7.2.3 Prefabricated Vertical Drains (PVDs) with Staged Loading

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel
7.2.3 Prefabricated Vertical Drains (PVDs) with Staged Loading
7.2.3.1 Radial Consolidation Theory (Barron 1948)

PVDs accelerate consolidation by reducing the drainage path from the full layer thickness H_dr (vertical flow) to the horizontal spacing s_r between drains (radial flow). The average degree of consolidation from radial drainage U_r is:

Ur = 1 - exp[-8 Trμ]

Where T_r is the radial time factor:

Tr = ch ⋅ tde2

And:

  • c_h = horizontal coefficient of consolidation (ft²/day); typically 2–5× c_v for laminated clays
  • t = elapsed time (days)
  • d_e = equivalent diameter of influence zone (ft) = 1.13 × s for square grid; 1.05 × s for triangular grid; s = drain spacing (ft)
  • μ = drain spacing/smear/resistance factor:
μ = ln(dedw) - 34 + ds2de2 - ds2(khks - 1)ln(dsdw) + π kh ⋅ z(2L - z)qw

Where:

  • d_w = equivalent drain diameter (ft); standard PVD: d_w = 2(a + b)/π where a = 4 in. (width), b = 0.16 in. (thickness) → 0.22 ft; Rixner et al. (1986) recommend (a + b)/2 ≈ 0.17 ft. This chapter uses d_w ≈ 0.196 ft
  • d_s = smear zone diameter (ft) = 2–3 × d_mandrel (typically 0.5 ft for standard mandrel)
  • k_h/k_s = horizontal to smear zone permeability ratio (typically 3–5)
  • q_w = drain discharge capacity (ft³/day); typically about 10–80 ft³/day (100–800 m³/yr) for standard PVDs
  • L = drain length (ft); z = depth (ft)
Placing the anchor on the drain during PVD installation
Photo 7.2.3-1. Placing the Anchor on the Drain. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Inserting the mandrel into the ground during PVD installation
Photo 7.2.3-2. Inserting the Mandrel into the Ground. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Inserting the drain core within the jacket to maintain continuity
Photo 7.2.3-3. Inserting the Drain Core within the Jacket to Maintain Continuity. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Stapling the drain splice
Photo 7.2.3-4. Stapling the Drain Splice. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Schematic of a generic prefabricated vertical drain installation for a highway embankment
Photo 7.2.3-5. Schematic of a Generic PVD Installation for a Highway Embankment, showing the surcharge, drainage blanket, wick drains, and monitoring instrumentation (deep settlement points, settlement platform, groundwater observation well, inclinometer, and piezometers). (Figure from Elias et al. 2006)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

For preliminary design, the simplified Hansbo (1981) formula is commonly used (omitting well resistance and smear):

μ ≈ ln(dedw) - 0.75
Inputs for the equations in this section (13)
SymbolWhat it isComes fromHow to get itTypical range
Ur1 - exp[ -8 T_r μ ]Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Trintermediate value computed on this pageAnother equationComputed: T_r = c_h ⋅ t d_e^2project-specific
chhorizontal coefficient of consolidation (ft²/day)Lab test (or field)Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests.CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group
telapsed time (days)TimeElapsed test time (recorded) or the analysis time chosen for design.project-specific
deequivalent diameter of influence zone (ft)Another equationComputed: d_e = 1.13 × s for square grid; 1.05 × s for triangular gridproject-specific
sdrain spacing (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
μdrain spacing/smear/resistance factor:Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
dwequivalent drain diameter (ft)Product dataManufacturer's data sheet for the specified product, confirmed by project QA testing.project-specific
dssmear zone diameter (ft)Another equationComputed: d_s = 2–3 × d_mandrel (typically 0.5 ft for standard mandrel)typically 0.5 ft for standard mandrel
kh/kshorizontal to smear zone permeability ratio (typically 3–5)Field or lab testField: pumping test, slug test (ASTM D4044, withdrawn 2024) or packer test. Lab: constant head (D2434) for sands, flexible-wall (D5084) for clays. Hazen k ≈ C·D102 for clean sands only.clean sand 1–100, clay < 0.001 ft/day · by USCS group
qwdrain discharge capacity (ft³/day)Product dataManufacturer's data sheet for the specified product, confirmed by project QA testing.typically about 10–80 ft³/day (100–800 m³/yr) for standard PVDs
Ldrain length (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
zdepth (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
7.2.3.2 Combined Radial and Vertical Consolidation

The total degree of consolidation U_total combines radial and vertical drainage:

1 - Utotal = (1 - Ur)(1 - Uv)

Where U_v is from the Terzaghi vertical consolidation equation (Chapter 6.2, Section 6.2.7).

7.2.3.3 Staged Loading for Embankment Construction

Where subgrade shear strength s_u is insufficient for the full embankment load, construction proceeds in stages with PVDs to gain strength before next stage:

Strength gain from consolidation (Ladd 1991 SHANSEP):

su,consolidated = S ⋅ σ'v,consolidated ⋅ OCRm

Where S = 0.22–0.25 (normalized undrained strength ratio for soft clay); m = 0.88 (for CK₀U triaxial compression). For each stage: place fill to height H_i; wait for U_r ≥ 80% before next stage; verify FS_slope ≥ 1.3 (EOC) before next placement.

Table 7.2-2: PVD Design Parameters — Representative Railroad Embankment Cases
ProjectRailroadSoft Layer (ft)c_h (ft²/day)c_v (ft²/day)Drain Spacing (ft)GridTarget UtotalTime to Utarget
Coastal Georgia MainlineClass I350.0120.0065.0Triangle90%120 days
Manitoba Prairie FillClass I280.0180.0094.5Square85%90 days
Louisiana Yard ExpansionClass I420.0150.0085.0Triangle90%150 days
Quebec Mainline Soft ClayClass I500.0100.0054.0Triangle90%180 days
Passenger corridor Embankment WideningPassenger200.0220.0114.0Square95%75 days
Inputs for the equations in this section (5)
SymbolWhat it isComes fromHow to get itTypical range
S0.22–0.25 (normalized undrained strength ratio for soft clay)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
m0.88 (for CK₀U triaxial compression)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
suundrained shear strengthLab or field testLab: UU triaxial (ASTM D2850) or unconfined compression (D2166). Field: vane shear (D2573), CPT su = (qt − σv)/Nkt, or pocket penetrometer/Torvane for screening.soft 250–500, stiff 1,000–2,000 psf · by USCS group
OCRpreconsolidation stress / OCRLab test (or correlation)Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0.OCR 1 (NC) to > 4 (heavily OC) · by USCS group
σ'vvertical stress / pore pressureAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific

Wick drains in rail work

Wick drains give trapped pore water a short vertical path out, accelerating consolidation of soft saturated ground that would otherwise take years to drain. Several mandrels can work a large site at once.

After Geotechnology for Railroaders Program, Module 6.2; §02. Full reference under Supplemental References.

Case study: 7.2.17.2 Wick-drain rigs on dredged sand over 104 psf clay: four ways to size the platform (Look 2023), in §17.17 Case Studies.

Figure 7.2-14. Wick-drain installation rigs.
Figure 7.2-14. Wick-drain installation rigs.
7.2.3.4 Prefabricated Vertical Drains Under Embankments and New Track

A new track or siding on soft clay can settle for years. Prefabricated vertical (wick) drains shorten the drainage path from half the clay thickness to half the drain spacing, so most of the primary settlement can be taken out under a preload before the track goes down. Craig's Soil Mechanics and Das's Advanced Soil Mechanics give the theory. Barron's equal-strain solution covers radial flow to the drain. Barron's smear-zone extension (Das Eq. 8.177) accounts for the clay remolded by the mandrel. Carrillo's rule combines radial and vertical drainage. Craig stresses that ch controls the design and matters more than refinements to the theory. Drains do nothing to secondary compression, and they may help little in overconsolidated clay that stays below its preconsolidation pressure.

7.2.3.4.1 Method

Equation 7.2-1. Radial and combined consolidation

dw = 2(a + b)/π;   de = 1.128s (square) or 1.05s (triangular);   n = de/dw

Ur = 1 − exp(−8Tr/F),   Tr = cht/de²
F = n²/(n² − S²) ln(n/S) − 3/4 + S²/(4n²) + (kh/ks)(n² − S²)/n² ln S
U = 1 − (1 − Uv)(1 − Ur)

With no smear (S = 1) F reduces to Barron's F(n) = n²/(n² − 1) ln n − (3n² − 1)/4n². The calculator reproduces Das's Example 8.11: 6 m of clay drained both ways, 0.45 m drains at 3 m effective diameter, and U = 0.871 at one year against the published 0.870 (217.5 mm of the 250 mm). It also reproduces Craig's Example 7.8, where 400 mm sand drains in a square pattern must reach 85% in six months under 10 m of single-drained clay. The calculator's spacing is 10.34 ft (3.15 m), against Craig's 3.2 m read from Barron's chart.

7.2.3.4.2 Worked example

A siding embankment over 30 ft of double-drained soft clay (cv = 0.15, ch = 0.30 ft²/day) will settle 18 in. Without drains only 39.1% of that occurs in six months. Band drains (4 × 0.15 in.) at 5 ft on a triangular grid, with a smear zone twice the drain diameter, reach 99.6% in 180 days and 90% in 72 days. The widest spacing that still reaches 90% in six months is 7.80 ft, which lowers the drain footage.

Get ch from CPTu dissipation tests in the clay itself (Chapter 5.1), not from oedometer cv. Monitor settlement plates and piezometers through the preload, and remove the surcharge on measured settlement, not on the predicted schedule.

Open the wick drain calculator →
Barron equal-strain radial consolidation with a smear zone, combined with vertical drainage, settlement with and without drains, the spacing needed to reach a target degree of consolidation, and the time to reach it.

7.2.3.4.3 Drain types and checks on the theory

Table 7.2-9. Vertical drain types (after Craig, Section 7.11)
TypeTypical sizeNotes
Sand drain (bored or driven, sand backfill)8 to 16 in. diameter, to depths over 100 ftCareful backfilling needed to avoid necking; a large drain can act as a weak pile and carry part of the load
Sandwick (filter sock filled with sand)About 2.5 in. diameterFlexible, so lateral soil movement rarely breaks continuity
Band (wick) drain: plastic core in filter fabricAbout 4 × 0.16 in.Installed with a mandrel and anchor plate; equivalent diameter = perimeter/π; the usual choice today

Smear around the drain can be modeled by a reduced ch or a reduced drain diameter. The calculator instead uses Barron's smear-zone solution as given by Das.

Table 7.2-10. Time factor Tr for radial consolidation, Das Table 8.8 and the calculator's equation
n = de/dwF(n)Tr at Ur = 50%: Das / equationTr at Ur = 80%: Das / equation
50.9360.0811 / 0.08110.1884 / 0.1884
101.5780.1368 / 0.13680.3175 / 0.3175
151.9710.1708 / 0.17080.3966 / 0.3966
202.2540.1953 / 0.19530.4534 / 0.4534
252.4740.2144 / 0.21440.4978 / 0.4978

7.2.3.4.4 Spacing, smear and the settlement curve

The worked example was rerun to show how drain spacing and smear affect the schedule. The time to 90% consolidation rises roughly with the square of the spacing: about 45 days at 4 ft against 285 days at 10 ft. Smear matters less but is not negligible. Going from no smear to a smear zone four times the drain diameter adds about half again to the time. Because the smear zone grows with mandrel size, use the smallest mandrel that can install the drain.

Table 7.2-11. Time to 90% consolidation for the worked example (30 ft clay, ch = 0.30 ft²/day, triangular pattern), from the calculator
Spacing (ft)Days to 90%Smear ratio ds/dw (5 ft spacing, kh/ks = 2)Days to 90%
4451 (no smear)57
572272
6106381
7145486
8189
9236
10285
0100200300051015Time after loading (days)Settlement (in.)Drains at 5 ftDrains at 7 ftDrains at 9 ft
Figure 7.2-25. Settlement against time for the worked example with drains at 5, 7 and 9 ft on a triangular grid (final settlement 18 in.).

7.2.3.4.5 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • R.F. Craig, Craig's Soil Mechanics, 7th edition: vertical drains, design considerations and Example 7.8Find source ↗Library entry
  • B.M. Das, Advanced Soil Mechanics, 4th edition: sand drain theory (free strain, equal strain, smear), Table 8.8 and Example 8.11Find source ↗
  • M. Budhu, Soil Mechanics and Foundations, 3rd edition: one-dimensional consolidation and time rateFind source ↗
  • B.M. Das, Principles of Geotechnical Engineering, 7th edition: precompression and consolidationFind source ↗
Supplemental reference · Yan, Feng and Chu (2009)

Vacuum Preloading: How It Works and What It Achieved

Vacuum preloading lowers the pore water pressure in the soil instead of raising the total stress with fill. The effective stress rises by the same amount in both cases, but under vacuum the soil is pulled inward rather than pushed outward, so there is no risk of a stability failure during loading. Where more load is needed than the vacuum can supply, fill surcharge is added on top of the sealed membrane.

  • Case study: PVDs on a 3.3-ft square grid with 4-in. corrugated collector pipes distributed the vacuum well.
  • Total settlement exceeded 3 ft, field vane strength roughly doubled, and the water content fell substantially.
  • The paper discusses the effective depth of vacuum and how to estimate the degree of consolidation from settlement and pore pressure records.

For railroad work: Vacuum, alone or combined with fill, suits new yard tracks and embankments on very soft clay where the fill needed for an equivalent surcharge would itself be unstable. It removes the staged-loading waiting periods that fill surcharge needs. The vacuum sheet in Section 7.2.16 covers design and specification.

Source: Yan, Feng and Chu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Edil and Berilgen (2009)

Staged Construction of Tall Fills Directly on Soft Ground

Removing thick soft river deposits and replacing them with compacted fill added a third or more to the cost of the earth dams studied. The authors show that 65- to 100-ft-high dams can instead be built directly on fine-grained soft deposits by staged construction, with stage height, rate and waiting time set by undrained strength gain analysis.

  • PVDs shortened the staged program from about 15 years to about 2 years.
  • Cracking was not a problem where the subsurface was laterally uniform; the transition to the abutments needed the most attention.
  • Fine-grained deposits without continuous sand or gravel lenses posed little seepage risk; granular deposits did.

For railroad work: The same principles govern tall railroad embankments and bridge approach fills on soft ground. The transition at an abutment is the counterpart of the dam-to-abutment transition: plan settlement monitoring and stage limits there with the most care (Chapter 6.2, Section 6.2.6).

Source: Edil and Berilgen (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.