5.3.4 Pile Installation Monitoring

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.4 Pile Installation Monitoring
5.3.4.1 WEAP Analysis (Wave Equation Analysis of Piles)

WEAP is a predictive analysis performed before driving to establish the driving criterion (blow count per foot at target penetration depth or refusal) that corresponds to the required pile capacity. It models the pile, hammer, and soil system using wave propagation theory.

WEAP output:

  • Bearing graph: ultimate capacity (tons) vs. blow count (blows/ft)
  • Stress wave propagation: compressive and tensile stress peaks (psi)
  • Transfer efficiency: (E_transferred / E_rated) × 100%

Hammer energy — English units:

E_rated = W_ram × h (ft·lb)

where:

  • W_ram = ram weight (lb)
  • h = stroke height (ft) for drop hammers; rated for diesel/hydraulic

Transferred energy:

E_transferred = ∫ F(t) × v(t) dt (ft·lb; the maximum value is EMX from the PDA)

Required input parameters for WEAP:

  • Pile: type, cross-section (area A in.², modulus E = 29,000 ksi for steel, 57√f'_c for concrete), length (ft), elastic modulus
  • Hammer: type, rated energy, efficiency, cushion and capblock properties
  • Soil: ultimate capacity distribution (side friction vs. tip) from static analysis; quake and damping factors (Smith damping)

Smith damping constants (typical):

Soil TypeSide Quake (in.)Tip Quake (in.)Side Damping (s/ft)Tip Damping (s/ft)
Sand0.100.100.050.15
Clay0.100.100.200.15
Silt0.100.100.150.15

Specify WEAP for bridge foundation piles, particularly long piles and piles in soft clay.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
Inputs for the equations in this section (2)
SymbolWhat it isComes fromHow to get itTypical range
Wramram weight (lb)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
hstroke height (ft) for drop hammersProject geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
5.3.4.2 Pile Driving Analyzer (PDA) — ASTM D4945

The PDA measures force and velocity at the pile head during driving using strain gauges and accelerometers. It provides a real-time assessment of:

  • Transferred hammer energy (E_transferred, ft·lb)
  • Peak compressive stress at pile top (CSX, ksi)
  • Peak tensile stress (TSX, ksi)
  • Integrity (BTA flag for damage)
  • Estimated capacity via Case Method
Pile Integrity Test (PIT)
Pile Integrity Test (PIT)

Case Method capacity:

R_total = ½ × (1 + J_c) × [F(t₁) + Z × V(t₁)] + ½ × (1 − J_c) × [F(t₁ + 2L/c) − Z × V(t₁ + 2L/c)] (lb)

where:

  • F(t) = measured force at time t (lb)
  • V(t) = measured velocity at time t (ft/s)
  • Z = pile impedance = E × A / c (lb·s/ft); c = wave speed in pile (ft/s); c = 16,800 ft/s for steel
  • J_c = Case damping factor (about 0.1–0.25 for sand, 0.25–0.4 for silt, 0.4–1.0 for clay)
  • t₁ = time of peak force
  • L = pile length below gauge (ft)

Transfer ratio: ETR = (E_transferred / E_rated) × 100%. Compare the measured transfer ratio with the expected range for the hammer type and with the project specification.

Minimum PDA testing frequency varies by owner and project; confirm it with the owner railroad and the project specification. Typical requirements include:

  • 10% of production piles, with a minimum number per bridge
  • 5% of production piles plus all test piles
  • All piles on some critical or passenger projects
Inputs for the equations in this section (7)
SymbolWhat it isComes fromHow to get itTypical range
F(t)measured force at time t (lb)Field or lab measurementRecorded during the test or monitoring (readings, times, dimensions of the test setup).project-specific
V(t)measured velocity at time t (ft/s)Field or lab measurementRecorded during the test or monitoring (readings, times, dimensions of the test setup).project-specific
Zpile impedanceAnother equationComputed: Z = E × A / c (lb·s/ft)project-specific
cwave speed in pile (ft/s)ConstantPhysical constant or standard value.project-specific
JcCase damping factor (0.10–0.20 for sandChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
t₁time of peak forceTimeElapsed test time (recorded) or the analysis time chosen for design.project-specific
Lpile length below gauge (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
5.3.4.3 CAPWAP Analysis

CAPWAP (CAse Pile Wave Analysis Program) is a post-processing signal matching analysis of PDA records that provides:

  • Ultimate total capacity (tons)
  • Skin friction distribution by depth (tons/ft)
  • End bearing capacity (tons)
  • Unit skin friction and unit end bearing values

CAPWAP replaces WEAP as the definitive capacity prediction when PDA data is available. Whether CAPWAP results can stand in for a static load test is the owner's decision; confirm it before the test program is set. Restrike after setup, typically at least 24 hours in sand and 7 days in clay.

Supplemental reference

Field practice checks during driving

  • Vibration near track and structures (USACE EI 02G001): with impact hammers, consider a smaller or double-acting hammer. With vibratory hammers, use a high-frequency, low-amplitude unit. Vibratory hammers typically cause more ground vibration than impact hammers. If neither works, use a non-driven foundation. Monitor during test piles and production driving where susceptible structures are nearby.
  • Obstructions (old fill, riprap, timber in railroad embankments): drive a heavy spud and withdraw it, or probe with a vibratory hammer that can extract and reinsert the pile. Hard driving through obstructions invites pile damage.
  • Sequence and heave: drive groups from the center outward. Restrike piles that heave when neighbors are driven to confirm resistance and embedment.
  • Driving stresses: AASHTO/FHWA limit steel piles to 0.9 fy during driving (FHWA NHI-05-042, superseded by GEC 12, FHWA-NHI-16-009 (2016)). Classroom notes (Swan) use more conservative limits of 0.8 fy for steel and 0.6 f′c for concrete. Damage risk is highest at refusal on stiff soil or rock.
  • Dynamic formulas (ENR and variants) ignore setup in clay and rate effects in sand. Where they are used at all, FS of 4–6 on formula capacity is customary, which is why Table 11-S2 assigns the Gates formula FS = 3.5 and wave equation or dynamic testing much less.
  • Load-test count by project size (Engel, 1988): cumulative driven length 0–1.1 mi, none; 1.1–1.9 mi, 1; 1.9–3.7 mi, 2; 3.7–5.6 mi, 3; 5.6–7.5 mi, 4. Quick maintained-load tests without rate correction can overestimate capacity and underestimate settlement relative to slow tests.
Pile Foundation Execution Inspection
Pile Foundation Execution Inspection

Source: U.S. Army Corps of Engineers (1997). Pile Driving Equipment. Engineering Instructions EI 02G001 · Swan, C. C. Field Estimates of Pile Capacities, 53:139 Foundation Engineering supplemental notes. The University of Iowa · Hannigan, P. J. et al. (2006). Design and Construction of Driven Pile Foundations. FHWA NHI-05-042 (superseded by GEC 12, FHWA-NHI-16-009 (2016))

Case study: 5.3.18.2 Sinkhole beside a piling rig on a sound working platform (Look 2023), in Section 5.3.18 Case Studies.

Project management · Goldbloom (1989)

Specifying, Measuring and Paying for Driven Piles

Goldbloom gives a checklist of what a bearing-pile section must state. Pile monitoring depends on these items, so they should be confirmed before driving starts:

Crane Inspection HSE Checklist
Crane Inspection HSE Checklist
  • the design capacity;
  • a requirement that excavation be complete before piles are driven;
  • driving criteria: minimum tip elevation, minimum penetration, and final blow count in blows per inch over the last 6 in. Where test piles and load tests are included, set the blow count after the load tests;
  • driving sequence for groups, from the center outward;
  • a minimum distance from concrete less than 7 days old (60 ft in his example);
  • submittal of the driving equipment;
  • limits on jetting, which must stop 3 to 6 ft above the expected final tip so the last few feet are driven;
  • conditions under which predrilling is allowed;
  • whether cut-offs may be spliced and reused.
Excavation Safety
Excavation Safety

His example tolerance is a maximum deviation of ¼ in. per ft from vertical or plan batter, and 3 in. in any direction at cut-off elevation.

For payment, he separates fixed costs from variable costs so that neither party gains or loses unfairly when the pile footage changes:

  • Mobilization of pile-driving equipment: lump sum, including moves between locations and demobilization. This is the largest fixed cost, especially for barge work.
  • Production piles: per linear foot from tip to actual cut-off, by type and size. The unit price normally covers jetting, followers, rejected and damaged piles, and, depending on the contract, cut-offs.
  • Cut-offs on timber or precast piles: pay separately by the linear foot when the engineer sets the ordered lengths.
  • Test piles: pay separately. They cost more per foot than production piles even if they become permanent.
  • Load tests: pay per each, because the number is uncertain.
  • Predrilled holes: per linear foot. Pipe-pile points, H-pile tips and splices: per each.

For railroad work: On bridge and culvert replacement projects, the pile monitoring plan in this section should check that the driving criteria and tolerances in the contract match the design, and that the pay items match what the inspector will record. Tip elevation, penetration, final set, cut-off elevation, and splice and cut-off lengths should all appear on the pile log. Where tie-in work is restricted to short track windows, mobilization and remobilization between windows should be priced explicitly so they do not end up as claims.

Source: Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold, pp. 20, 225–233. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Seeley (1993)

Recording Piling Data to Match the Pay Items

Seeley shows how CESMM3 (Classes P and Q) splits piling so that a variation can be valued fairly. Items are grouped by piles of the same type, material and section at one location. Each group produces two or three items:

  1. The number of piles. This covers moving the rig to each position, setting up and preparing to drive or bore.
  2. The length of piles. This covers the material. For cast-in-place piles it is measured from the cut-off level to the toe level that was expressly required.
  3. The depth driven or bored, measured from a stated commencing surface. Raked piles are identified, with the rake stated.

Interlocking sheet piling is measured by area: the mean horizontal length of the wall times the depth. Corner, junction, closure and taper piles are extra linear items. Plant mobilization and temporary staging suit fixed method-related charges, and operating the piling plant suits a time-related charge. Ancillary work is measured only when expressly required. That includes cutting off surplus length, preparing pile heads, and extensions, which are paid as a number item for each joint plus a length item split at about 10 ft. Breaking out obstructions above the founding stratum is paid by the hour, and only when ordered, so the engineer can control and record it. Load tests and non-destructive tests are separate items.

For railroad work: on bridge pier, abutment and retaining-wall piling, the inspector’s driving record is the evidence for each of these quantities, so record them on the log as the work proceeds. For every pile, record:

  • pile ID and group
  • ground or commencing elevation when driving starts
  • tip elevation reached and the cut-off elevation
  • length delivered, length cut off and splices made
  • batter
  • start and stop times of any ordered obstruction work, with the reason
  • any re-strike or dynamic test

When a pile runs past its plan length, separate records for the pile count, the length furnished and the depth driven let the change be priced from the bid items. It does not have to become a lump-sum claim. Where piling is done under track windows or next to live track, note the time lost waiting for trains, so that time-related standby can be reconciled against the railroad’s own records.

Source: Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press, pp. 166–167. Summarized and paraphrased. Full reference under Supplemental References.