Compaction grouting injects a stiff grout (slump < 2 in.) that does not penetrate soil pores but instead forms a grout bulb, displacing and densifying surrounding soils. Used for:






Grout volume per bulb:
Where D_bulb = target bulb diameter (ft); typically 1.5–2.5 ft. Injection spacing = 4–8 ft on grid; primary and secondary passes used to achieve uniform densification.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Dbulb | target bulb diameter (ft) | Design criterion | Set by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification. | typically 1.5–2.5 ft. Injection spacing = 4–8 ft on grid |
Low-viscosity grout (sodium silicate, acrylamide, or ultrafine cement) is injected under low pressure to penetrate pore spaces without disturbing soil fabric. Used in granular soils (D₁₅ > 0.025 in.) to reduce permeability or improve strength.

Groutability ratio (GR):
After Selig & Waters (1994), ch. 11. Full reference under Supplemental References.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| GR | D_15,soil D_85,grout ≥ 24 (for successful permeation) | Chart, table or correction factor | Read from the cited chart or table for the site conditions; values listed in the definition. | project-specific |
High-pressure jetting (3,000–7,000 psi) simultaneously erodes and mixes in-situ soil with cement grout, creating cylindrical treated columns. Single-fluid, double-fluid, and triple-fluid systems produce column diameters of 1.5–5.0 ft. Used by a passenger railroad for underpinning passenger corridor structures and by a Class I railroad for liquefaction mitigation under existing embankments.
Column diameter depends on the soil, the jet system and the jetting parameters (pressure, flow, lift and rotation rates), so confirm it with test columns before production.
The grouting methods above are general. The method developed specifically for railroad subgrades is slurry pressure injection from hi-rail equipment, which can clear for trains between injections. Soft fine-grained subgrade and repeated resurfacing drive ballast down into ballast pockets that trap water, cause squeezes and keep the soil weak. Injection works in two ways:

Table 17-S1. Typical injection parameters (FRA handbook, 1977, and Pengelly)
| Parameter | Typical value |
|---|---|
| Rods | Three, 5 ft apart: one on track centerline, one each side (Figure 17-S2) |
| Depth | Lime: 10–16 ft historically; most programs ≥ 20 ft; modern units 30–40 ft |
| Longitudinal spacing | About 5 ft (every second or third crib; never more than 4 crib spaces); every crib, staged, in severe distress |
| Stage interval | 18–24 in., injecting downstage (top down) to refusal or target take |
| Pump pressure | 50–250 psi (150 psi common); keep low to maximize take |
| Lime slurry | 2.5–3 lb lime per gallon of water (never > 4); SG about 1.15–1.17 |
| Quantity | 30–50 gal per track ft for a 10–16 ft lime injection (FRA); 200–250 lb dry solids per track ft typical, 150 mild to 1,000 severe (Pengelly) |
| Staging | Second or third pass 48 hr or more later into skipped cribs, e.g., deep lime pass then shallow void-filling pass |

Investigation and testing. The FRA handbook suggests about 2 + L/250 borings for L up to 1,000 ft of problem track, 6 + (L − 1,000)/300 for 1,000–4,000 ft, and 16 + (L − 4,000)/400 for 4,000–10,000 ft, with continuous Shelby tubes for 5 ft just below the ballast and borings at least 5 ft below the deepest planned injection. Lab “lime-inoculated” specimens (1% lime by dry weight, representing 5-ft centers) are compared with untreated controls in swell, consolidation and strength tests. CPT before and after injection locates ballast pockets, sets the target take and verifies improvement. Contractor case histories (a line in Iowa, every other crib, 14–40 ft; a line in Missouri, every crib to 20 ft after CPT found weak soil to 18–20 ft) used this approach. The FRA handbook itself cautions that results cannot yet be predicted reliably from lab tests and recommends a field test section before a program.

Material caution: Pengelly attributes past poor results partly to substandard fly ash and recommends only ash that reliably sets (Class C in his experience). Test every ash source for compatibility. Note that his description of the coal sources is reversed relative to ASTM C618, where Class F comes from bituminous or anthracite coal and Class C from sub-bituminous or lignite.
How the method developed. Railroads began pumping slurry into subgrades in the 1930s, when maintenance engineers drove pipes into soft roadbed and pumped blends of sand, cement and emulsified asphalt 6 to 12 ft deep to fill ballast pockets. By the 1940s dozens of railroads used the method; one Class I railroad treated more than 1,000 miles of track between 1942 and 1955. Lime slurry, intended to react with the clay rather than fill voids, was first injected under track in 1959. Hi-rail injection units and a federal handbook (Blacklock and Lawson, 1977) made lime injection a routine yearly maintenance contract by the late 1970s. Fly ash was added from about 1978, partly because lime had become expensive and partly because lime and fly ash together set. In the early 1990s finely ground railroad cements took the practice back to void filling. Use declined after railroad consolidation, as the staff who ran injection programs moved on and maintenance budgets turned to other parts of the track. Pengelly attributes much of the doubt about the method to programs that were run without before-and-after test data, and to substandard materials, rather than to the method itself.
Choosing the slurry. Choose the material from the goal of the program.
Under pressure the slurry follows the paths of least resistance: the shear planes, slickensides and disturbed zones of a failing subgrade, which are the zones that most need treatment. Interval timing and staging spread it further.
Injecting downstage. The rods are pushed hydraulically, and slurry is pumped through four 1/4-in. nozzles set 90° apart on the tip at intervals of about 18 in. from the top down. Each interval is pumped to the target take, or for a minimum time, or until slurry refuses through earlier holes or out of the embankment side. If slurry runs up the rod, push the rod deeper to make a seal before pumping. Keep the pressure as low as the ground allows: high pressure brings early refusal and a smaller take. Most soft subgrades accept slurry well below the pump’s upper range, and the pressure is raised only to fracture tight soil. Typical equipment is a hi-rail unit with a mast that reaches 40 ft and three rods 5 ft apart; a piston or progressive-cavity pump of about 90 gal/min at 50 to 200 psi; and an agitated slurry tank of 17,000 to 22,000 gal on a flat car in tow, which can clear for trains between holes. The operator records depth, take and time at every hole. Compare the daily totals with the target, and adjust spacing, staging or depth while the crew is still on site.
Checking the result. Repeat the CPT soundings after treatment. Where railroad cement has filled the pockets the cone may not push through, so use borings to measure moisture content and in-place strength instead. Lime results can take 6 to 9 months to appear, so schedule the after-soundings accordingly.
| Area | Dry density (pcf) | Percent of ASTM D698 maximum | Moisture content (%) | Field CBR at 0.1 in. penetration | Field CBR at 0.2 in. penetration | LL / PI |
|---|---|---|---|---|---|---|
| Untreated brown and tan clay (4 tests) | 84.1 | 87.6 | 34.8 | 0.9 to 1.8 | 1.2 to 2.3 | 71 / 39 |
| Lime/fly ash injected tan and brown clayey silt (3 tests) | 95.3 | 104.2 | 23.4 | 24 to 29 | 22 to 34 | 63 / 25 |
Read Table 17-S2 as an indication of what injection can do to moisture and bearing, not as a design value for track. The test area was an airfield taxiway, and the treated and untreated soils were logged differently, so part of the difference may be the soil itself. The improvement is consistent with the mechanism: hydration of the injected material takes up water, the moisture content drops by about 11 points, and the bearing rises with it.
Running a program. Injection is used in two ways.
Worked example. Example 7.2-4 in Section 7.2.9 works through the slurry quantity needed to fill the ballast pockets in a section of track, from a CPT sounding.
Source: Blacklock, J. R. and Lawson, C. H. (1977). Handbook for Railroad Track Stabilization Using Lime Slurry Pressure Injection. FRA/ORD-77/30, Federal Railroad Administration · Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR) · Hayward Baker, Inc. Railroad Subgrade Stabilization (brochure)
Cement-slurry injection and compaction grouting pump material into the ground under pressure, densifying loose soil or filling voids without excavating the track. Where poor material is shallow, remove-and-replace with engineered granular fill over a separator geotextile is still the most direct fix. Admixture stabilization, usually with Portland cement, treats soil in place, and is faster and cheaper when the soil responds well.





After Geotechnology for Railroaders Program, Module 6.2; §04–05. Full reference under Supplemental References.
Technology sheets for this method · see 7.2.16 Technology Library
To grout beneath an existing foundation, the grout pipe is often inclined from outside the loaded area. The authors estimate the heave at the ground surface above an inclined compaction grout column from elastic theory, with influence factors for the column length, the depth of injection and the inclination.
For railroad work: Compaction grouting under track is normally done with inclined holes from the shoulder or between tracks. Estimate the heave beneath the rails before grouting and set track geometry limits and monitoring intervals for the work, so that the track is not lifted out of tolerance (Chapter 5.3).
Source: Basu, Madhav and Prezzi (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.
Double-erosion jet grouting (a rotary-jet variant) cuts the soil twice and forms very large columns. In a deep excavation in a soft coastal deposit, columns reached about 164 ft deep.
For railroad work: Column diameter and quality depend heavily on soil type, so specify trial columns in each soil layer and check diameter and uniformity before production. Jet-grouted cutoffs and bottom seals are relevant to deep excavations for underpasses and pump stations beside track.
Source: Shen, Luo, Xiao and Wang (2009); Wang, Wang and Wang (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.
Compensation grouting injects grout under high pressure through sleeve pipes (tubes-à-manchette) to fracture the soil deliberately. The grout fills the fractures, which open in the direction of least principal stress, and the added volume makes up for ground loss. It is used to prevent or reverse settlement of structures above tunnels and excavations, and in repeated passes can lift settled structures in a controlled way.
For railroad work: Compensation grouting can protect track over a tunnel or jacked crossing, or relevel track and structures that have settled. It needs real-time monitoring of the track and the ground during injection, with stop criteria, because grout fractures can heave the track unevenly or reach drains and culverts. Agree the target lift and allowable rates with the railroad before work starts.
Source: Singh and Hymavathi (n.d.). Full reference under Supplemental References.