WEAP is a predictive analysis performed before driving to establish the driving criterion (blow count per foot at target penetration depth or refusal) that corresponds to the required pile capacity. It models the pile, hammer, and soil system using wave propagation theory.
WEAP output:
Hammer energy — English units:
E_rated = W_ram × h (ft·lb)
where:
Transferred energy:
E_transferred = ∫ F(t) × v(t) dt (ft·lb; the maximum value is EMX from the PDA)
Required input parameters for WEAP:
Smith damping constants (typical):
| Soil Type | Side Quake (in.) | Tip Quake (in.) | Side Damping (s/ft) | Tip Damping (s/ft) |
|---|---|---|---|---|
| Sand | 0.10 | 0.10 | 0.05 | 0.15 |
| Clay | 0.10 | 0.10 | 0.20 | 0.15 |
| Silt | 0.10 | 0.10 | 0.15 | 0.15 |
Specify WEAP for bridge foundation piles, particularly long piles and piles in soft clay.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Wram | ram weight (lb) | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| h | stroke height (ft) for drop hammers | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
The PDA measures force and velocity at the pile head during driving using strain gauges and accelerometers. It provides a real-time assessment of:
Case Method capacity:
R_total = ½ × (1 + J_c) × [F(t₁) + Z × V(t₁)] + ½ × (1 − J_c) × [F(t₁ + 2L/c) − Z × V(t₁ + 2L/c)] (lb)
where:
Transfer ratio: ETR = (E_transferred / E_rated) × 100%. Compare the measured transfer ratio with the expected range for the hammer type and with the project specification.
Minimum PDA testing frequency varies by owner and project; confirm it with the owner railroad and the project specification. Typical requirements include:
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| F(t) | measured force at time t (lb) | Field or lab measurement | Recorded during the test or monitoring (readings, times, dimensions of the test setup). | project-specific |
| V(t) | measured velocity at time t (ft/s) | Field or lab measurement | Recorded during the test or monitoring (readings, times, dimensions of the test setup). | project-specific |
| Z | pile impedance | Another equation | Computed: Z = E × A / c (lb·s/ft) | project-specific |
| c | wave speed in pile (ft/s) | Constant | Physical constant or standard value. | project-specific |
| Jc | Case damping factor (0.10–0.20 for sand | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
| t₁ | time of peak force | Time | Elapsed test time (recorded) or the analysis time chosen for design. | project-specific |
| L | pile length below gauge (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
CAPWAP (CAse Pile Wave Analysis Program) is a post-processing signal matching analysis of PDA records that provides:
CAPWAP replaces WEAP as the definitive capacity prediction when PDA data is available. Whether CAPWAP results can stand in for a static load test is the owner's decision; confirm it before the test program is set. Restrike after setup, typically at least 24 hours in sand and 7 days in clay.

Source: U.S. Army Corps of Engineers (1997). Pile Driving Equipment. Engineering Instructions EI 02G001 · Swan, C. C. Field Estimates of Pile Capacities, 53:139 Foundation Engineering supplemental notes. The University of Iowa · Hannigan, P. J. et al. (2006). Design and Construction of Driven Pile Foundations. FHWA NHI-05-042 (superseded by GEC 12, FHWA-NHI-16-009 (2016))
Case study: 5.3.18.2 Sinkhole beside a piling rig on a sound working platform (Look 2023), in Section 5.3.18 Case Studies.
Goldbloom gives a checklist of what a bearing-pile section must state. Pile monitoring depends on these items, so they should be confirmed before driving starts:

His example tolerance is a maximum deviation of ¼ in. per ft from vertical or plan batter, and 3 in. in any direction at cut-off elevation.
For payment, he separates fixed costs from variable costs so that neither party gains or loses unfairly when the pile footage changes:
For railroad work: On bridge and culvert replacement projects, the pile monitoring plan in this section should check that the driving criteria and tolerances in the contract match the design, and that the pay items match what the inspector will record. Tip elevation, penetration, final set, cut-off elevation, and splice and cut-off lengths should all appear on the pile log. Where tie-in work is restricted to short track windows, mobilization and remobilization between windows should be priced explicitly so they do not end up as claims.
Source: Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold, pp. 20, 225–233. Summarized and paraphrased. Full reference under Supplemental References.
Seeley shows how CESMM3 (Classes P and Q) splits piling so that a variation can be valued fairly. Items are grouped by piles of the same type, material and section at one location. Each group produces two or three items:
Interlocking sheet piling is measured by area: the mean horizontal length of the wall times the depth. Corner, junction, closure and taper piles are extra linear items. Plant mobilization and temporary staging suit fixed method-related charges, and operating the piling plant suits a time-related charge. Ancillary work is measured only when expressly required. That includes cutting off surplus length, preparing pile heads, and extensions, which are paid as a number item for each joint plus a length item split at about 10 ft. Breaking out obstructions above the founding stratum is paid by the hour, and only when ordered, so the engineer can control and record it. Load tests and non-destructive tests are separate items.
For railroad work: on bridge pier, abutment and retaining-wall piling, the inspector’s driving record is the evidence for each of these quantities, so record them on the log as the work proceeds. For every pile, record:
When a pile runs past its plan length, separate records for the pile count, the length furnished and the depth driven let the change be priced from the bid items. It does not have to become a lump-sum claim. Where piling is done under track windows or next to live track, note the time lost waiting for trains, so that time-related standby can be reconciled against the railroad’s own records.
Source: Seeley, I. H. (1993). Civil Engineering Quantities, 5th ed. Basingstoke: The Macmillan Press, pp. 166–167. Summarized and paraphrased. Full reference under Supplemental References.