7.2.6 Grouting Methods

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel
7.2.6 Grouting Methods
7.2.6.1 Compaction Grouting

Compaction grouting injects a stiff grout (slump < 2 in.) that does not penetrate soil pores but instead forms a grout bulb, displacing and densifying surrounding soils. Used for:

Bio-mediated soil treatment overview
Bio-mediated soil treatment overview
Jet grouting process
Jet grouting process
Jet Grouting — Multiple Rigs Operating
Jet Grouting — Multiple Rigs Operating
Figure 7.2-17. Compaction grouting and dynamic compaction concept.
Figure 7.2-17. Compaction grouting and dynamic compaction concept.
  • Densification of loose fills beneath existing track (historical mainline settlement)
  • Foundation underpinning adjacent to active track
  • Correction of localized subgrade settlement
Jet grouting process schematic
Photo 7.2.6-1. Jet grouting process schematic. Photograph courtesy of Hayward Baker, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Multiple jet grouting rigs on site
Photo 7.2.6-2. Multiple jet grouting rigs. Photograph courtesy of Soilmec S.p.A. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

Grout volume per bulb:

Vgrout = π6 Dbulb3    (ft3)

Where D_bulb = target bulb diameter (ft); typically 1.5–2.5 ft. Injection spacing = 4–8 ft on grid; primary and secondary passes used to achieve uniform densification.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
Dbulbtarget bulb diameter (ft)Design criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.typically 1.5–2.5 ft. Injection spacing = 4–8 ft on grid
7.2.6.2 Permeation Grouting

Low-viscosity grout (sodium silicate, acrylamide, or ultrafine cement) is injected under low pressure to penetrate pore spaces without disturbing soil fabric. Used in granular soils (D₁₅ > 0.025 in.) to reduce permeability or improve strength.

Pressure grouting of fractured rock
Pressure grouting of fractured rock

Groutability ratio (GR):

GR = D15,soilD85,grout ≥ 24    (for successful permeation)

Groutability limits for permeation grouting

  • Cement and clay grouts suit sands and gravels only. They do not suit silts or clays, or soils with more than about 10% fines.
  • Silicate chemical grouts reach coarse silts and medium to fine sands.
  • Check the particle-size ratio: D15(soil) ≥ 25 × D85(grout).

After Selig & Waters (1994), ch. 11. Full reference under Supplemental References.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
GRD_15,soil D_85,grout ≥ 24    (for successful permeation)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
7.2.6.3 Jet Grouting

High-pressure jetting (3,000–7,000 psi) simultaneously erodes and mixes in-situ soil with cement grout, creating cylindrical treated columns. Single-fluid, double-fluid, and triple-fluid systems produce column diameters of 1.5–5.0 ft. Used by a passenger railroad for underpinning passenger corridor structures and by a Class I railroad for liquefaction mitigation under existing embankments.

Column diameter depends on the soil, the jet system and the jetting parameters (pressure, flow, lift and rotation rates), so confirm it with test columns before production.

Supplemental reference

Slurry pressure injection under live track

The grouting methods above are general. The method developed specifically for railroad subgrades is slurry pressure injection from hi-rail equipment, which can clear for trains between injections. Soft fine-grained subgrade and repeated resurfacing drive ballast down into ballast pockets that trap water, cause squeezes and keep the soil weak. Injection works in two ways:

  • Mechanical (void filling): a slurry heavier than water displaces trapped water from the pockets and sets into a ballast–grout block that resists the progressive shear (Figure 17-S1). Railroad cements (about 70–80% finely ground limestone, 20–30% cement clinker) reach up to about 1,000 psi; lime/fly ash up to about 125 psi. Slurry specific gravity should be at least 1.25.
  • Chemical (lime): hydrated or quicklime slurry travels along fissures, slickensides and shear planes and reacts with the clay. Lime slurry does not set on its own. Results may take 6–9 months to appear as lime migrates into the soil. Pengelly reports a CPT-measured average shear strength increase of 308% ten months after lime/fly ash injection.
Subgrade cross-sections before and after slurry injection: ballast pockets forcing lateral shear (top) and the solidified ballast&ndash;slurry block resisting shear (bottom).
Supplemental Figure 17-S1. Subgrade cross-sections before and after slurry injection: ballast pockets forcing lateral shear (top) and the solidified ballast–slurry block resisting shear (bottom). Source: Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR).

Table 17-S1. Typical injection parameters (FRA handbook, 1977, and Pengelly)

ParameterTypical value
RodsThree, 5 ft apart: one on track centerline, one each side (Figure 17-S2)
DepthLime: 10–16 ft historically; most programs ≥ 20 ft; modern units 30–40 ft
Longitudinal spacingAbout 5 ft (every second or third crib; never more than 4 crib spaces); every crib, staged, in severe distress
Stage interval18–24 in., injecting downstage (top down) to refusal or target take
Pump pressure50–250 psi (150 psi common); keep low to maximize take
Lime slurry2.5–3 lb lime per gallon of water (never > 4); SG about 1.15–1.17
Quantity30–50 gal per track ft for a 10–16 ft lime injection (FRA); 200–250 lb dry solids per track ft typical, 150 mild to 1,000 severe (Pengelly)
StagingSecond or third pass 48 hr or more later into skipped cribs, e.g., deep lime pass then shallow void-filling pass
Injection rod spacing across the track (5 ft) and crib staging of initial and secondary injections.
Supplemental Figure 17-S2. Injection rod spacing across the track (5 ft) and crib staging of initial and secondary injections. Source: Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR).

Investigation and testing. The FRA handbook suggests about 2 + L/250 borings for L up to 1,000 ft of problem track, 6 + (L − 1,000)/300 for 1,000–4,000 ft, and 16 + (L − 4,000)/400 for 4,000–10,000 ft, with continuous Shelby tubes for 5 ft just below the ballast and borings at least 5 ft below the deepest planned injection. Lab “lime-inoculated” specimens (1% lime by dry weight, representing 5-ft centers) are compared with untreated controls in swell, consolidation and strength tests. CPT before and after injection locates ballast pockets, sets the target take and verifies improvement. Contractor case histories (a line in Iowa, every other crib, 14–40 ft; a line in Missouri, every crib to 20 ft after CPT found weak soil to 18–20 ft) used this approach. The FRA handbook itself cautions that results cannot yet be predicted reliably from lab tests and recommends a field test section before a program.

Untreated vs bio-cemented sand (microscope)
Untreated vs bio-cemented sand (microscope)

Material caution: Pengelly attributes past poor results partly to substandard fly ash and recommends only ash that reliably sets (Class C in his experience). Test every ash source for compatibility. Note that his description of the coal sources is reversed relative to ASTM C618, where Class F comes from bituminous or anthracite coal and Class C from sub-bituminous or lignite.

How the method developed. Railroads began pumping slurry into subgrades in the 1930s, when maintenance engineers drove pipes into soft roadbed and pumped blends of sand, cement and emulsified asphalt 6 to 12 ft deep to fill ballast pockets. By the 1940s dozens of railroads used the method; one Class I railroad treated more than 1,000 miles of track between 1942 and 1955. Lime slurry, intended to react with the clay rather than fill voids, was first injected under track in 1959. Hi-rail injection units and a federal handbook (Blacklock and Lawson, 1977) made lime injection a routine yearly maintenance contract by the late 1970s. Fly ash was added from about 1978, partly because lime had become expensive and partly because lime and fly ash together set. In the early 1990s finely ground railroad cements took the practice back to void filling. Use declined after railroad consolidation, as the staff who ran injection programs moved on and maintenance budgets turned to other parts of the track. Pengelly attributes much of the doubt about the method to programs that were run without before-and-after test data, and to substandard materials, rather than to the method itself.

Choosing the slurry. Choose the material from the goal of the program.

  • Void filling. Railroad cement can be mixed in batches of about 12,000 gal without a flash set; add a mild retarder if the set comes too soon. Slag cement or masonry cement can be substituted where railroad cement is not available. Much of the past success of lime/fly ash is probably void filling, because its reaction with the soil is weaker than that of lime alone.
  • Chemical treatment of soft clay. Use a quicklime product. Slaking raises the slurry temperature, which speeds the reaction, and gives a finer particle that penetrates the clay better. Mix 2.5 to 3.0 lb of dry solids per gallon (specific gravity about 1.15 to 1.17). In a saturated subgrade, a thicker slurry lets part of the slaking take place in the ground and dries the soil further.
  • Setting the lime dose. Remold subgrade samples to the field density and moisture, treat them with slurry at trial rates, cure them and test their unconfined compressive strength. The dose that gives the needed strength, usually 1 to 2% lime by dry weight of soil and expressed in gallons per cubic foot, becomes the field target.

Under pressure the slurry follows the paths of least resistance: the shear planes, slickensides and disturbed zones of a failing subgrade, which are the zones that most need treatment. Interval timing and staging spread it further.

Injecting downstage. The rods are pushed hydraulically, and slurry is pumped through four 1/4-in. nozzles set 90° apart on the tip at intervals of about 18 in. from the top down. Each interval is pumped to the target take, or for a minimum time, or until slurry refuses through earlier holes or out of the embankment side. If slurry runs up the rod, push the rod deeper to make a seal before pumping. Keep the pressure as low as the ground allows: high pressure brings early refusal and a smaller take. Most soft subgrades accept slurry well below the pump’s upper range, and the pressure is raised only to fracture tight soil. Typical equipment is a hi-rail unit with a mast that reaches 40 ft and three rods 5 ft apart; a piston or progressive-cavity pump of about 90 gal/min at 50 to 200 psi; and an agitated slurry tank of 17,000 to 22,000 gal on a flat car in tow, which can clear for trains between holes. The operator records depth, take and time at every hole. Compare the daily totals with the target, and adjust spacing, staging or depth while the crew is still on site.

Checking the result. Repeat the CPT soundings after treatment. Where railroad cement has filled the pockets the cone may not push through, so use borings to measure moisture content and in-place strength instead. Lime results can take 6 to 9 months to appear, so schedule the after-soundings accordingly.

Table 17-S2. Field test section results after lime/fly ash injection of a clay subgrade (airfield taxiway test area, after Pengelly, Table 1)
AreaDry density (pcf)Percent of ASTM D698 maximumMoisture content (%)Field CBR at 0.1 in. penetrationField CBR at 0.2 in. penetrationLL / PI
Untreated brown and tan clay (4 tests)84.187.634.80.9 to 1.81.2 to 2.371 / 39
Lime/fly ash injected tan and brown clayey silt (3 tests)95.3104.223.424 to 2922 to 3463 / 25

Read Table 17-S2 as an indication of what injection can do to moisture and bearing, not as a design value for track. The test area was an airfield taxiway, and the treated and untreated soils were logged differently, so part of the difference may be the soil itself. The improvement is consistent with the mechanism: hydration of the injected material takes up water, the moisture content drops by about 11 points, and the bearing rises with it.

Running a program. Injection is used in two ways.

  • A single site. This is usually a site where other repairs have failed, and it justifies a full investigation first: a track study of the soils and the cause of failure, lime reactivity tests, and CPT soundings or cross trenches to measure the ballast pockets and set the target take.
  • A system-wide program. Injection is cheapest when many sites are treated under one planned contract. That needs one railroad coordinator who knows every site and orders the work to keep mobilizations down. The plan lists each site by milepost, with its injection depth, nearest siding and order of treatment. The railroad may furnish the material to the sidings, with the contractor unloading and handling it. Price the program as a lump sum for the planned sites, or on time and materials where emergency sites are likely to be added during the contract.

Worked example. Example 7.2-4 in Section 7.2.9 works through the slurry quantity needed to fill the ballast pockets in a section of track, from a CPT sounding.

Source: Blacklock, J. R. and Lawson, C. H. (1977). Handbook for Railroad Track Stabilization Using Lime Slurry Pressure Injection. FRA/ORD-77/30, Federal Railroad Administration · Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR) · Hayward Baker, Inc. Railroad Subgrade Stabilization (brochure)

Injection and grouting from the track

Cement-slurry injection and compaction grouting pump material into the ground under pressure, densifying loose soil or filling voids without excavating the track. Where poor material is shallow, remove-and-replace with engineered granular fill over a separator geotextile is still the most direct fix. Admixture stabilization, usually with Portland cement, treats soil in place, and is faster and cheaper when the soil responds well.

Drilling to place grout pipes inside a tunnel
Photo 7.2.6-3. Drilling to place grout pipes. Courtesy of Hayward Baker, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Cross-section diagram of grout pipes fanning out beneath an existing tunnel to improve soil under the structure
Photo 7.2.6-4. Example of improvement of soil under an existing structure. From Munfakh (1991).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Schematic of chemical grouting equipment injecting grout beneath a structure ahead of planned excavation
Photo 7.2.6-5. Example of chemical grouting underpinning of a structure to allow excavation without settlement of the foundation. Courtesy of Hayward Baker, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Grouting of abandoned mine voids beneath a structure
Grouting of abandoned mine voids beneath a structure
Figure 7.2-16. Rail-mounted cement-slurry injection rig.
Figure 7.2-16. Rail-mounted cement-slurry injection rig.

After Geotechnology for Railroaders Program, Module 6.2; §04–05. Full reference under Supplemental References.

Supplemental reference · Basu, Madhav and Prezzi (2009)

Ground Heave from Inclined Compaction Grouting

To grout beneath an existing foundation, the grout pipe is often inclined from outside the loaded area. The authors estimate the heave at the ground surface above an inclined compaction grout column from elastic theory, with influence factors for the column length, the depth of injection and the inclination.

  • Heave increases with inclination, steeply at first and then more slowly. For deep injection (about 10 column diameters), heave changes little once the inclination exceeds about 70° from vertical.
  • For inclinations of 10° to 30°, injecting deeper than about five grout-column diameters gives little further reduction in the maximum surface heave.
  • Heave can be estimated before work starts from the soil deformation modulus and the planned grouting parameters.

For railroad work: Compaction grouting under track is normally done with inclined holes from the shoulder or between tracks. Estimate the heave beneath the rails before grouting and set track geometry limits and monitoring intervals for the work, so that the track is not lifted out of tolerance (Chapter 5.3).

Source: Basu, Madhav and Prezzi (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Shen, Luo, Xiao and Wang (2009); Wang, Wang and Wang (2009)

Large-Diameter Jet Grouting in Soft Deposits

Double-erosion jet grouting (a rotary-jet variant) cuts the soil twice and forms very large columns. In a deep excavation in a soft coastal deposit, columns reached about 164 ft deep.

  • Column diameters ranged from about 2.6 to 10.8 ft. In soft clay they exceeded 5.9 ft and mixing was uniform.
  • In stiff silty clay the same settings produced columns smaller than 3.3 ft.
  • In sand below the water table the jet cut a wide zone, but cement and soil separated and mixing was poor.
  • 28-day unconfined strength was about 130 to 1,175 psi.
  • A companion review describes jet grouting over the past decade in the same city for foundation support and for horizontal and vertical water cutoffs, with treatment depths increasing from 65–100 ft to about 165 ft.

For railroad work: Column diameter and quality depend heavily on soil type, so specify trial columns in each soil layer and check diameter and uniformity before production. Jet-grouted cutoffs and bottom seals are relevant to deep excavations for underpasses and pump stations beside track.

Source: Shen, Luo, Xiao and Wang (2009); Wang, Wang and Wang (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Singh and Hymavathi (n.d.)

Compensation Grouting

Compensation grouting injects grout under high pressure through sleeve pipes (tubes-à-manchette) to fracture the soil deliberately. The grout fills the fractures, which open in the direction of least principal stress, and the added volume makes up for ground loss. It is used to prevent or reverse settlement of structures above tunnels and excavations, and in repeated passes can lift settled structures in a controlled way.

For railroad work: Compensation grouting can protect track over a tunnel or jacked crossing, or relevel track and structures that have settled. It needs real-time monitoring of the track and the ground during injection, with stop criteria, because grout fractures can heave the track unevenly or reach drains and culverts. Agree the target lift and allowable rates with the railroad before work starts.

Source: Singh and Hymavathi (n.d.). Full reference under Supplemental References.