PVDs accelerate consolidation by reducing the drainage path from the full layer thickness H_dr (vertical flow) to the horizontal spacing s_r between drains (radial flow). The average degree of consolidation from radial drainage U_r is:
Where T_r is the radial time factor:
And:
Where:





For preliminary design, the simplified Hansbo (1981) formula is commonly used (omitting well resistance and smear):
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Ur | 1 - exp[ -8 T_r μ ] | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
| Tr | intermediate value computed on this page | Another equation | Computed: T_r = c_h ⋅ t d_e^2 | project-specific |
| ch | horizontal coefficient of consolidation (ft²/day) | Lab test (or field) | Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests. | CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group |
| t | elapsed time (days) | Time | Elapsed test time (recorded) or the analysis time chosen for design. | project-specific |
| de | equivalent diameter of influence zone (ft) | Another equation | Computed: d_e = 1.13 × s for square grid; 1.05 × s for triangular grid | project-specific |
| s | drain spacing (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| μ | drain spacing/smear/resistance factor: | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
| dw | equivalent drain diameter (ft) | Product data | Manufacturer's data sheet for the specified product, confirmed by project QA testing. | project-specific |
| ds | smear zone diameter (ft) | Another equation | Computed: d_s = 2–3 × d_mandrel (typically 0.5 ft for standard mandrel) | typically 0.5 ft for standard mandrel |
| kh/ks | horizontal to smear zone permeability ratio (typically 3–5) | Field or lab test | Field: pumping test, slug test (ASTM D4044, withdrawn 2024) or packer test. Lab: constant head (D2434) for sands, flexible-wall (D5084) for clays. Hazen k ≈ C·D102 for clean sands only. | clean sand 1–100, clay < 0.001 ft/day · by USCS group |
| qw | drain discharge capacity (ft³/day) | Product data | Manufacturer's data sheet for the specified product, confirmed by project QA testing. | typically about 10–80 ft³/day (100–800 m³/yr) for standard PVDs |
| L | drain length (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| z | depth (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
The total degree of consolidation U_total combines radial and vertical drainage:
Where U_v is from the Terzaghi vertical consolidation equation (Chapter 6.2, Section 6.2.7).
Where subgrade shear strength s_u is insufficient for the full embankment load, construction proceeds in stages with PVDs to gain strength before next stage:
Strength gain from consolidation (Ladd 1991 SHANSEP):
Where S = 0.22–0.25 (normalized undrained strength ratio for soft clay); m = 0.88 (for CK₀U triaxial compression). For each stage: place fill to height H_i; wait for U_r ≥ 80% before next stage; verify FS_slope ≥ 1.3 (EOC) before next placement.
| Project | Railroad | Soft Layer (ft) | c_h (ft²/day) | c_v (ft²/day) | Drain Spacing (ft) | Grid | Target Utotal | Time to Utarget |
|---|---|---|---|---|---|---|---|---|
| Coastal Georgia Mainline | Class I | 35 | 0.012 | 0.006 | 5.0 | Triangle | 90% | 120 days |
| Manitoba Prairie Fill | Class I | 28 | 0.018 | 0.009 | 4.5 | Square | 85% | 90 days |
| Louisiana Yard Expansion | Class I | 42 | 0.015 | 0.008 | 5.0 | Triangle | 90% | 150 days |
| Quebec Mainline Soft Clay | Class I | 50 | 0.010 | 0.005 | 4.0 | Triangle | 90% | 180 days |
| Passenger corridor Embankment Widening | Passenger | 20 | 0.022 | 0.011 | 4.0 | Square | 95% | 75 days |
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| S | 0.22–0.25 (normalized undrained strength ratio for soft clay) | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
| m | 0.88 (for CK₀U triaxial compression) | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
| su | undrained shear strength | Lab or field test | Lab: UU triaxial (ASTM D2850) or unconfined compression (D2166). Field: vane shear (D2573), CPT su = (qt − σv)/Nkt, or pocket penetrometer/Torvane for screening. | soft 250–500, stiff 1,000–2,000 psf · by USCS group |
| OCR | preconsolidation stress / OCR | Lab test (or correlation) | Preconsolidation stress from the consolidation curve (Casagrande or work method, ASTM D2435). CPT screening: σ'p ≈ 0.33(qt − σv). OCR = σ'p/σ'v0. | OCR 1 (NC) to > 4 (heavily OC) · by USCS group |
| σ'v | vertical stress / pore pressure | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
Wick drains give trapped pore water a short vertical path out, accelerating consolidation of soft saturated ground that would otherwise take years to drain. Several mandrels can work a large site at once.
After Geotechnology for Railroaders Program, Module 6.2; §02. Full reference under Supplemental References.
Technology sheets for this method · see 7.2.16 Technology Library
Case study: 7.2.17.2 Wick-drain rigs on dredged sand over 104 psf clay: four ways to size the platform (Look 2023), in §17.17 Case Studies.

A new track or siding on soft clay can settle for years. Prefabricated vertical (wick) drains shorten the drainage path from half the clay thickness to half the drain spacing, so most of the primary settlement can be taken out under a preload before the track goes down. Craig's Soil Mechanics and Das's Advanced Soil Mechanics give the theory. Barron's equal-strain solution covers radial flow to the drain. Barron's smear-zone extension (Das Eq. 8.177) accounts for the clay remolded by the mandrel. Carrillo's rule combines radial and vertical drainage. Craig stresses that ch controls the design and matters more than refinements to the theory. Drains do nothing to secondary compression, and they may help little in overconsolidated clay that stays below its preconsolidation pressure.
Equation 7.2-1. Radial and combined consolidation
Ur = 1 − exp(−8Tr/F), Tr = cht/de²
F = n²/(n² − S²) ln(n/S) − 3/4 + S²/(4n²) + (kh/ks)(n² − S²)/n² ln S
U = 1 − (1 − Uv)(1 − Ur)
With no smear (S = 1) F reduces to Barron's F(n) = n²/(n² − 1) ln n − (3n² − 1)/4n². The calculator reproduces Das's Example 8.11: 6 m of clay drained both ways, 0.45 m drains at 3 m effective diameter, and U = 0.871 at one year against the published 0.870 (217.5 mm of the 250 mm). It also reproduces Craig's Example 7.8, where 400 mm sand drains in a square pattern must reach 85% in six months under 10 m of single-drained clay. The calculator's spacing is 10.34 ft (3.15 m), against Craig's 3.2 m read from Barron's chart.
A siding embankment over 30 ft of double-drained soft clay (cv = 0.15, ch = 0.30 ft²/day) will settle 18 in. Without drains only 39.1% of that occurs in six months. Band drains (4 × 0.15 in.) at 5 ft on a triangular grid, with a smear zone twice the drain diameter, reach 99.6% in 180 days and 90% in 72 days. The widest spacing that still reaches 90% in six months is 7.80 ft, which lowers the drain footage.
Open the wick drain calculator →
Barron equal-strain radial consolidation with a smear zone, combined with vertical drainage, settlement with and without drains, the spacing needed to reach a target degree of consolidation, and the time to reach it.
| Type | Typical size | Notes |
|---|---|---|
| Sand drain (bored or driven, sand backfill) | 8 to 16 in. diameter, to depths over 100 ft | Careful backfilling needed to avoid necking; a large drain can act as a weak pile and carry part of the load |
| Sandwick (filter sock filled with sand) | About 2.5 in. diameter | Flexible, so lateral soil movement rarely breaks continuity |
| Band (wick) drain: plastic core in filter fabric | About 4 × 0.16 in. | Installed with a mandrel and anchor plate; equivalent diameter = perimeter/π; the usual choice today |
Smear around the drain can be modeled by a reduced ch or a reduced drain diameter. The calculator instead uses Barron's smear-zone solution as given by Das.
| n = de/dw | F(n) | Tr at Ur = 50%: Das / equation | Tr at Ur = 80%: Das / equation |
|---|---|---|---|
| 5 | 0.936 | 0.0811 / 0.0811 | 0.1884 / 0.1884 |
| 10 | 1.578 | 0.1368 / 0.1368 | 0.3175 / 0.3175 |
| 15 | 1.971 | 0.1708 / 0.1708 | 0.3966 / 0.3966 |
| 20 | 2.254 | 0.1953 / 0.1953 | 0.4534 / 0.4534 |
| 25 | 2.474 | 0.2144 / 0.2144 | 0.4978 / 0.4978 |
The worked example was rerun to show how drain spacing and smear affect the schedule. The time to 90% consolidation rises roughly with the square of the spacing: about 45 days at 4 ft against 285 days at 10 ft. Smear matters less but is not negligible. Going from no smear to a smear zone four times the drain diameter adds about half again to the time. Because the smear zone grows with mandrel size, use the smallest mandrel that can install the drain.
| Spacing (ft) | Days to 90% | Smear ratio ds/dw (5 ft spacing, kh/ks = 2) | Days to 90% |
|---|---|---|---|
| 4 | 45 | 1 (no smear) | 57 |
| 5 | 72 | 2 | 72 |
| 6 | 106 | 3 | 81 |
| 7 | 145 | 4 | 86 |
| 8 | 189 | ||
| 9 | 236 | ||
| 10 | 285 |
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.
Vacuum preloading lowers the pore water pressure in the soil instead of raising the total stress with fill. The effective stress rises by the same amount in both cases, but under vacuum the soil is pulled inward rather than pushed outward, so there is no risk of a stability failure during loading. Where more load is needed than the vacuum can supply, fill surcharge is added on top of the sealed membrane.
For railroad work: Vacuum, alone or combined with fill, suits new yard tracks and embankments on very soft clay where the fill needed for an equivalent surcharge would itself be unstable. It removes the staged-loading waiting periods that fill surcharge needs. The vacuum sheet in Section 7.2.16 covers design and specification.
Source: Yan, Feng and Chu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.
Removing thick soft river deposits and replacing them with compacted fill added a third or more to the cost of the earth dams studied. The authors show that 65- to 100-ft-high dams can instead be built directly on fine-grained soft deposits by staged construction, with stage height, rate and waiting time set by undrained strength gain analysis.
For railroad work: The same principles govern tall railroad embankments and bridge approach fills on soft ground. The transition at an abutment is the counterpart of the dam-to-abutment transition: plan settlement monitoring and stage limits there with the most care (Chapter 6.2, Section 6.2.6).
Source: Edil and Berilgen (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.