5.3.1 Background and Railroad Context

Construction monitoring is the geotechnical consultant's final opportunity to verify that subsurface conditions match design assumptions, that materials meet…
Authors: Daniel P. Colwell and Mario Ruel
5.3.1 Background and Railroad Context

Railroad construction monitoring differs from typical civil construction monitoring in three critical ways:

  1. Active railroad operations. Most railroad capital projects are constructed while adjacent or parallel tracks remain in service. Contractor and geotechnical inspector access requires roadway worker protection (RWP) and must be coordinated with the dispatcher. Monitoring instruments must be read without delaying trains, and inspectors must be prepared to evacuate work zones on short notice.
  2. Tight schedule windows. Track outages (track windows) for construction are typically 4–8 hours per day, with total project schedules measured in weeks, not months. Monitoring data must be processed in near-real-time so that decisions on embankment lifts, pile acceptance, or shoring movements can be made before the next construction window.
  3. Client construction inspectors are co-present. Owner railroads usually assign their own construction inspectors to capital projects. The geotechnical inspector works alongside — not instead of — the railroad inspector. Role delineation must be established at the pre-construction meeting. The geotechnical inspector owns subsurface QA; the railroad inspector owns track geometry, clearances, and operational compliance.
Project management · ASCE (2012)

QA versus QC: Who Is Responsible for What

ASCE Manual 73 (ASCE 2012) separates two functions that are often blurred together as “QA/QC.” Quality assurance is the planned, systematic work of the owner or its agent to gain confidence that the design complies with codes and criteria and that construction complies with the contract documents; it verifies that the other parties’ quality control is working. Quality control belongs to the design professional (control of the contract documents) and to the constructor (control of the work), and includes observations, calculations, inspections, tests and documentation.

The owner sets the value placed on quality, funds it, and decides whether to use a standing generic QA plan, a project-specific plan, or a tailored generic plan. The owner may specify the designer’s and constructor’s QC plans prescriptively or in performance terms. During construction the owner must choose who inspects: the owner, the design professional, an independent agency, a code official, or the constructor. The Manual stresses that none is always best and the choice should balance cost, safety, schedule and quality. A resident project representative (RPR) may oversee the constructor’s QC and reviews the constructor’s QC plan before production starts.

A typical constructor project-specific QC plan addresses a skilled workforce, a QC organization, a submittal schedule, inspections, mock-ups and sample construction, a testing plan including special inspections, documentation, and corrective action when acceptance criteria are not met. It should also cover subcontractor qualification, control of measuring and test equipment, and segregation of nonconforming material. The Manual summarizes responsibilities in a chart: the owner establishes the QA program; the designer develops design-phase QC; the constructor develops and documents construction QC; and all communicate regularly.

For railroad work: On a railroad-funded embankment or subgrade project the railroad (or its engineering consultant acting as RPR) performs QA, and the contractor performs QC testing such as compaction and gradation. When the geotechnical consultant’s field staff perform acceptance testing, the scope should say whether that testing is QA (owner verification) or is replacing contractor QC, because the two carry different responsibility for rework and different testing frequencies. State this explicitly in the construction monitoring scope and the GSP.

Source: American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE, pp. 169–170, 191–199. Summarized and paraphrased. Full reference under Supplemental References.