the required response.

DepthCurves left to right:Wk 1: 0.15 in.Wk 2: 0.38 in.Wk 3: 0.65 in.toward fillWeekly increments = ?Alert 0.25 / action 0.50 in./wk reached?GivenCumulative: 0.15, 0.38, 0.65 in.Weeks 1, 2, 3Alert 0.25 in./weekAction 0.50 in./weekRequired(a) Weekly increments(b) Trigger levels reached(c) Required actionBlack = given; red = required
Given and required for Question 5.3-4.

Given

VariableValueDescription
Readings0.15, 0.38, 0.65 in.Weeks 1, 2, 3
LevelsAlert 0.25 in./week; action 0.50 in./weekMonitoring plan

Required

  • (a) Weekly increments
  • (b) Trigger levels reached
  • (c) Required action

Equations

  1. Eq. 1: Δ = readingn − readingn−1

Steps

Step 1 · (a) Increments
0.23 and 0.27 in./week
↓
Step 2 · (b) Levels
0.27 > 0.25: alert; neither reaches 0.50
↓
Step 3 · (c) Action
Notify the engineer; read daily; re-run stability; prepare to escalate
↓
Solution
Alert level reached in week 3.

Solution

(a) 0.23 and 0.27 in./week. (b) Alert level in week 3; action level not reached. (c) Alert response: notify, read daily, check stability.

The rate is increasing, which matters more than its size: an accelerating inclinometer is the classic warning before a slide.

Question 5.3-5: Proof Roll Failures and Rework

Problem Statement

Proof rolling of the subgrade for a new Class I railroad siding found two soft spots, where density tests gave 88.2% and 86.5% against a 92% minimum. After rework, the retest gave the density shown. The inspector must state the corrective action and decide whether the retest passes.

Subgrade, new siding (92% minimum)Proof rollerRC 88.2%RC 86.5%ruts > ½ in.Corrective action = ?Retest: γd 126.8 / 133.5 pcf passes?GivenTwo soft spots, ruts > ½ in.RC 88.2% and 86.5% vs 92%Retest γd = 126.8 pcfγd,max = 133.5 pcfRequired(a) Corrective action(b) Does the retest pass?Black = given; red = required
Given and required for Question 5.3-5.

Given

VariableValueDescription
Soft spotsTwo stations, ruts over ½ in.Proof roll
RC88.2% and 86.5%Against 92% minimum
Retestγd = 126.8 pcf; γd,max = 133.5 pcfAfter rework

Required

  • (a) Corrective action
  • (b) Whether the retest passes

Equations

  1. Eq. 1: RC = γd/γd,max

Steps

Step 1 · (a) Action
Overexcavate to firm soil; backfill in 6-in. loose lifts; compact and test each lift
↓
Step 2 · (b) RC
126.8 / 133.5
95.0% ≥ 92%: pass
↓
Solution
Overexcavate and rebuild; retest passes at 95.0%.

Solution

(a) Remove the soft material and rebuild in tested 6-in. lifts. (b) RC = 95.0%: passes.

Record the failing tests, the rework and the passing retest in the daily report. A proof roll finds what a spot density test misses, which is why both are used.

Question 5.3-6: Hyperbolic Settlement Prediction at a Bridge Approach

Problem Statement

A new approach embankment for a bridge on a Class I railroad located in South Carolina was built on soft clay without drains. The plate under the fill had settled 4.0 in. by the end of fill placement, and it has been read every 30 days since. Track is scheduled to be laid 180 days after the fill was finished. The engineer must predict the final settlement, the settlement still to come when the track is laid, and when 90% of the post-construction settlement will have occurred, so the railroad can plan resurfacing at the bridge end.

050100150 05101520 Time since end of fill, t′ (days) t′ / Δs (days per in.) Required: intercept a Required: slope b → sf = s0 + 1/b Given s0 = 4.0 in. at end of fill Settlement since end of fill, Δs: t′ = 30 d: 3.6 in.t′ = 60 d: 5.6 in.t′ = 90 d: 6.8 in.t′ = 120 d: 7.7 in. Track to be laid at t′ = 180 d Requiredsf; settlement left at 180 d;time to 90% of Δsf
Figure 5.3-21. Question 5.3-6: hyperbolic plot of the plate readings.

Given

VariableValueDescription
s04.0 in.Settlement at the end of fill placement (t′ = 0)
Δs at t′ = 30, 60, 90, 120 days3.6, 5.6, 6.8, 7.7 in.Settlement since the end of fill
ttrack180 daysTrack placement after the end of fill

Required

  • (a) Hyperbola constants a and b, and final settlement sf
  • (b) Settlement remaining when the track is laid
  • (c) Time to 90% of the post-construction settlement

Equations

  1. Eq. 5.3-10: t′/Δs = a + b t′; sf = s0 + 1/b
  2. Eq. 1: Δs(t′) = t′ / (a + b t′) — the same hyperbola solved for settlement
  3. Eq. 2: t′90 = 9a/b — from b t′/(a + b t′) = 0.9

Steps

Step 1 · Plot values t′/Δs
30/3.6; 60/5.6; 90/6.8; 120/7.7
8.33, 10.71, 13.24, 15.58 days/in.
↓
Step 2 · (a) Fit the line
x̄ = 75, ȳ = 11.965; Sxy = 364.2, Sxx = 4,500; b = 364.2/4,500; a = 11.965 − 0.0809 × 75
b = 0.0809 per in.; a = 5.90 days/in.
↓
Step 3 · (a) Final settlement
4.0 + 1/0.0809
sf = 16.4 in. (12.4 in. after the end of fill)
Spot check: At t′ = 120 days the fit gives 120/(5.90 + 9.71) = 7.69 in., matching the 7.7 in. read.
↓
Step 4 · (b) Remaining at track placement
Δs(180) = 180/(5.90 + 0.0809 × 180) = 180/20.46 = 8.8 in.; 12.4 − 8.8
About 3.6 in. still to come
↓
Step 5 · (c) Time to 90%
9 × 5.90 / 0.0809
t′90 ≈ 660 days (about 22 months)
Spot check: At 660 days Δs = 660/(5.90 + 53.4) = 11.1 in. = 90% of 12.4 in.
↓
Solution
sf ≈ 16.4 in.; about 3.6 in. still to come at 180 days; 90% at about 22 months.

Solution

(a) a = 5.90 days/in., b = 0.0809 per in., sf ≈ 16.4 in. (b) About 3.6 in. remains when the track is laid. (c) About 660 days after the end of fill.

Laying track at 180 days means about 3.6 in. of further settlement at the bridge end, most of it in the first year, against a rigid abutment. Either delay track, add a surcharge, or plan for repeated surfacing and a transition at the approach (Chapter 6.2, Section 6.2.7). The hyperbolic method tends to over-predict final settlement when it is fitted to early readings, so refit as readings come in and compare with an Asaoka plot (Section 5.3.26).

Question 5.3-7: Turning InSAR Line-of-Sight Rates Into Vertical Settlement

Problem Statement

A persistent scatterer InSAR screen along a line of a Class I railroad located in Illinois flags a bridge pier over old coal mine workings. The pier is a stable reflector seen from both ascending and descending satellite passes. The engineer must convert the line-of-sight rates into vertical and horizontal movement, estimate the settlement over five years, and decide what to do next (Section 5.3.25).

Old mine workings below the line Bridge pier Ascending (looks east) Descending (looks west) θa = 35°θd = 39° Given (PSInSAR)Ascending:−0.40 in./yr LOSDescending:−0.30 in./yr LOS(negative = awayfrom satellite) RequiredVertical and eastrates; 5-yr total
Figure 5.3-22. Question 5.3-7: ascending and descending views of the pier.

Given

VariableValueDescription
da, θa−0.40 in./yr; 35°Ascending pass: line-of-sight rate (negative = away from the satellite) and incidence angle; satellite to the west
dd, θd−0.30 in./yr; 39°Descending pass; satellite to the east
SimplificationNorth–south motion and satellite heading ignoredBoth look directions taken as due east or west

Required

  • (a) Vertical rate from the ascending pass alone, assuming no horizontal movement
  • (b) Vertical and east–west rates from both passes
  • (c) Settlement over five years, and the next step

Equations

  1. Eq. 1: da = U cos θa − E sin θa (U up, E east positive)
  2. Eq. 2: dd = U cos θd + E sin θd
  3. Eq. 3: vertical only: U = d / cos θ

Steps

Step 1 · (a) Ascending only
−0.40 / cos 35° = −0.40 / 0.819
U = −0.49 in./yr
↓
Step 2 · (b) Set up the two equations
−0.40 = 0.819 U − 0.574 E; −0.30 = 0.777 U + 0.629 E
Determinant = 0.819 × 0.629 + 0.574 × 0.777 = 0.961
↓
Step 3 · (b) Solve
U = (−0.40 × 0.629 − 0.574 × 0.30) / 0.961; E = (−0.30 × 0.819 + 0.40 × 0.777) / 0.961
U = −0.44 in./yr (down); E = +0.07 in./yr (east)
Spot check: Ascending: 0.819(−0.44) − 0.574(0.07) = −0.40 ✓. Descending: 0.777(−0.44) + 0.629(0.07) = −0.30 ✓.
↓
Step 4 · (c) Five years
5 × 0.44
About 2.2 in. of settlement
↓
Solution
About 0.44 in./yr down and 0.07 in./yr east; about 2.2 in. in five years.

Solution

(a) −0.49 in./yr if all movement were vertical. (b) 0.44 in./yr of settlement and 0.07 in./yr eastward movement. (c) About 2.2 in. over five years.

Using one pass and assuming vertical movement overstated the settlement by about 10% here; with larger horizontal movement, for example on a landslide, the error can be much bigger or even change sign. Treat the result as a reason to survey, not as a measurement: set survey points on the pier and abutments, check the record for bearing and joint distress, and look up the mine maps and subsidence history (Chapter 3.10). If leveling confirms the rate, compare the differential settlement between piers with the bridge’s tolerance and the track surfacing record.

Question 5.3-8: Fitting a Site Blast Attenuation Line From Monitored Shots

Problem Statement

A Class I railroad located in West Virginia is lowering grade through a sandstone cut to gain clearance for double-stack trains. Four shots have been monitored with a seismograph beside the main track. The next lift brings the blasting to within 120 ft of a reinforced concrete box culvert under the track. The specification sets a shutdown threshold of 0.5 in./s at the rail and allows a charge per delay based on the site attenuation line once enough shots have been monitored (Section 5.3.27). The engineer must fit the line and set the maximum charge per delay for the next lift.

102050100 0.10.31.03.0 Scaled distance SD = D/√W (ft/lb½) — log scale PPV (in./s) — log scale 0.5 in./s limit Fitted line (Required: K, β)Upper line through highest point Given Shot 1: SD 20, PPV 1.60Shot 2: SD 30, PPV 0.85Shot 3: SD 45, PPV 0.52Shot 4: SD 70, PPV 0.25Next: D = 120 ft toa concrete box culvertLimit 0.5 in./s at rail Required(a) K and β(b) Upper-bound K(c) W at 120 ft
Figure 5.3-24. Question 5.3-8: monitored shots plotted on log scales, with the fitted attenuation line and the upper line used for design.

Given

VariableValueDescription
SDi, PPVi(20, 1.60), (30, 0.85), (45, 0.52), (70, 0.25)Scaled distance (ft/lb1/2) and measured peak particle velocity (in./s) for shots 1 to 4
D120 ftNearest hole of the next lift to the culvert
PPVlimit0.5 in./sShutdown threshold at the rail
Ds50Federal scaled distance without a seismograph, 0 to 300 ft (Table 5.3-17), for comparison

Required

  • (a) Site constants K and β from a least-squares fit of log PPV against log SD
  • (b) Upper-bound K from a line of the same slope through the highest point
  • (c) Maximum charge per delay at 120 ft, compared with the no-seismograph rule

Equations

  1. Eq. 5.3-14: PPV = K · SD−β, so log PPV = log K − β log SD
  2. Least squares: −β = Sxy / Sxx; log K = ȳ + β x̄, with x = log SD and y = log PPV
  3. Upper bound: Kub = max (PPVi · SDiβ)
  4. Eq. 5.3-14 rearranged: SDreq = (Kub / PPVlimit)1/β; Eq. 5.3-15: W = (D / SDreq)2

Steps

Step 1 · Take logs
x = 1.301, 1.477, 1.653, 1.845; y = 0.204, −0.071, −0.284, −0.602
x̄ = 1.569; ȳ = −0.188
↓
Step 2 · (a) Fit the line
Sxx = Σ(x − x̄)2 = 0.1636; Sxy = Σ(x − x̄)(y − ȳ) = −0.2383; −β = −0.2383 / 0.1636; log K = −0.188 + 1.457 × 1.569 = 2.098
β = 1.46; K = 125 in./s
Spot check: 125 × 45−1.46 = 125 / 257 = 0.49 in./s, against 0.52 measured at shot 3.
↓
Step 3 · (b) Upper bound
PPV · SD1.457 for each shot: 125.7, 120.5, 133.1, 121.8
Kub = 133 in./s (shot 3)
↓
Step 4 · (c) Scaled distance for 0.5 in./s
(133.1 / 0.5)1/1.457 = 266.20.686: ln 266.2 = 5.584; × 0.686 = 3.833; e3.833
SDreq = 46.2 ft/lb1/2
↓
Step 5 · (c) Charge per delay
(120 / 46.2)2 = 2.5972; no-seismograph rule: (120 / 50)2
W = 6.7 lb per delay (monitored); 5.8 lb per delay (no seismograph)
Spot check: 120 / √6.7 = 46.4; 133.1 × 46.4−1.457 = 133.1 / 268 = 0.50 in./s.
↓
Solution
K = 125, β = 1.46; Kub = 133; maximum 6.7 lb per delay at 120 ft with every shot monitored.

Solution

(a) K ≈ 125 in./s, β ≈ 1.46. (b) Kub ≈ 133 in./s. (c) 6.7 lb per delay at 120 ft, against 5.8 lb under the no-seismograph rule.

This site attenuates faster than the generic upper bound (K = 242 with β = 1.6) used in Example 5.3-9, so the monitored line allows about 15% more charge than the no-seismograph rule. Four shots are a thin data set, and they cover scaled distances of 20 to 70. The next lift, at SD of about 46, falls inside that range, which supports using the fit. Keep the seismograph at the culvert for every shot and add each reading to the regression. If a reading plots above the upper line, recompute Kub before the next shot. Check the dominant frequency as well: a reinforced concrete box culvert is far less sensitive than masonry, but the 0.5 in./s threshold applies at the rail regardless of the structure.

Method: Section 5.3.27 and Dowding (1985). Scaling discussion after Holub et al., in Feng (ed.) (2017), Ch. 21. Full reference under S27.

← Previous · 5.0 Testing Chapter 5.2 — Laboratory Testing Program
Next · 5.0 Testing → Chapter 5.4 — Geo-Environmental Testing on Railroad Corridors