5.3.15 Construction Monitoring Checklist

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.15 Construction Monitoring Checklist

Checklist · Part VII · Stabilization Methods

Construction Monitoring Checklist

Pre-Construction0 of 9
During Construction0 of 10
Post-Construction0 of 8
Ticks are saved in this browser.
Plain text version

Pre-Construction

  • [ ] Pre-construction meeting held; geotechnical inspector role vs. railroad inspector role defined
  • [ ] RWP certification obtained for all field personnel (correct client railroad certification; see Introduction Table)
  • [ ] Nuclear gauge licensed; operator radiation certification current
  • [ ] Modified Proctor reference tests (γ_d,max, w_opt) completed for all fill materials before construction begins
  • [ ] Trigger levels defined in writing and signed by geotechnical engineer
  • [ ] Monitoring instruments installed and baseline readings recorded (minimum 3 consecutive readings over 1 week before construction)
  • [ ] Automated datalogger programmed and communication verified
  • [ ] Pile driving equipment inspection: hammer type, rated energy, leads, and cushion condition
  • [ ] WEAP analysis completed; driving criterion established and submitted to railroad engineer

During Construction

  • [ ] Compaction test performed at required frequency; failing tests reworked and retested same day
  • [ ] Proof rolling performed on each subgrade lift; soft areas flagged and overexcavated
  • [ ] PDA monitoring performed on required percentage of piles; ETR checked at each blow
  • [ ] Pile driving log completed for every pile
  • [ ] Settlement plates read per Table 5.3-2 schedule; data plotted same day
  • [ ] Piezometers read per schedule; r_u calculated; Alert/Action evaluated each reading
  • [ ] Inclinometers read per schedule; deflection profiles updated
  • [ ] Daily field report submitted within 24 hours (including weekends during active filling)
  • [ ] Any Alert or Action trigger: written notification issued within 1 hour; filling suspended if required
  • [ ] Photographs taken at each inspection visit; GPS-referenced; filed to project folder

Post-Construction

  • [ ] Final compaction summary table prepared (all test results, locations, pass/fail)
  • [ ] Pile installation summary table prepared (all piles: location, tip elevation, blow count, capacity)
  • [ ] CAPWAP analyses completed for all PDA-monitored piles; results submitted
  • [ ] Static load test results analyzed (Davisson method); Q_allow confirmed
  • [ ] Settlement and piezometer data plotted through end of monitoring period
  • [ ] Construction monitoring report submitted to railroad project engineer
  • [ ] PE seal on monitoring report (commonly required)
  • [ ] All instrument casings located, documented, and protected (or abandoned per railroad protocol)