5.3.5 Static Axial Load Testing (ASTM D1143)

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.5 Static Axial Load Testing (ASTM D1143)

Static load testing is the most reliable method for confirming driven or drilled pile capacity. It is often required for new bridge foundations; confirm the owner railroad's requirement.

Static Vertical Pile Load Testing
Static Vertical Pile Load Testing
Pile Load Test – Vertical Compression
Pile Load Test – Vertical Compression
Pile Testing — Purpose Behind Each Test
Pile Testing — Purpose Behind Each Test
Pile Load Test
Pile Load Test
CSL Access Tube Requirements for Drilled Piles
CSL Access Tube Requirements for Drilled Piles
Bored Pile Tremie Concreting
Bored Pile Tremie Concreting
Bi-Directional Static Load Testing
Bi-Directional Static Load Testing
5.3.5.1 Quick Load Test Method (ASTM D1143, Method B)

In the quick test (ASTM D1143, Procedure A), load is applied in increments of about 5% of the anticipated failure load, each held 4 to 15 minutes, until failure or the maximum test load is reached. Total test duration is typically a few hours.

Why Are Some Foundation Piles Tested Until They Move
Why Are Some Foundation Piles Tested Until They Move

Load application:

Test load applied by hydraulic jack against a reaction system (kentledge deadweight, reaction piles, or helical anchor reaction frame).

Jack force:

P_jack = p_hydraulic × A_ram (lb)

where p_hydraulic = hydraulic pressure (psi) and A_ram = ram area (in.²).

Settlement measurement: Four dial gauges or LVDTs at 90° spacing, referenced to a stable reference beam. Resolution ≥ 0.001 in.

5.3.5.2 Failure Criteria

Davisson Offset Method (standard for driven piles, commonly adopted):

Δ_failure = (Q × L) / (A_pile × E_pile) + (D/120) + 0.15 in.

where:

  • Q = applied load (lb)
  • L = pile length (in.)
  • A_pile = pile cross-sectional area (in.²)
  • E_pile = elastic modulus of pile material (psi); 29 × 10⁶ psi for steel
  • D = pile diameter or width (in.)
  • 0.15 in. = constant offset

Plot load-settlement curve; intersection of load-settlement curve with Davisson offset line defines Q_failure (tons).

Design capacity: Q_allow = Q_failure / FS

FS = 2.0 with a static load test; 2.25 with dynamic testing and signal matching (PDA + CAPWAP); 2.5 with indicator piles and wave equation analysis; 2.75 with wave equation analysis only; 3.5 with the Gates formula (FHWA NHI-05-042, superseded by GEC 12, FHWA-NHI-16-009 (2016), allowable stress design). Confirm the owner railroad's requirements.

Inputs for the equations in this section (6)
SymbolWhat it isComes fromHow to get itTypical range
Qapplied load (lb)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Lpile length (in.)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Apilepile cross-sectional area (in.²)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Epileelastic modulus of pile material (psi)Material property (published)Code or manufacturer value: steel E = 29,000,000 psi; concrete per ACI 318; rail and pile section properties from AREMA or producer tables.project-specific
Dpile diameter or width (in.)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
FS2.0 (with PDA + CAPWAP)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
5.3.5.3 Drilled Shaft (Drilled Pier) Load Testing — ASTM D1143

For Class I railroad crane rail foundations and Class I railroad intermodal structure piers, Osterberg Cell (O-Cell) testing is preferred over top-down testing when reaction frames would conflict with existing structures. The O-Cell is a bidirectional load cell embedded in the shaft; it loads the tip against the side in two directions simultaneously.

O-Cell net upward force:

Upward resistance above the cell = Q_cell − buoyant weight of the shaft above the cell; downward resistance below the cell = Q_cell (lb). ASTM D8169 covers bi-directional tests.

The O-Cell test produces separate side friction and tip resistance load-settlement curves, which are combined analytically to produce the equivalent top-down capacity.

O-Cell Load Testing — Pile Resistance
O-Cell Load Testing — Pile Resistance
5.3.5.4 Pile Load and Integrity Testing

Section 5.3 gives the Davisson criterion for static load tests. Volume II of the ICE Manual adds an extrapolation method for tests that stop short of failure and the equations behind the dynamic and integrity tests used on bridge and structure piles.

Static tests: Chin extrapolation

Equation 5.3-4. Chin hyperbolic extrapolation of a load test

U = Δ / [(Δ/P) − K]

Brown (2012), Eq. 98.1, p. 1457, after Chin (1972). Plot Δ/P against Δ; the points fall on a straight line whose slope is 1/U and whose intercept is K. U = extrapolated ultimate capacity.

Where a failure definition is needed and none is reached, Eurocode 7 takes the load at a settlement of 10% of the pile diameter; UK specifications end constant-rate-of-penetration tests when the load has fallen over 0.4 in. (10 mm) of movement or the settlement reaches 15% of the diameter (Brown, 2012, p. 1457).

High-strain dynamic tests

Equation 5.3-5. Pile impedance and the Case damping term

Z = E A / c = ρ c A;   F = Z v (single wave);   Rd = J Z vtoe

Brown (2012), Eqs. 98.4–98.9, pp. 1461–1462. Rd = dynamic (damping) resistance removed from the total to give the static resistance; J = Case damping factor (Table 5.3-13). Signal matching (CAPWAP-type analysis) is preferred to the closed-form Case method.

Table 5.3-13. Case damping factor J by soil type
SoilJ (s/m)J (s/ft)
Sand0.05–0.200.015–0.061
Silty sand, sandy silt0.15–0.300.046–0.091
Silt0.20–0.450.061–0.137
Silty clay, clayey silt0.40–0.700.122–0.213
Clay0.60–1.100.183–0.335

Brown (2012), Table 98.6, p. 1462, after Randolph (2003).

Integrity tests

Equation 5.3-6. Low-strain integrity test relations

c = √(E/ρ);   t = 2L/c;   Z = ρ c A;   Δf = c/(2L)

French and Turner (2012), Eqs. 97.1–97.5, pp. 1423–1424. c = wave speed in the pile; L = length; Δf = spacing of resonant peaks in the frequency (mobility) response. Wave speed in concrete is typically 3,500 to 4,000 m/s (11,500 to 13,100 ft/s).

A change in impedance (a neck, a bulge, a soil layer change) reflects part of the wave early. Low-strain sonic echo tests are cheap but lose resolution in long piles and in stiff ground; cross-hole sonic logging through access tubes cast into the pile, and parallel seismic testing beside an existing pile, examine the full length (French and Turner, 2012).

Example 5.3-6: Chin extrapolation and an integrity-test check

A static load test on a drilled shaft for a bridge pier was stopped at 385 kips without a clear failure. A sonic echo test on a 60-ft production shaft shows a toe reflection.

Settlement Δ (in.)Load P (kips)Chin asymptote Qult = ?0.10.20.30.40.5200300400Toe reflection 2L/c = ? Δf = ?GivenP = 200, 286, 333, 364, 385 kipsΔ = 0.10 to 0.50 in. (0.10 steps)Production shaft L = 60 ftWave speed c = 12,500 ft/sRequiredChin extrapolated capacityToe-reflection time 2L/cResonant-peak spacing c/2LBlack = given; red = required
Given and required for Example 5.3-6.

Given

VariableValueDescription
P (kips)200, 286, 333, 364, 385Test loads
Δ (in.)0.10, 0.20, 0.30, 0.40, 0.50Head settlements
L60 ftProduction shaft length
c12,500 ft/sWave speed in the concrete

Required

  • Extrapolated ultimate capacity U
  • Expected toe-reflection time and resonant-peak spacing

Equations

  1. Eq. 5.3-4: Δ/P = Δ/U + K — linear in Δ
  2. Eq. 5.3-6: t = 2L/c; Δf = c/2L

Steps

Step 1 · Δ/P
0.10/200 = 0.00050; 0.50/385 = 0.00130 in./kip
Five points on a straight line
↓
Step 2 · Slope and U
(0.00130 − 0.00050)/(0.50 − 0.10) = 0.0020 kip−1
U = 1/0.0020 = 500 kips
Spot check: Intercept K = 0.00050 − 0.0020 × 0.10 = 0.00030 in./kip; 0.20/(0.0020 × 0.20 + 0.00030) = 286 kips matches the second load.
↓
Step 3 · Toe reflection
2 × 60/12,500
9.6 ms
↓
Step 4 · Peak spacing
12,500/(2 × 60)
104 Hz
↓
Solution
U ≈ 500 kips by Chin; toe reflection expected at about 9.6 ms and resonant peaks about 104 Hz apart.

Solution

The Chin value is an extrapolation from a test stopped at 77% of it; hyperbolic fits tend to overestimate capacity, so use it as an upper estimate and apply the factor of safety to a defined settlement criterion where the owner requires one.

A toe reflection much earlier than 9.6 ms, or a peak spacing much wider than 104 Hz, points to a defect or a shorter shaft; follow up with cross-hole sonic logging.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • Brown, M. (2012). Pile capacity testing. Chapter 98 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1451–1470Find source ↗Library entry
  • French, S. and Turner, M. (2012). Pile integrity testing. Chapter 97 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1419–1450Find source ↗Library entry
← Previous · 5.0 Testing Chapter 5.2 — Laboratory Testing Program
Next · 5.0 Testing → Chapter 5.4 — Geo-Environmental Testing on Railroad Corridors