↑ Parent Menu⌂ Main Menu
← Chapter 5.3 Construction Monitoring and Field Testing
GHRM
Railway Ground Hazard Risk Management · 5.0 · Testing
Sections · click a car to open it

5.3.14 Practical Recommendations

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.14 Practical Recommendations
  1. Establish trigger levels in writing before construction begins. Trigger levels for piezometers, settlement plates, and inclinometers must be defined in the geotechnical monitoring plan and agreed upon by the consultant, railroad project engineer, and contractor before any instrumentation is read. Ambiguous triggers during construction lead to decision paralysis at critical moments.
  2. Calibrate nuclear gauges against sand cone tests at each project. At least 5 paired nuclear/sand-cone tests at the start of each project verify gauge performance in the specific soil being tested. Nuclear gauges are accurate for most applications but can be unreliable in gravelly fills or soils with high organic content.
  3. Never accept PDA Case Method results as final capacity without CAPWAP. Case Method is a real-time field screening tool, not a definitive capacity method. CAPWAP signal matching provides the accepted capacity. Owner railroads that require PDA monitoring also require CAPWAP analysis for final acceptance.
  4. Require restrike tests for piles driven in fine-grained soils. Skin friction in clay can be temporarily reduced by remolding during driving (setup loss) and then recovers (soil setup or freeze). Restrike piles at least 24 hours (sand) and 7 days (clay) after driving. Restrike PDA data with CAPWAP often reveals 30–80% capacity gain in clay over initial drive capacity.
  5. Assign GPS coordinates to every compaction test and monitoring reading. Modern nuclear gauges have integrated GPS. For older gauges, use a handheld GPS unit. Station + offset alone is insufficient for QC documentation on long linear projects. GPS coordinates allow test results to be plotted on a project map and deficiency patterns to be identified.
  6. Submit inclinometer and settlement plate data to the railroad engineer weekly during active construction. Do not wait for the final report. Real-time data allows fill rate adjustments before unstable conditions develop. Deliver monitoring data on time; late data is a scope deficiency.
  7. Document all oral decisions in writing within 24 hours. Construction monitoring generates many verbal field decisions (suspend filling, add a lift, reduce hammer stroke). Every decision made verbally in the field must be confirmed in writing by the geotechnical engineer and communicated to the contractor and railroad inspector. Undocumented field decisions are the primary source of claims and disputes in railroad geotechnical construction.
Backfilling and Trench Compaction
Backfilling and Trench Compaction
Critical Lift Planning
Critical Lift Planning

Building in track quality: renewal, tamping and stabilization

Inherent quality is set at construction. After every tamping, track drifts back toward the shape it acquired when it was built or renewed. Three findings show how strong this effect is:

  • A bend in the rail persisted 313 days after ballast renewal and four tampings, and reappeared within 2 months of each tamping. Keep rails straight in handling, and straighten them in place.
  • Long-wave faults in an uncompacted, as-laid ballast surface were still present after 3 years and 6 tampings. Lay track on a compact, fault-free ballast surface.
  • British Rail’s layered renewal reopened at full speed (about 125 mph) within a 48-hour possession, with a longer maintenance cycle afterward. The method: cut about 16 in. under laser depth control; place ballast in layers, then regulate and tamp each one to the same datum and compact it with a dynamic track stabilizer; then make a final stabilizer pass with compaction control.

Undercutter depth control. On a manually controlled undercutter, the cut depth follows the machine’s bogies, and deviations of about ±3 in. were recorded. Laser or water-level control gives a far smoother cut. Specify it, together with a cut surface sloped to the side drains that does not damage an existing blanket.

After tamping. Tamping loosens the cribs and shoulders, so lateral resistance drops. It is substantially regained after about a month of traffic.

  • One full-load stabilizer pass is roughly equivalent to 100,000 tons of traffic for lateral stability, and recovers about half of the loss. For settlement it is equivalent to 100,000–700,000 tons.
  • Relative to freshly tamped track at 0.079 in. of lateral displacement, crib consolidation raised resistance to about 115% and the dynamic track stabilizer to about 134%.
  • Crib and shoulder compaction also cut the scatter of later settlement. Tamped-only track varied 2 to 4 times more.

Tamping policy. Tamp only when geometry requires it. A low-lift tamp does not produce a lasting improvement; a lasting change needs a lift greater than the ballast D50. Stoneblowing complements tamping: use it for low lifts and short-wavelength faults, and use tamping for high lifts and long-wavelength faults.

After Selig & Waters (1994), chs. 14 and 15. Full reference under Supplemental References.

Project management · Haidar (2016)

Delay Analysis: Gross and Net Extensions, Concurrent Delay and Constructive Acceleration

Haidar reviews how extensions of time are calculated when an excusable event occurs while the contractor is already late through its own fault (culpable delay). Under the gross method, the extension runs from the date the event occurred, which sets a new completion date and removes liquidated damages up to it. Under the net method, the contractor receives only the time needed to absorb the event, added to the original completion date. In his example, a contractor six months late is delayed one further month by a relevant event. Under the net method the completion date moves one month past the original date, and five months of culpable delay remain exposed to liquidated damages. The net approach follows Lord Denning’s reasoning in Amalgamated Building Contractors v Waltham Holy Cross (1952).

Gross method, which restarts the extension from the date of the delaying event, compared with the net method, which adds only the time for the extra work to the completion date.
Figure 15-PM4. Gross method, which restarts the extension from the date of the delaying event, compared with the net method, which adds only the time for the extra work to the completion date. Source: Haidar (2016), Fig. 3.10.

On concurrent delay, Haidar cites Henry Boot v Malmaison (2000). If a week of work is lost both to exceptional weather (an excusable event) and to a labor shortage (not excusable), the contractor may still be entitled to a one-week extension. He warns that retrospective CPM analysis of very large networks is unreliable, because every logic link is an assumption and a network can be adjusted to make almost any work critical. Liquidated damages work only if the contract also provides a workable extension mechanism. To recover for constructive acceleration, a contractor must show that the owner failed to grant an adequate extension, insisted on the original date, received notice that the contractor was treating this as acceleration, and that extra cost was actually incurred. The cases cited are English, so the governing contract and jurisdiction control on any U.S. project.

For railroad work: the geotechnical field record is often the evidence in these analyses, so record in daily reports:

  • Track time requested, granted, and cancelled or shortened by operations, with times.
  • Weather and site conditions that stopped earthwork, compaction testing or drilling.
  • Hold points imposed because of monitoring results (inclinometer movement, settlement rate, pore pressure) and the time each was released.
  • Contractor resource shortfalls observed (crews, equipment, material) on the same days.

With all four recorded side by side, the railroad and the contractor can separate excusable delay from culpable delay without reconstructing events months later.

Source: Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing, pp. 75–79. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · Cretu et al. (2011)

Risk Monitoring, Control and Contingency Drawdown

Cretu et al. stress that risk management fails most often after the analysis is finished. They invert the usual pyramid: planning and analysis take less effort than carrying out and tracking the responses. Their monitoring and control step includes tracking every risk in a master register, identifying new risks and retiring old ones, adjusting responses that are not working, managing the risk reserve (contingency) as it is spent, and checking that responses are actually carried out. Each risk gets an owner and a task manager who tracks how well the response works and reports on a set schedule. Updates go back to a single master register held by the project manager. The response action plans can be loaded into the project schedule as dated activities so that overdue responses stand out at each status date. On large projects the authors recommend formal risk reviews at the end of concept development (where “project-killer” risks surface), during preliminary design and during final design (construction and contract risks), with interim reviews during construction.

Construction Rarely Fails at the Point of Failure
Construction Rarely Fails at the Point of Failure

They close with keys to success from NCHRP Report 658. These include: identify risks early and tie contingencies to explicit risks; communicate cost uncertainty as ranges or explicit contingency; assign responsibility for each risk; and monitor threats and opportunities as the way to resolve contingency. They also note that responsibility shared by everyone tends to end up with no one.

For railroad work: Construction monitoring data are the evidence for retiring or escalating geotechnical risks. Link each instrument and test program to the register entries it tests. For example, inclinometer and piezometer readings during staged fill test the “foundation instability” risk, and proof-rolling and density results test the “unsuitable subgrade quantity” risk. Set the threshold that would trigger the planned response. Report contingency drawdown against those same entries at each progress meeting, so the railroad can see that the reserve is being spent on risks that actually occurred or released as they are retired, not absorbed by unrelated changes.

Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 149–150, 164–168. Summarized and paraphrased. Full reference under Supplemental References.