5.3.21 Observational Method and Planned Monitoring

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.21 Observational Method and Planned Monitoring

The observational method designs for the most probable ground conditions and plans in advance what to do if monitoring shows the less favourable conditions. Peck (1969) set out the approach; UK practice formalised it in CIRIA C185 and Eurocode 7 permits it (Patel, 2012, pp. 1489–1490). It suits railroad work where track time is scarce and a conservative design would be expensive: staged embankments on soft ground, shoring beside live track, and slope repairs.

Ingredients

  • Two assessments: the most probable conditions (the design basis) and the most unfavourable credible conditions.
  • Predicted behaviour for each, expressed as values of the monitored quantities.
  • Trigger values (for example green, amber and red) and the pre-planned modification that each trigger sets off; the modification must be buildable in the time between trigger and consequence.
  • A monitoring plan that reads fast enough to act on, and a named person with authority to act.

The method can also be adopted part-way through a conventionally designed job that has run into difficulty, as a “best way out” (Patel, 2012).

Table 5.3-14. Systematic planning of a monitoring program
StepTask
1Define the project conditions
2Predict mechanisms that control behaviour
3Define the geotechnical questions that need to be answered
4Identify, analyse, allocate and plan for control of risks
5Select the parameters to be monitored
6Predict magnitudes of change
7Devise remedial action
8Assign tasks for the construction phase
9Select instruments
10Select instrument locations
11Plan documentation of factors that may influence measured data
12Establish procedures for ensuring data correctness
13List the specific purpose of each instrument
14Prepare budget
15Prepare instrumentation system design report
16Plan installation
17Plan regular calibration and maintenance
18Plan data collection and data management
19Prepare contract documents
20Update budget

Dunnicliff, Marr and Standing (2012), Table 94.1, p. 1366. Every instrument should answer a specific question; if there is no question, there should be no instrument.

The trigger values and the response they start belong in the work plan and the track protection plan before construction begins, not in the monitoring report after a reading is exceeded.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • Patel, D. (2012). Observational method. Chapter 100 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1489–1502Find source ↗Library entry
  • Dunnicliff, J., Marr, W. A. and Standing, J. (2012). Principles of geotechnical monitoring. Chapter 94 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1363–1378Find source ↗Library entry
Supplemental reference · Feng (ed.) (2017)

On-Site Visualization: Showing Monitoring Results Where the Work Is

Conventional monitoring sends readings to an office, where they are processed, checked against thresholds and reported back to the field. Hours or days can pass between a change in the ground and the people at risk learning about it. On-site visualization (OSV) uses sensors that display their own reading at the instrument, usually as the color of an LED. One example is a light-emitting deformation sensor that spans a crack or joint and changes color as the opening reaches set levels. Everyone nearby sees the state of the ground at the same moment, without waiting for a report (Akutagawa, in Feng 2017).

OSV works only if the color levels are tied to actions that the workers know. The reported projects held safety briefings and posted a board at the site showing what to do at each color.

For railroad work: OSV fits the alert and action levels of the observational method (above) and works well where track forces or construction crews work below or beside a moving slope, a shored excavation or a rock face. Tie each color to the trigger-action plan: for example, green to continue, yellow to stop and call the engineer, red to clear the area and protect the track. Give the dispatcher and the track supervisor the same plan. Keep a data logger behind the display so that the record can be analyzed later.

Source: Akutagawa, “On-site visualization for advanced safety management in rock engineering,” in Feng (ed.) (2017), Ch. 7. Summarized and paraphrased. Full reference under S27.