5.3.27 Blast Vibration and Airblast Monitoring

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.27 Blast Vibration and Airblast Monitoring

Rock excavation for second main tracks, cut widenings and grade lowering often needs drilling and blasting within a few hundred feet of operating track, bridges, culverts, signal houses and buildings. The licensed blaster designs the shots. The geotechnical engineer sets the vibration and airblast limits, reviews the blast plan against them, places and reads the seismographs, and decides whether results allow the work to continue. This section covers that side of the work. Explosive products, initiation systems and charge loading are the blaster’s responsibility and are not covered in GHRM.

What to measure

  • Ground vibration: peak particle velocity (PPV, in./s) in three perpendicular components (longitudinal, transverse, vertical), with the dominant frequency (Hz) of each. Report the largest component as the PPV.
  • Airblast: peak overpressure in dB (linear, flat response), measured with a microphone about 3 ft above ground at the structure.
  • Placement: on the ground at the structure, on the side nearest the blast. Bury the geophone or spike it into soil, and sandbag it on pavement or rock. A loosely set geophone reads high and gives false exceedances.
  • Record: date, time, shot number, distance to the shot, maximum charge per delay and the full waveform for each event.

Scaled distance and prediction

Eq. 5.3-13: SD = D / √W, where D = distance from the nearest charge to the structure (ft) and W = maximum weight of explosive fired in any 8-ms delay period (lb).

Eq. 5.3-14: PPV = K · SD−β, where K = site ground-transmission constant (in./s) and β = attenuation exponent, commonly about 1.6 (RK-14). For a new site with no data, K ≈ 160 is an average and K ≈ 242 a 90% upper bound (R in ft, W in lb), as listed in the construction vibration limits set of the soil properties database. Fit K and β by regression of log PPV against log SD as soon as several shots have been monitored, and design to the upper bound of the site data, not the mean.

Eq. 5.3-15: Wmax = (D / Ds)2, the largest charge per delay allowed by a required scaled distance Ds.

Square-root scaling (SD = D/√W) is used in U.S. regulations and in the U.S. Bureau of Mines work. Some authors prefer cube-root scaling (D/W1/3), which can fit close-in data better. Both are in use, so state which one a regression or a contractor’s prediction uses before comparing numbers (Holub et al., in Feng 2017).

Table 5.3-17. Federal ground vibration limits often adopted in blasting specifications (30 CFR 816.67(d))
Distance from the blastMaximum PPV when every shot is monitored (in./s)Scaled distance factor Ds when no seismograph is used
0 to 300 ft1.2550
301 to 5,000 ft1.0055
More than 5,000 ft0.7565

The same rule allows a frequency-based limit instead of the flat limits when every shot is monitored. That limit is lower at low frequency (about 0.75 in./s for residential drywall at 4 to 12 Hz) and rises to 2.0 in./s above about 40 Hz (Siskind et al. 1980). Low-frequency vibration is more damaging because it matches the natural frequency of houses and of long, flexible structures. The airblast limits in 30 CFR 816.67(b) depend on the lower frequency limit of the measuring system: 134 dB peak for 0.1 Hz or lower, 133 dB for 2 Hz or lower, 129 dB for 6 Hz or lower, and 105 dBC (C-weighted, slow response).

These federal limits protect residential structures. They are not limits for track, signals or masonry railroad structures. The owner railroad’s limits govern where they are stricter. GHRM elsewhere uses 0.5 in./s at the rail as a typical shutdown threshold for construction vibration near operating track (Chapter 7.2, Section 7.2.2). Limits for fresh concrete by age are also in the soil properties database.

Monitoring program

  1. Before blasting: a pre-blast condition survey (photographs, crack mapping, crack gauges on existing cracks) of bridges, culverts, retaining walls, signal houses and nearby buildings. Record the background vibration from passing trains, which can exceed 0.5 in./s close to the rail. That reading separates train vibration from blast vibration later.
  2. Test shots: start with small charges per delay and monitor at two or more distances to fit K and β for the site.
  3. Production: a seismograph at each structure of concern for every shot. Plot each reading on the PPV against SD chart and update the regression.
  4. Alert and action levels: an alert level (for example 50% of the limit) triggers a review of the delay pattern and charge per delay. Reaching the limit stops blasting until the plan is revised.
  5. After each shot: inspection of track geometry and structures, and clearance of flyrock from the track, before trains are released.
  6. Face quality: terrestrial laser scanning of each lift gives a difference model of the as-built face against the design line. That shows overbreak and underbreak, documents the half-barrel count, and measures the remaining catchment width (Feng, Wang and Röshoff, in Feng 2017). Irregular blasted profiles also concentrate stress and loosen blocks, which matters for tunnel and rock-cut stability.

For railroad work: Blasting near operating track is planned around the train schedule. Shots are fired in a work window under track protection, with the track and structures inspected before trains are released. Old masonry arches, stone retaining walls and timber trestles crack at lower vibration than modern concrete. Set their limits on the low side, and survey them closely before and after the work. Saturated loose sand and silt, fresh embankment fill and marginal slopes near the shot can be affected at PPV well below structural limits. Where such ground lies within about 300 ft, add a piezometer and an inclinometer or survey points, and watch for pore-pressure rise and movement after each shot. Blast vibration is usually higher frequency than earthquake shaking, but a shot can still trigger a fall from a marginally stable rock face. Scale and inspect nearby faces after each shot (Simser, in Feng 2017). Design of the controlled perimeter blasting for the final face is covered in Chapter 6.3, Section 6.3.7. Review of the contractor’s blast plan is in Chapter 8.4, Section 8.4.7.

Example 5.3-9: Charge Per Delay Near a Masonry Arch Culvert

Problem Statement

A Class I railroad located in Tennessee is widening a rock cut to add a second main track. The nearest structure is a stone-masonry arch culvert under the existing main track, 150 ft from the closest production holes. The specification adopts the federal scaled-distance rule and a shutdown threshold of 0.5 in./s at the rail. The contractor proposes 12 lb of explosive per delay. No shots have been monitored at the site yet. The engineer must decide whether the proposal can be accepted, and on what conditions.

Rock cut(widening) Final face (presplit line) Production holes Existing track Masonry archculvert D = 150 ft Seismographat culvert Given D = 150 ft to culvertDs = 50 (0–300 ft)Proposed W = 12 lb/delayPPV = K · SD−1.6K = 160 (average)K = 242 (upper bound)Limit: 0.5 in./s at rail Required (a) Wmax without seismograph(b) SD and PPV for 12 lb(c) W for 0.5 in./s at upper bound
Figure 5.3-23. Example 5.3-9: rock cut widening beside an existing track, with the nearest production hole 150 ft from a masonry arch culvert under the track.

Given

VariableValueDescription
D150 ftNearest production hole to the culvert
Ds50Required scaled distance without a seismograph, 0 to 300 ft (Table 5.3-17)
W12 lb per delayContractor’s proposed maximum charge per 8-ms delay
K160 in./s (average); 242 in./s (90% upper bound)Ground-transmission constant before site data
β1.6Attenuation exponent
PPVlimit0.5 in./sShutdown threshold at the rail; the culvert is under the track

Required

  • (a) Maximum charge per delay allowed without a seismograph
  • (b) Scaled distance and predicted PPV at the culvert for 12 lb per delay
  • (c) Charge per delay that keeps the upper-bound PPV at 0.5 in./s, and the recommendation

Equations

  1. Eq. 5.3-13: SD = D / √W — scaled distance
  2. Eq. 5.3-14: PPV = K · SD−β — predicted peak particle velocity
  3. Eq. 5.3-15: Wmax = (D / Ds)2 — charge allowed by a required scaled distance
  4. Eq. 5.3-14 rearranged: SDreq = (K / PPVlimit)1/β — scaled distance that meets a PPV limit

Steps

Step 1 · (a) Charge without a seismograph (Eq. 5.3-15)
(150 / 50)2 = 3.02
Wmax = 9.0 lb per delay
Spot check: √9.0 = 3.0 and 150 / 3.0 = 50 = Ds.
↓
Step 2 · (b) Scaled distance for 12 lb (Eq. 5.3-13)
150 / √12 = 150 / 3.464
SD = 43.3 ft/lb1/2 (less than 50, so 12 lb fails the no-seismograph rule)
↓
Step 3 · (b) Predicted PPV (Eq. 5.3-14)
43.31.6: ln 43.3 = 3.768; × 1.6 = 6.029; e6.029 = 415. Average: 160 / 415. Upper bound: 242 / 415
PPV = 0.39 in./s (average); 0.58 in./s (upper bound)
Spot check: at SD = 50, 501.6 = 523 and 160 / 523 = 0.31 in./s. A smaller SD gives a larger PPV, as expected.
↓
Step 4 · (c) Scaled distance for 0.5 in./s at the upper bound
(242 / 0.5)1/1.6 = 4840.625: ln 484 = 6.182; × 0.625 = 3.864; e3.864
SDreq = 47.6 ft/lb1/2
↓
Step 5 · (c) Charge for 0.5 in./s (Eq. 5.3-15 with SDreq)
(150 / 47.6)2 = 3.1512
W = 9.9 lb per delay
Spot check: 150 / √9.9 = 47.7, and 242 × 47.7−1.6 = 242 / 485 = 0.50 in./s.
↓
Solution
Start at 9 lb per delay with a seismograph at the culvert. Allow up to 12 lb only if the site data show K of about 207 in./s or less (0.5 × 415).

Solution

(a) 9.0 lb per delay without monitoring. (b) SD = 43.3; PPV = 0.39 in./s average and 0.58 in./s upper bound. (c) 9.9 lb per delay keeps the upper-bound PPV at 0.5 in./s.

The 12-lb proposal is well under the federal 1.25 in./s limit for 0 to 300 ft, but its upper-bound prediction exceeds the 0.5 in./s threshold at the rail. It also fails the no-seismograph scaled-distance rule. Do not accept it as submitted. Start production at 9 lb per delay, which meets both the scaled-distance rule and the upper-bound prediction, with a seismograph at the culvert for every shot. After the first several shots, fit K and β for the site. The charge can rise toward 12 lb only if the upper bound of the site data gives K of about 207 in./s or less (the value that gives 0.5 in./s at SD = 43.3). Set an alert level at about 0.25 in./s that triggers a review of the delay pattern. Masonry arches are sensitive to low-frequency vibration, so check the dominant frequency as well as the PPV. Survey the arch before and after the work.

Source: 30 CFR 816.61–816.68; Siskind et al. (1980); Dowding (1985); Austin Powder Company (2002), glossary and formula sheet; Feng (ed.) (2017), Chs. 10, 18 and 21. Summarized and paraphrased, with the railroad notes added by the authors of this manual. Full references under S28, S29, S30, S26, S27.