7.2.5 Deep Soil Mixing (DSM)

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel
7.2.5 Deep Soil Mixing (DSM)
7.2.5.1 Method Description

DSM mechanically blends in-situ soil with cementitious binder (Portland cement, lime, or blends) using hollow-stem augers with injection ports. The resulting soil-cement mass (referred to as a "treated mass" or "column") achieves unconfined compressive strengths of 50–300 psi depending on binder content and soil type. DSM is used for:

Cement-soil column auger and cement hopper
Cement-soil column auger and cement hopper
Exposed tops of DSM columns
Exposed tops of DSM columns
Exposed sides of DSM columns
Exposed sides of DSM columns
  • Soft clay improvement beneath railroad embankments (treated mass beneath track)
  • Liquefaction mitigation (Chapter 6.5, Example 6.5-1)
  • Lateral support walls for excavations adjacent to track
  • Embankment toe walls to prevent lateral spreading

Design unconfined compressive strength:

qu,field = flab × qu,lab

Where f_lab = field-to-laboratory strength ratio, commonly 0.2–0.5; use 0.25 for conservative preliminary design. Laboratory mix design targets q_u,lab ≥ 100 psi for soft clay treatment.

Inputs for the equations in this section (2)
SymbolWhat it isComes fromHow to get itTypical range
quintermediate value computed on this pageAnother equationComputed: q_u = f_lab × q_u,fieldproject-specific
flab0.20–0.33 (field-to-laboratory strength ratioChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
7.2.5.2 Composite Modulus for DSM Treatment

Treated mass elastic modulus:

EDSM = 150 ⋅ qu,field    to    500 ⋅ qu,field    (psi)

For q_u,field = 50–300 psi this gives about 7,500–150,000 psi. For settlement reduction using composite modulus approach:

Ecomposite = aDSM ⋅ EDSM + (1 - aDSM) ⋅ Esoil

Where a_DSM = area replacement ratio of DSM columns within the treated zone (typically 0.15–0.35 for track subgrade improvement).

Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
EDSMintermediate value computed on this pageAnother equationComputed: E_DSM = 150 ⋅ q_u,field    to    500 ⋅ q_u,field    (psi)project-specific
Ecompositesoil elastic modulus = a_DSM ⋅ E_DSM + (1 - a_DSM) ⋅ E_soilField test, lab test or correlationPressuremeter (ASTM D4719), DMT (D6635), plate load (D1196), triaxial secant modulus, or correlation with N60 or qc.loose sand 200–500, dense sand 1,000–1,700 ksf · by USCS group
aDSMarea replacement ratio of DSM columns within the treated zone (typically 0.15–0.35 for track subgrade improvement).Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.typically 0.15–0.35 for track subgrade improvement
7.2.5.3 Minimum Strength Criteria by Client
Railroadq_u,field minimum (psi)Test MethodCuring Period (days)Notes
Typical50ASTM D216628Common practice; confirm with owner

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.

Supplemental reference

Column-supported embankments (CSE) and load transfer platforms

When there is no time to preload, columns of almost any type — aggregate piers, vibro-concrete columns, DSM columns, augered or driven piles — can carry the embankment to a firm layer. SHRP2 R02 notes that the method is most economical for 15–70 ft of soft clay, peat or organic soil, and cites the Rancocas Creek Railroad Bridge approach in New Jersey (Figure 17-S3). Key points of the recommended design procedure (there is no approved FHWA method):

Completed T-Wall column-supported embankment for the Rancocas Creek railroad bridge approach, New Jersey (SHRP2 GeoTechTools).
Supplemental Figure 17-S3. Completed T-Wall column-supported embankment for the Rancocas Creek railroad bridge approach, New Jersey (SHRP2 GeoTechTools). Source: SHRP2 R02 / GeoTechTools (2012). Column-Supported Embankments — fact sheet, design guidance and photographs.
  • Design the columns to carry the entire embankment plus surcharge (commonly 250–300 psf). SHRP2 recommends an allowable post-construction settlement of 3 in.; track tolerances in Chapter 6.2 may govern tighter.
  • The embankment must exceed a critical height (below which differential settlement shows at the surface), and clear span s − a ≤ 10 ft (a = pile-cap width, or 0.886 dcol for round columns).
  • A geosynthetic-reinforced load transfer platform is typical where spacing exceeds about 5 ft. Thickness should be at least 2 ft and at least 0.5(s − a). Use select fill with φ′ ≥ 35°, graded 100% passing 4 in., 15–70% passing No. 4, 10–60% passing No. 40 and 5–15% passing No. 200, with LL < 40 and PI < 20. Place at least two reinforcement layers with 3-ft overlaps.
  • Check global stability (FS ≥ 1.5 recommended with LTPs) and lateral spreading of the reinforcement. Closely spaced aggregate columns often need no LTP.

Table 17-S3. Typical allowable column capacities (SHRP2, adapted from Elias et al., 2006)

Column typeAllowable capacity (kip)Typical length (ft)Diameter/width (in.)
Stone columns20–11010–3518–47
Geotextile-encased columns65–13510–3530–60
Rammed aggregate piers50–15010–3524–36
Augered piles75–25015–8012–24
Vibro-concrete columns100–25010–3518–24
Deep mixing columns90–27030–10024–120
Precast concrete piles90–22530–50up to 24
Steel H / pipe piles90–450 / 180–55015–100 / 30–1306–12 / 8–48
Deep mixing rig on levee, New Orleans
Deep mixing rig on levee, New Orleans
DSM batch plant and mixing rig
DSM batch plant and mixing rig
Close-up of deep soil mixing tool
Close-up of deep soil mixing tool

Source: SHRP2 R02 / GeoTechTools (2012). Column-Supported Embankments — fact sheet, design guidance and photographs

Placement of geosynthetic reinforcement for a load transfer platform over columns (SHRP2 GeoTechTools).
Supplemental Figure 17-S4. Placement of geosynthetic reinforcement for a load transfer platform over columns (SHRP2 GeoTechTools). Source: SHRP2 R02 / GeoTechTools (2012). Column-Supported Embankments — fact sheet, design guidance and photographs.

Technology sheets for this method · see 7.2.16 Technology Library

CSV installation adjacent to a sheet pile wall
Photo 7.2.5-1. CSV installation adjacent to a sheet pile wall. From the files of Jim Collin.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Top view of the CSV auger and cement hopper
Photo 7.2.5-2. Top view of the CSV auger and cement hopper. From the files of Jim Collin.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Deep mixing rig on a levee project in New Orleans, LA
Photo 7.2.5-3. Deep mixing rig on levee project in New Orleans, LA. From Trevi Icos Corporation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Batch plant and deep mixing rig
Photo 7.2.5-4. Batch plant and deep mixing rig. From Trevi Icos Corporation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Close-up view of mixing
Photo 7.2.5-5. Close-up view of mixing. From Trevi Icos Corporation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Exposed top of deep mixing columns
Photo 7.2.5-6. Exposed top of deep mixing columns. From Fudo Construction.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Exposed sides of deep mixing columns
Photo 7.2.5-7. Exposed sides of deep mixing columns. From George Filz (2010).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Supplemental reference · Madhyannapu, Puppala, Bhadriraju and Nazarian (2009)

Deep Soil Mixing to Control Swell and Shrinkage of Expansive Clay

Deep soil mixing is usually specified for strength and settlement. This study used it to stop seasonal heave and shrinkage of an expansive clay of moderate depth beneath pavements and earth structures.

  • The laboratory mix design selected a blend of 25% lime and 75% cement by weight, at about 337 lb of binder per cubic yard of soil and a water-to-binder ratio of 1.0.
  • Two instrumented test sections with surcharge fill were monitored for two years against untreated control sections.
  • Both vertical and lateral movements were smaller in the treated sections. The authors give a step-by-step design method.

For railroad work: Expansive clay subgrades cause recurring track surface and cross-level defects in dry and wet seasons (Chapter 2.5). Where the active zone is too deep for lime treatment of the top lifts (Section 7.2.7), soil-mix columns are an option for short critical lengths such as turnouts, crossings and bridge approaches.

Source: Madhyannapu, Puppala, Bhadriraju and Nazarian (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Liu, Zhang and Zhu (2009)

Checking How Well Deep-Mixed Columns Are Mixed

Strength tests alone do not show whether binder is evenly distributed through a column. The authors measured the electrical resistivity of cores, and the parameters derived from it (formation factor, shape factor and anisotropy factor), and found them direct indicators of mixing uniformity. The results agreed with SPTs on the columns and unconfined compression tests on the cores. Double-slurry mixing produced markedly more uniform columns than single-slurry mixing.

For railroad work: Add a uniformity check to deep-mixing QA for railroad work: resistivity of cores, or geophysical testing of whole columns, alongside core recovery and strength. Ask the contractor which mixing process will be used, because the process affects uniformity as much as the binder content does.

Source: Liu, Zhang and Zhu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Zheng, Liu and Chen (2009)

Composite Columns: a Concrete Core Inside a Soil-Cement Column

Column-type elements behave in three ways: granular columns (sand and stone), soil-cement columns (deep-mixed, lime and jet-grouted) and rigid piles (concrete and steel). Composite columns combine them by placing a small-diameter plain concrete, reinforced concrete or steel core in the center of a granular or soil-cement column.

  • The core gives much higher bearing and bending capacity than the soil-cement column alone, and the soil-cement shell provides side resistance.
  • A composite deep-mixed column can carry more than a bored pile of the same outside size and length, at competitive cost.
  • The extra stability allows embankments to be raised faster.

For railroad work: Composite columns fit bridge approach embankments and high fills where ordinary soil-cement columns would be too weak in bending under the side slopes (see Section 7.2.8 on lateral behavior of embankment columns), but a full pile foundation is more than the job needs.

Source: Zheng, Liu and Chen (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.