Settlement records from plates and survey points can be extrapolated to estimate the final settlement and the time to reach it, which is often more reliable than the laboratory-based prediction made before construction. The estimate decides when a surcharge can come off, when track can be surfaced to final grade, and whether the design settlement was right (Shi and Kong 2018; Kong 2018a, 2018b).
| Method | Form | Use |
|---|---|---|
| Asaoka | sj = β0 + β1 sj−1 at equal time steps (Eq. 5.3-8); sf = β0/(1 − β1) (Eq. 5.3-9) | Consolidation under constant load; graphical and easy to update |
| Hyperbolic | (t − t0)/(s − s0) = a + b(t − t0); sf = s0 + 1/b (Eq. 5.3-10) | Constant load; best fit for degree of consolidation 60% to 90%; tends to over-predict if used early |
| Three-point exponential | sf = (s1s3 − s2²)/(s1 + s3 − 2s2) for three readings at equal intervals (Eq. 5.3-11) | Quick check; sensitive to reading errors |
| Logistic (Pearl) and Gompertz growth curves | s(t) = L/(1 + a e−bt); s(t) = e(k + a bt) | S-shaped records that include the construction period of high fills; need many readings, split into three equal groups for fitting |
A second main track for a Class I railroad located in Louisiana is being built on a new embankment over soft clay improved with vertical drains. The design calls for the surcharge to stay in place until 90% of primary settlement has occurred, then be removed so the subballast and track can be placed. The fill reached full surcharge height, and a settlement plate under the centerline has been read every 30 days since. The engineer must predict the final settlement, the present degree of consolidation, and when the surcharge can come off.
| Variable | Value | Description |
|---|---|---|
| Δt | 30 days | Equal reading interval after the surcharge was complete |
| s1 to s5 | 6.0, 8.4, 10.3, 11.9, 13.1 in. | Plate settlement at 30, 60, 90, 120 and 150 days |
| Criterion | U = 90% | Surcharge removal |
(a) sf ≈ 18.1 in. (b) U ≈ 72%. (c) About 140 more days, or about 290 days after full surcharge.
Keep reading the plate monthly and refit after each reading; remove the surcharge only when the measured settlement reaches about 16.3 in. and the piezometers show excess pore pressure has largely dissipated. Compare 18.1 in. with the design prediction: a large difference means the design cv or compressibility was wrong, which matters for other sections of the line built on the same clay.
For railroad work: Track on new embankments over soft ground is usually surfaced to final grade only after primary settlement is essentially complete, and the predicted remaining settlement sets the ballast lift and resurfacing plan. Read plates and survey points at a fixed interval so that Asaoka plots can be used, keep piezometers alongside, and document the fit with each reading so the decision to remove surcharge is traceable (Section 5.3.21).
Source: Shi and Kong (2018); Kong (2018a, 2018b). Full references under Supplemental References.