The observational method designs for the most probable ground conditions and plans in advance what to do if monitoring shows the less favourable conditions. Peck (1969) set out the approach; UK practice formalised it in CIRIA C185 and Eurocode 7 permits it (Patel, 2012, pp. 1489–1490). It suits railroad work where track time is scarce and a conservative design would be expensive: staged embankments on soft ground, shoring beside live track, and slope repairs.
The method can also be adopted part-way through a conventionally designed job that has run into difficulty, as a “best way out” (Patel, 2012).
| Step | Task |
|---|---|
| 1 | Define the project conditions |
| 2 | Predict mechanisms that control behaviour |
| 3 | Define the geotechnical questions that need to be answered |
| 4 | Identify, analyse, allocate and plan for control of risks |
| 5 | Select the parameters to be monitored |
| 6 | Predict magnitudes of change |
| 7 | Devise remedial action |
| 8 | Assign tasks for the construction phase |
| 9 | Select instruments |
| 10 | Select instrument locations |
| 11 | Plan documentation of factors that may influence measured data |
| 12 | Establish procedures for ensuring data correctness |
| 13 | List the specific purpose of each instrument |
| 14 | Prepare budget |
| 15 | Prepare instrumentation system design report |
| 16 | Plan installation |
| 17 | Plan regular calibration and maintenance |
| 18 | Plan data collection and data management |
| 19 | Prepare contract documents |
| 20 | Update budget |
Dunnicliff, Marr and Standing (2012), Table 94.1, p. 1366. Every instrument should answer a specific question; if there is no question, there should be no instrument.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.
Conventional monitoring sends readings to an office, where they are processed, checked against thresholds and reported back to the field. Hours or days can pass between a change in the ground and the people at risk learning about it. On-site visualization (OSV) uses sensors that display their own reading at the instrument, usually as the color of an LED. One example is a light-emitting deformation sensor that spans a crack or joint and changes color as the opening reaches set levels. Everyone nearby sees the state of the ground at the same moment, without waiting for a report (Akutagawa, in Feng 2017).
OSV works only if the color levels are tied to actions that the workers know. The reported projects held safety briefings and posted a board at the site showing what to do at each color.
For railroad work: OSV fits the alert and action levels of the observational method (above) and works well where track forces or construction crews work below or beside a moving slope, a shored excavation or a rock face. Tie each color to the trigger-action plan: for example, green to continue, yellow to stop and call the engineer, red to clear the area and protect the track. Give the dispatcher and the track supervisor the same plan. Keep a data logger behind the display so that the record can be analyzed later.
Source: Akutagawa, “On-site visualization for advanced safety management in rock engineering,” in Feng (ed.) (2017), Ch. 7. Summarized and paraphrased. Full reference under S27.