During staged embankment filling over soft saturated fine-grained soils, piezometers are installed to monitor excess pore pressure buildup. Rapid excess pore pressure buildup indicates faster loading than the soil can drain, creating instability risk.
Excess pore pressure ratio:
r_u = Δu / σ_v
where Δu = excess pore pressure (psf) and σ_v = total vertical stress increase from fill (psf).
Safe fill criterion: a common practical trigger is to suspend filling if r_u exceeds about 0.5. Set the project trigger from the stability analysis for each stage.
Degree of consolidation from piezometer:
U_field = 1 − (Δu / Δu₀)
where Δu₀ = initial excess pore pressure immediately after fill placement; Δu = current excess pore pressure.
Compare U_field to the design U from the time-rate analysis (Chapter 6.2). If U_field is lagging behind design U, fill placement may be advanced at a reduced rate; never faster than design.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Δu | current excess pore pressure. | Instrument reading / calibration | From the instrument readout and the manufacturer's calibration certificate. | project-specific |
VW piezometers output a frequency reading (Hz) that is converted to pressure:
P = G × (R − R₀) + K × (T − T₀) (psf or psi)
where:
Typical VW reading cycle: automated datalogger at 15-minute intervals during active filling; hourly during consolidation monitoring. Owner railroads may require automated datalogger downloads every 24 hours to project engineer during active construction.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| G | gauge factor (psi/digit, from calibration sheet) | Instrument reading / calibration | From the instrument readout and the manufacturer's calibration certificate. | project-specific |
| R | current reading (digits = Hz²) | Instrument reading / calibration | From the instrument readout and the manufacturer's calibration certificate. | project-specific |
| R₀ | baseline reading (Hz²) | Instrument reading / calibration | From the instrument readout and the manufacturer's calibration certificate. | project-specific |
| K | temperature correction factor (psi/°F) | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |