Railroad corridors carry a long history of activities that leave chemicals in the ground: creosote-treated ties, herbicide spraying, coal and cinder handling, fueling, locomotive servicing and spills. A geotechnical investigation does not need to be an environmental site assessment, but it does need to know what it may encounter, how to protect the crew, how to handle cuttings and water, and when to collect samples that will save a second mobilization. This chapter covers those questions.
Geo-environmental testing on a geotechnical project serves three purposes: protecting workers and the public during drilling and excavation; classifying soil, ballast and water that will be removed so they can be reused or disposed of properly; and flagging conditions that need a formal environmental assessment. Each has a cost; the aim is to collect the minimum data that answers the question, at the same time as the geotechnical work.
| Source | Typical contaminants | Where found |
|---|---|---|
| Treated crossties and timber structures | Creosote compounds (PAHs), pentachlorophenol | Ballast and shoulder soils along all tracks; tie storage sites |
| Herbicide application | Arsenic (historical), other herbicides | Ballast and shoulders; highest on older lines |
| Coal, cinders and ash | PAHs, metals (arsenic, lead), sulfate | Old ballast sections, coaling stations, embankment shoulders |
| Fueling and servicing | Petroleum hydrocarbons, BTEX, lubricants, solvents | Yards, fueling racks, engine houses |
| Electrical equipment | PCBs (older transformers) | Substations, signal houses (older) |
| Spills and car leaks | Product-specific | Sidings, interchange and industrial tracks |
| Adjacent land use | Varies | Industry, landfills, agriculture |
Ballast and the upper few feet of shoulder soil along mainline track commonly contain PAHs and metals above residential screening levels, which affects where excavated material can go even when it poses no special risk on the right-of-way.
| Stage | Standard | Content | Relation to geotechnical work |
|---|---|---|---|
| Phase I environmental site assessment | ASTM E1527 | Records review, site visit, interviews; identifies recognized environmental conditions | Shares sources with the geotechnical desktop study (Chapter 3.2) |
| Phase II environmental site assessment | ASTM E1903 | Sampling and analysis to confirm or rule out conditions | Borings can be shared; samples collected and preserved differently |
| Waste characterization | Disposal facility and state requirements | Analysis of soil, ballast or water for disposal acceptance | Usually needed for excavation spoil and drilling waste |
Geotechnical staff should not represent field screening as an environmental assessment. Where screening finds evidence of contamination, the finding is reported to the project manager and client for decision, and a qualified environmental professional takes over.
If analysis is likely, collect samples during the geotechnical borings rather than remobilizing. Environmental samples need different handling from geotechnical samples:
Analysis packages commonly used for railroad spoil are total petroleum hydrocarbons, PAHs, metals and, for disposal, the leaching procedure required by the receiving facility. The laboratory testing program is covered in Chapter 5.2.
Drilling generates cuttings, drilling fluid and decontamination water. On railroad property these are usually containerized (55-gallon drums) where contamination is possible, then characterized and disposed of. The number of drums is a cost and logistics item that should be in the estimate.
Excavation spoil, fouled ballast and ditch cleanings removed during construction follow the same logic at larger scale: characterize, then reuse on the right-of-way where allowed, or dispose of at a facility that accepts the material. Including the characterization in the geotechnical program avoids delays when the contractor starts excavating.
Twenty borings, each 30 ft deep, are planned with hollow-stem augers in a rail yard with a history of fueling. The owner requires all cuttings to be drummed and characterized before disposal.
| Variable | Value | Description |
|---|---|---|
| n | 20 | Number of borings |
| L | 30 ft | Depth of each boring |
| D | 8 in. (0.667 ft) | Outside diameter of the auger flights (hole diameter) |
| fb | 1.25 | Bulking factor for cuttings |
| Drum | 55 gal = 7.35 cf, filled to 80% | Usable volume 5.88 cf per drum |
The borings will produce about 262 cf of bulked cuttings, requiring about 45 drums for cuttings alone, before decontamination water.
Carry about 50 drums in the estimate to cover decontamination water and the partly filled last drum at each location, plus one composite characterization sample per group of drums as the receiving facility requires. The drums also need a staging area on railroad property that is clear of tracks and accessible to the disposal contractor; include that in the access and right-of-entry planning.
If the yard history suggests petroleum only, ask the client whether cuttings from borings with clean PID readings can be spread on site. That decision can cut the drum count sharply, but it belongs to the client and its environmental staff, not to the drilling crew.