Proof rolling is a rapid field technique for identifying soft, pumping, or inadequately compacted subgrade zones prior to placing overlying layers. It is commonly required for all mainline subgrade preparation.



Method: A loaded tandem-axle dump truck (typically about 25 tons gross, or as the specification requires) traverses the prepared subgrade at 2–3 mph. The geotechnical inspector observes for:
Reporting: GPS-tagged station of each deficiency location. Soft areas are marked, overexcavated to competent material (confirmed by nuclear gauge or hand penetrometer), and replaced with approved compacted fill.
Limitation: Proof rolling detects near-surface softness (top 18–24 in.) only. It does not evaluate deeper consolidation or deep subgrade conditions. Supplement with nuclear gauge density testing.
Inspect the subgrade at every stage of preparation, and again just before geotextile or sub-ballast is placed. Once the subgrade is covered, problems are expensive to find and fix.
| Item | Requirement | Inspector check |
|---|---|---|
| Subgrade | Inspected at each stage of preparation and before geotextile or sub-ballast is placed | Proof roll (Section 5.3.3); record stations of soft areas and repairs |
| Drainage | Ditches, culverts, subdrains and nearby earthwork complete before final subgrade preparation | Inspect subdrains before covering; check ditch flow lines and sections before track work starts |
| Geotextile exposure | No more than 7 days from removal of the shipping cover to final placement | Record delivery and uncovering dates in the daily field report |
| Geotextile cover | No equipment on geotextile until it has at least 6 in. of sub-ballast or ballast cover | Stop equipment tracking onto exposed fabric |
| Geotextile overlap | At least 3 ft, longitudinal and transverse | Measure at each seam |
| Geotextile contamination | Surface drainage directed away from placed fabric | Check for silted or blinded fabric before covering |
| Sub-ballast | Placed to plan lines and grades; compacted to at least 95% of ASTM D1557 (modified Proctor) maximum dry density | Test at the Table 5.3-1 frequency; check grade |
| Ballast placed by truck | No rutting that blocks drainage of sub-ballast or subgrade | Level and grade any ruts to drain before more ballast is placed |
Ballast delivery. For large quantities (several hundred tons or more), unloading from ballast hopper cars is usually the most efficient method. Where the owner has a locomotive and crew, using them to spot ballast cars for the contractor can lower the unit cost. Settle that arrangement in the contract documents and at the pre-construction meeting. Where trucks place ballast, watch for rutting: ruts in sub-ballast or subgrade hold water under the track.
After UFC 4-860-01FA (2004), ch. 9, §4 and §5a, 5c. Full reference under Supplemental References.