Pre-Construction
- [ ] Pre-construction meeting held; geotechnical inspector role vs. railroad inspector role defined
- [ ] RWP certification obtained for all field personnel (correct client railroad certification; see Introduction Table)
- [ ] Nuclear gauge licensed; operator radiation certification current
- [ ] Modified Proctor reference tests (γ_d,max, w_opt) completed for all fill materials before construction begins
- [ ] Trigger levels defined in writing and signed by geotechnical engineer
- [ ] Monitoring instruments installed and baseline readings recorded (minimum 3 consecutive readings over 1 week before construction)
- [ ] Automated datalogger programmed and communication verified
- [ ] Pile driving equipment inspection: hammer type, rated energy, leads, and cushion condition
- [ ] WEAP analysis completed; driving criterion established and submitted to railroad engineer
During Construction
- [ ] Compaction test performed at required frequency; failing tests reworked and retested same day
- [ ] Proof rolling performed on each subgrade lift; soft areas flagged and overexcavated
- [ ] PDA monitoring performed on required percentage of piles; ETR checked at each blow
- [ ] Pile driving log completed for every pile
- [ ] Settlement plates read per Table 5.3-2 schedule; data plotted same day
- [ ] Piezometers read per schedule; r_u calculated; Alert/Action evaluated each reading
- [ ] Inclinometers read per schedule; deflection profiles updated
- [ ] Daily field report submitted within 24 hours (including weekends during active filling)
- [ ] Any Alert or Action trigger: written notification issued within 1 hour; filling suspended if required
- [ ] Photographs taken at each inspection visit; GPS-referenced; filed to project folder
Post-Construction
- [ ] Final compaction summary table prepared (all test results, locations, pass/fail)
- [ ] Pile installation summary table prepared (all piles: location, tip elevation, blow count, capacity)
- [ ] CAPWAP analyses completed for all PDA-monitored piles; results submitted
- [ ] Static load test results analyzed (Davisson method); Q_allow confirmed
- [ ] Settlement and piezometer data plotted through end of monitoring period
- [ ] Construction monitoring report submitted to railroad project engineer
- [ ] PE seal on monitoring report (commonly required)
- [ ] All instrument casings located, documented, and protected (or abandoned per railroad protocol)