5.3.12 Representative Monitoring Data Table

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.12 Representative Monitoring Data Table
Table 5.3-6. Construction Monitoring Summary — Class I railroad Staged Embankment located in Alabama
DayFill H (ft)σ_v (psf)Δu (psf)r_uS_plate (in.)ΔS/day (in.)Status
000000—Baseline
34.04881950.400.220.07OK
78.09764400.450.680.11OK
1012.01,4648500.581.500.27Alert — Suspend
1412.01,4646100.422.100.15Consolidating
2112.01,4643850.263.200.16OK — Resume fill
2515.01,8305200.283.850.16OK
3518.02,1964900.225.100.13OK