5.3.11 Worked Calculation Examples

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.11 Worked Calculation Examples
The examples cover compaction acceptance, pile capacity from dynamic testing and a piezometer alert during staged fill. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 5.3-1: Compaction Acceptance of Structural Fill

Structural fill behind a bridge abutment replacement on a Class I railroad located in Georgia. The nuclear gauge reads wet density and moisture; the inspector converts them to dry density and compares both density and moisture with the specification before the next lift goes on.

Previous liftsLift under testNuclear gaugeprobeγd = ? RC = ? Pass or fail?WD = 139.4 pcf; w = 11.8%GivenWD = 139.4 pcf (Test 014)w = 11.8%γd,max = 125.5 pcf; wopt = 11.2%Spec: RC ≥ 95%, w within ±3%RequiredField dry density and RCPass or failBlack = given; red = required
Given and required for Example 5.3-1.

Given

VariableValueDescription
WD139.4 pcfGauge wet density, Test 014
w11.8%Gauge moisture
γd,max, wopt125.5 pcf; 11.2%Modified Proctor
SpecRC ≥ 95%; w within ±3% of optimum (assumed)

Required

  • Field dry density and RC
  • Pass or fail

Equations

  1. Eq. 1: γd = WD / (1 + w) — dry density from the gauge wet density and moisture
  2. Eq. 2: RC = γd / γd,max × 100% — relative compaction

Steps

Step 1 · γd (Eq. 1)
139.4 / 1.118
124.7 pcf
↓
Step 2 · RC (Eq. 2)
124.7 / 125.5
99.4% ≥ 95%
↓
Step 3 · Moisture
Window 8.2 to 14.2%; field 11.8%
Within
↓
Solution
RC 99.4%, moisture in range: pass.

Solution

Test 014 passes: RC = 99.4% and moisture 11.8%, within the window.

Record it on the daily report and compaction log. A result this close to 100% is worth a second look at the Proctor reference: if the fill source has changed, the reference may no longer represent the material being placed.

Example 5.3-2: Case Method Capacity From a PDA Record

An H-pile for a Class I railroad crossing of the Columbia River is monitored with a pile driving analyzer. The Case method combines the force and velocity at impact with those one wave round-trip later to estimate the resistance mobilized by the blow.

Clay, Jc = 0.50Hammerstrain + accel.HP14×117, L = 75 ftF (black), ZV (blue)t1 t1 + 2L/cZ = ? RCase = ? Allowable = ?GivenA = 34.4 in.²; E = 29 × 106 psic = 16,808 ft/sF(t1) = 650,000 lb; V = 8.5 ft/sAt t1 + 2L/c: 280,000 lb; −2.1 ft/sJc = 0.50; FS 2.25Design load 180 tonsRequiredPile impedance ZCase method capacityAllowable loadBlack = given; red = required
Given and required for Example 5.3-2.

Given

VariableValueDescription
PileHP14×117, L = 75 ft; A = 34.4 in.²Steel H-pile
E, c29 × 106 psi; 16,808 ft/s
F(t1), V(t1)650,000 lb; 8.5 ft/sAt impact
F, V at t1 + 2L/c280,000 lb; −2.1 ft/sOne round-trip later
Jc0.50Case damping, clay
FS2.25Dynamic testing with signal matching
Design load180 tons

Required

  • Pile impedance
  • Case method capacity and allowable load

Equations

  1. Eq. 1: Z = E A / c — impedance
  2. Eq. 2: R = ½(1 + Jc)[F1 + Z V1] + ½(1 − Jc)[F2 − Z V2] — Case method
  3. Eq. 3: Qallow = R / FS

Steps

Step 1 · Z (Eq. 1)
29×106 × 34.4 / 16,808
Z = 59,400 lb·s/ft
Spot check: psi × in.² = lb, divided by ft/s gives lb·s/ft.
↓
Step 2 · First term
0.75 × (650,000 + 59,400 × 8.5) = 0.75 × 1,154,900
866,200 lb
↓
Step 3 · Second term
0.25 × (280,000 + 59,400 × 2.1) = 0.25 × 404,700
101,200 lb
↓
Step 4 · R and Qallow (Eq. 2, 3)
967,400 lb = 484 tons; 484 / 2.25
Qallow = 215 tons ≥ 180 tons
↓
Solution
R ≈ 484 tons; Qallow = 215 tons > 180 tons.

Solution

Case method capacity ≈ 484 tons; allowable 215 tons, above the 180-ton design load.

The Case method depends on the damping factor chosen, so the factor of safety of 2.25 assumes the result is confirmed by CAPWAP signal matching on this and other records, ideally on restrike after setup in the clay.

Example 5.3-3: Piezometer Alert During Staged Construction

A staged embankment over soft Gulf Coast clay on a Class I railroad located in Alabama, with wick drains. The excess pore pressure ratio ru tells whether the clay is draining as fast as fill is being placed. If it rises past the trigger, filling stops before the clay fails.

Settlement Plate Installation
Settlement Plate Installation

Given

VariableValueDescription
H12 ft, the last lift placed in 3 daysFill height above the piezometer
γfill122 pcf
Δu850 psfVW piezometer at 15 ft
TriggersStop at ru > 0.50; resume below 0.35Monitoring plan (Section 5.3.7.1)
Settlement0.82 in. in 3 daysSettlement plate

Required

  • ru and the required response

Equations

  1. Eq. 1: σv = γfill H — added vertical stress from all fill
  2. Eq. 2: ru = Δu / σv

Steps

Step 1 · σv (Eq. 1)
122 × 12
1,464 psf
↓
Step 2 · ru (Eq. 2)
850 / 1,464
0.58 > 0.50: action threshold exceeded
↓
Step 3 · Response
Stop filling; notify within 1 hour; read every 2 hours; resume when ru < 0.35
↓
Step 4 · Cause
0.27 in./day settlement with ru rising
Load placed faster than the drains can relieve it; check drain spacing (Chapter 7.2)
↓
Solution
ru = 0.58: stop filling until it falls below 0.35.

Solution

ru = 0.58, above the 0.50 trigger: suspend filling and do not resume until ru falls below 0.35.

Issue a written alert with the reading log and calculation within 24 hours. Table 5.3-6 shows how this site recovered: ru fell to 0.26 by day 21, and filling resumed safely. The pause cost 11 days; a failure would have cost months.

Project management · Sears et al. (2015)

Earned Value Analysis of a Construction Contract

Sears et al. point out that a standard monthly cost forecast shows only whether the job will finish over or under budget. It cannot tell whether the variance comes from cost performance, schedule performance or both. The earned value management system (EVMS) separates the two by comparing three cumulative quantities at each update:

  • BCWS (budgeted cost of work scheduled): the planned value of the work that the baseline schedule calls for by the update date.
  • BCWP (budgeted cost of work performed): the earned value, meaning the budgets of the work actually accomplished.
  • ACWP (actual cost of work performed): what the accomplished work actually cost.
Earned value plot showing BCWS, BCWP and ACWP curves at the present date, the cost and schedule variances, and the projected EAC range against the budget at completion.
Figure 15-PM3. Earned value plot showing BCWS, BCWP and ACWP curves at the present date, the cost and schedule variances, and the projected EAC range against the budget at completion. Source: Sears et al. (2015), Figure 11.9.

From these: cost variance CV = BCWP − ACWP; schedule variance SV = BCWP − BCWS, expressed in dollars; CPI = BCWP/ACWP; SPI = BCWP/BCWS. An index below 1.0 calls for management attention. The estimate at completion is bracketed by EAC1 = ACWP + (BAC − BCWP)/CPI and EAC2 = ACWP + (BAC − BCWP)/(CPI × SPI), where BAC is the budget at completion. The to-complete index TCPI = (BAC − BCWP)/(EAC − ACWP) gives the cost efficiency needed on the remaining work.

Source example (highway bridge, day 27): BAC = $390,214; BCWS = $160,622; BCWP = $147,011; ACWP = $157,582. Then CV = −$10,571 and SV = −$13,611; CPI ≈ 0.93 and SPI ≈ 0.92. The forecast range is EAC1 ≈ $418,273 to EAC2 ≈ $442,409. In other words, if the cost inefficiency continues, the job finishes about $28,000 over, and continued schedule slippage could raise that to about $52,000.

The authors also describe the time-cost envelope (early-start and late-start cumulative cost curves) as the graphical forerunner of EVMS.

For railroad work: On a unit-price subgrade rehabilitation or slope repair, use the bid items as the budget lines and the construction monitoring quantities (cubic yards of undercut, tons of subballast or riprap, linear feet of drain, piles driven) as the earned value. Because work is confined to track windows, a low SPI often means windows were lost or shortened, not that crews were slow. Keep the window log next to the EV report so the cause is clear. A falling CPI combined with deeper-than-planned undercut is an early quantitative sign of a differing-condition trend that should be raised with the railroad before the next window, not at close-out.

Source: Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O., Jr. (2015). Construction Project Management: A Practical Guide to Field Construction Management, 6th ed. Hoboken, NJ: John Wiley & Sons, pp. 298–303. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Example 5.3-4: Earned Value of a Construction Contract

The Sears et al. highway bridge example at day 27. Earned value separates a cost overrun from a schedule slip, which a simple budget forecast cannot do.

TimeCost ($)Planned (BCWS)data dateBCWS $160,622BCWP $147,011ACWP $157,582BAC $390,214CV, SV, CPI, SPI = ? EAC range = ?GivenBAC = $390,214BCWS = $160,622BCWP = $147,011ACWP = $157,582RequiredCost and schedule variancesCPI and SPIRange of EACBlack = given; red = required
Given and required for Example 5.3-4.

Given

VariableValueDescription
BAC$390,214Budget at completion
BCWS$160,622Planned value to date
BCWP$147,011Earned value to date
ACWP$157,582Actual cost to date

Required

  • Cost and schedule variances and indices
  • Range of the estimate at completion

Equations

  1. Eq. 1: CV = BCWP − ACWP; SV = BCWP − BCWS
  2. Eq. 2: CPI = BCWP/ACWP; SPI = BCWP/BCWS
  3. Eq. 3: EAC1 = ACWP + (BAC − BCWP)/CPI; EAC2 = ACWP + (BAC − BCWP)/(CPI × SPI)

Steps

Step 1 · Variances (Eq. 1)
CV = −$10,571; SV = −$13,611
↓
Step 2 · Indices (Eq. 2)
CPI = 0.93; SPI = 0.92
↓
Step 3 · EAC (Eq. 3)
157,582 + 243,203/0.933; 157,582 + 243,203/(0.933 × 0.915)
$418,273 to $442,409
↓
Solution
CPI 0.93, SPI 0.92; EAC $418,000 to $442,000.

Solution

The job is over cost (CPI 0.93) and behind schedule (SPI 0.92). It will finish about $28,000 over budget if the cost inefficiency continues, and about $52,000 over if the schedule slip continues too.

On railroad work, a low SPI often means track windows were lost or shortened rather than that crews were slow; check the window log before blaming productivity.